ML073270113: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(StriderTol Bot change)
 
(2 intermediate revisions by the same user not shown)
Line 19: Line 19:


==SUMMARY==
==SUMMARY==
Responsible RPBB RIV-2007-A-0048 Branch Facility Name Callaway ARB Date: April 17, 2007 Docket Number 050-483 01 Case No.: ARB DECISION Purpose of ARB Initial Previous N/A Decisions Today's Decision RPBB to inspect all 3 concerns.Basis for Another ARB REFERRAL Refer to: Criteria Reviewed?Referral Rationale 01 INVESTIGATION Priority Rationale DOL Deferral Rationale ARB PARTICIPANTS  
Responsible   RPBB       RIV-2007-A-0048 Branch Facility Name       Callaway             ARB Date:     April 17, 2007 Docket Number       050-483             01 Case No.:
(' denotes.ARB Chairman Approval)JWalker HFreeman KFuller DWhite AHowell*DChamberiain W MVasquez VGaddy MBloodgood I Information in this record was deleted in accordance with the Freedom of Informatiorn Act, exemptions  
ARB DECISION Purpose of ARB Initial Previous           N/A Decisions Today's Decision RPBB to inspect all 3 concerns.
')C S"0fA- o___ ,_o_-____se-G Iv -3cu.rift lestod InforM-8tirin CONCERNS LIST RIv-2007-A-0048 Concern (Brief Statement)
Basis for Another ARB REFERRAL Refer to:                               Criteria Reviewed?
Reulatory Requirement Branch Action (Inspect, Refer, Planned..
Referral Rationale 01 INVESTIGATION Priority Rationale DOL Deferral Rationale ARB PARTICIPANTS (' denotes.ARB Chairman Approval)
Significance 01 Prority Investigate, No Action) Completion  
JWalker             HFreeman         KFuller         DWhite           AHowell*
((High, (H, N, L)* ' Normal)1 The licensee decided, due to economic reasons, to not 10 CFR 50 App. B correct a long standing design deficiency on the RHR Criterion XVI suction relief valves' discharge piping during the spring 2007 (, refueling outage but wait until the next refueling outage. p_ _ _ _ _ _ _RPBB Inspect 5/17/07 Normal L 2 The licensee changed the RHR suction relief valve 10 CFR 50 App. B surveillance from a staggered test basis to reduce the Criterion XI probability of identifying a failed valve while the valve is in the system. This again was an economic decision.RPBB Inspect 5/17/07 Normal L 3 The licensee delayed testing RHR suction relief valve that 10 CFR 50 App. B had been previously removed. A mid-cycle outage would Criterion Xl have been required to replace the other valve if the valve had failed its test.RPBB Inspect 5/17/07 Normal L 4 5 6 Revised 5/22/02 Indirect Charaes Al 0304 Support for Allegations (Reactors)
DChamberiain       MVasquez W             VGaddy           MBloodgood     I Information in this record was deleted in accordance with the Freedom of Informatiorn se-G Iv 3cu.rift lestodInforM-8tirin Act, exemptions ')C S"0fA-       o___ ,_o_-____
Al 0191 Support for Allegations (Materials)
 
Direct Inspection Activities AF BJ2 AFT Allegation Followup Allegation Prep/Doc Allegation Travel ALLEGATION RECEIPT FORM Page 24 Received By: Michael Peck Receipt Date: April 6, 2007 Receipt Method (meeting, phone call, letter, Plant Mail -Letter etc.)FACILITY Facility Name Callaway Plant Location Fulton, Missouri Docket(s)50-483 CONCERN Summary the of Concerns (be brief)* AmerenUE deferred corrective action for a potentially significant design deficiency from the current refueling outage until the next refueling outage.This design deficiency has been a long standing problem (please see attached letter).Delay in testing RHR relief valves (removed October 2005, not tested until August 2006).*AmerenUE changed RHR relief valve surveillance from a staggered test bases to reduce the probability of identifying a failed valve.,Obtain concern specifics.
CONCERNS LIST                                                             RIv-2007-A-0048 Concern (Brief Statement)                                           Reulatory Requirement Branch   Action (Inspect, Refer,   Planned..       Significance   01 Prority Investigate, No Action)   Completion * ' Normal)          ((High, (H,N, L) 1   The licensee decided, due to economic reasons, to not               10 CFR 50 App. B correct a long standing design deficiency on the RHR                 Criterion XVI suction relief valves' discharge piping during the spring 2007               p_ (,
What Is the concern, when did It occur, who was Involved, oft. t the conoern Involves dtrimlrnation.'fll In the last section o1 the torm.The Callaway RHR suction relief and PORV discharge are routed through a common discharge line into the PRT. During operating cycle 14, the PORV lifted several times during a plant transient.
refueling outage but wait until the next refueling outage.
The PRT pressurized, lifting a column of water up the common discharge line. This water collected on the backside of the RHR relief valve. A subsequent PORV lift caused a significant water hammer against the back side of the RHR relief valve, damaging the valve internals.
RPBB      Inspect                   5/17/07         Normal         L 2   The licensee changed the RHR suction relief valve                   10 CFR 50 App. B surveillance from a staggered test basis to reduce the               Criterion XI probability of identifying a failed valve while the valve is in the system. This again was an economic decision.
The licensee's interim corrective action was to declare the RHR relief valves inoperable if the PORV should lift. AmerenUE had scheduled modification to correct the design problem this outage, but deferred the modification until the following refueling outage.What Is the potential safety impact? Is this an ongolna concern?1. Unavailability of the RHR suction relief valves for cold pressure over protection (Technical Specification 3.4.12).2. Potential loss of RHR pressure boundary -RWST drains to PRT (loss of both cold leg injection and cold leg recirculation modes of ECCS).What requlrement/reauiation governs this concern?50.50.a, ASME Code (relief valve discharge must have a drain path), 50, App B, Criteria 16, prompt corrective actions What records should the NRC review?CARS 200703254, 200609805, 200607188, Mod MP 07-0007, LER 05000483/2006-008-00 NRC Component Design Bases Inspection Report 05000483/2006009 What other Individuals could the NRC contact for Information?
RPBB     Inspect                   5/17/07         Normal         L 3   The licensee delayed testing RHR suction relief valve that           10 CFR 50 App. B had been previously removed. A mid-cycle outage would               Criterion Xl have been required to replace the other valve ifthe valve had failed its test.
RPBB     Inspect                   5/17/07         Normal         L 4
5 6
Revised 5/22/02 Indirect Charaes                                         Direct Inspection Activities Al 0304 Support for Allegations (Reactors)               AF              Allegation Followup Al 0191 Support for Allegations (Materials)             BJ2             Allegation Prep/Doc AFT              Allegation Travel
 
ALLEGATION RECEIPT FORM                                                                       Page 24 Received By:                           Michael Peck                         Receipt Date:                         April 6, 2007 Receipt Method (meeting, phone call, letter,                                                           Plant Mail - Letter etc.)
FACILITY Facility Name                                                   Callaway Plant Location                                                         Fulton, Missouri Docket(s) 50-483 CONCERN Summary the of Concerns (be brief)
* AmerenUE deferred corrective action for a potentially significant design deficiency from the current refueling outage until the next refueling outage.
This design deficiency has been a long standing problem (please see attached letter).
**                        Delay in testing RHR relief valves (removed October 2005, not tested until August 2006).
*AmerenUE                                     changed RHR relief valve surveillance from a staggered test bases to reduce the probability of identifying a failed valve.
,Obtain concern specifics. What Is the concern, when did It occur, who was Involved, oft. t the conoern Involves dtrimlrnation.'fll In the last section o1 the torm.
The Callaway RHR suction relief and PORV discharge are routed through a common discharge line into the PRT. During operating cycle 14, the PORV lifted several times during a plant transient. The PRT pressurized, lifting a column of water up the common discharge line. This water collected on the backside of the RHR relief valve. A subsequent PORV lift caused a significant water hammer against the back side of the RHR relief valve, damaging the valve internals. The licensee's interim corrective action was to declare the RHR relief valves inoperable ifthe PORV should lift. AmerenUE had scheduled modification to correct the design problem this outage, but deferred the modification until the following refueling outage.
What Is the potential safety impact? Is this an ongolna concern?
: 1. Unavailability of the RHR suction relief valves for cold pressure over protection (Technical Specification 3.4.12).
: 2. Potential loss of RHR pressure boundary - RWST drains to PRT (loss of both cold leg injection and cold leg recirculation modes of ECCS).
What requlrement/reauiation governs this concern?
50.50.a, ASME Code (relief valve discharge must have a drain path),
50, App B,Criteria 16, prompt corrective actions What records should the NRC review?
CARS 200703254, 200609805, 200607188, Mod MP 07-0007, LER 05000483/2006-008-00 NRC Component Design Bases Inspection Report 05000483/2006009 What other Individuals could the NRC contact for Information?
n/a How did the Individual find out about the concern?
n/a How did the Individual find out about the concern?
ALLEGATION RECEIPT FORM Page 25 Served on as Root Cause Team Member Was the concern brought to management's attention?
 
If so. what actions have been taken, If not, why not?Why was the concern brmuaht to the NRCs attention?
ALLEGATION RECEIPT FORM                                           Page 25 Served on as Root Cause Team Member Was the concern brought to management's attention? If so. what actions have been taken, If not, why not?
ALLEGATION RECEIPT FORM Page 26 ALLEGER INFORMATION Full Name "Redacted]
Why was the concern brmuaht to the NRCs attention?
Employer AmerenUE Mailing Address (Home) [Redacted]
 
Occupation Engineer Telephone (Daytime) odace Relationship to facility Employee (Other)Preference for method and time n/a Was the Individual advised of no of contact identity protection Referral Explain that If the concerns are referred to the licensee, that alleger's Identity will not be revealed and that the NRC will review and evaluate the thoroughness and adequacy of the licensee's response.
ALLEGATION RECEIPT FORM                                                                             Page 26 ALLEGER INFORMATION Full Name       "Redacted]                                                         Employer                                 AmerenUE Mailing Address (Home)                   [Redacted]                               Occupation                               Engineer Telephone                   (Daytime)         odace                               Relationship to facility                 Employee (Other)
Nf the concerns are an agreement state issue or the )urlsdiction of another agency, explain that we will rater the concern to the appropriate agency, and If the alleger agrees, we will provide the alleger's Identity for followup.Does the Individual object to the n/a Does the Individual object to n/a referral?
Preference for method and time                                       n/a         Was the Individual advised of             no of contact                                                                         identity protection Referral                                   Explain that If the concerns are referred to the licensee, that alleger's Identity will not be revealed and that the NRC will review and evaluate the thoroughness and adequacy of the licensee's response. Nfthe concerns are an agreement state issue or the )urlsdiction of another agency, explain that we will rater the concern to the appropriate agency, and Ifthe alleger agrees, we will provide the alleger's Identity for followup.
releasing their identity?Regulations prohibit NRC licensees (including contractors and subcontractors) from discriminating against Individuals who engage In protected activities (alleging violations of regulatory requirements, refusing to engage in practices made unlawful by statues, etc.).Does the concern involve n/a Was the Individual advised of the No discrimination?
Does the Individual object to the                           n/a                   Does the Individual object to             n/a referral?                                                                         releasing their identity?
DOL process?What was the protected activity?Yes What adverse actions have been taken? When?n/a Why does the individual believe the actions were taken as a result of en-,aging in a protected activit?Revised 9/3/0.
Regulations prohibit NRC licensees (including contractors and subcontractors) from discriminating against Individuals who engage In protected activities (alleging violations of regulatory requirements, refusing to engage in practices made unlawful by statues, etc.).
April 5, 2007 Michael Peck Nuclear Regulatory Commission Senior Resident Inspector Callaway Plant Mr. Peck The Primary Relief Tank Common Relief Valve Discharge Header at Callaway Plant is not properly designed:
Does the concern involve                                             n/a         Was the Individual advised of the         No discrimination?                                                                   DOL process?
the arrangement of the piping permits the RHR Suction Relief Valves to be damaged by a water slug propelled down the pipe when a Pressurizer PORV is actuated at Normal Operating Pressure.Callaway Plant management has known about this liability since September 22, 2006.The liability was formally documente Cause doio-CAR-z206071 88 in October 2006. 1 was the b)(7)c b)(7)c I 1ln October 2006 b)(7)c e anager of Desig ngineenng (then Fadi Diya) that the piping arrangement was inadequate and needed to be corrected at the next opportunity (Refueling Outage 15).After questioning the Root Cause Team's findings for three months, Callaway Plant approved Modification Package MP 07-0007 on January 26, 2007. 1 learned late in the evening on April 3 that MP 07-0007 has been removed from RF15.Ogb)(7)C the Manager of Design Engineering (now Mark McLathlan) b)(7 .. ecision to not modify the PRT Common Relief Valve Discharge eader dumrig RF15 might not be viewed favorably by the NRC. Mr. McLachlan's response was that it was not the NRC's decision as to whether or not we performed the modification.
What was the protected activity?
Callaway Plant had evaluaed the Operability of the system with an Operability Determination and could decide to defer the modification based on a Probabilistic Risk Assessment.
Yes What adverse actions have been taken? When?
If the NRC disagreed with our decisions, they could challenge our decisions during their routine or special inspections.
n/a Why does the individual believe the actions were taken as a result of en-,aging in a protected activit?
I was directed to CARS 200609805, Action 13 for the justification.
Revised 9/3/0.
CARS 200609805, Action 13 states: There were no instances where the set pressure of a relief was lowered, so loss of inventory from low pressure actuation is not considered credible.I'am not satisfied that a low pressure actuation is not considered credible.
 
The-events of February 11, 2004 caused the assembly pins of these valves to break into many pieces.With assembly pin fragments (FME) present as the bellows assembly is moving up and/V -AW-4 0 q9 1 down due to the water hammer transient on the PRT Common Relief Discharge Header, I believe it is credible that an assembly pin fragment might lodge in such a manner that the full spring for'ce is no longer applied to the center of the disk. With metal FME present along wi'tAl movement, many things are credible."b)(7)c o neeIms were documented in CARS 200703254, Inadequate LTs 0 1 ction to Safety Related System one cycle. CARS 200703254 was screened a Sig 4 (Corrective Action Only) meaning no investigation of the inadequacy of the CARS 200609805, Action 13 response nor any investigation of the inadequacy of our PI&R and modification processes is necessary.
April 5, 2007 Michael Peck Nuclear Regulatory Commission Senior Resident Inspector Callaway Plant Mr. Peck The Primary Relief Tank Common Relief Valve Discharge Header at Callaway Plant is not properly designed: the arrangement of the piping permits the RHR Suction Relief Valves to be damaged by a water slug propelled down the pipe when a Pressurizer PORV is actuated at Normal Operating Pressure.
Note that Callaway Plant has had many opportunities to discover and corrept the. design deficiencies of the PRT Common Relief Valve Discharge Header: In 1993, while pressurizing the RCS to start Reactor Coolant Pumps fbr the RF6 heatup, a RHR Suction Relief Valve lifted at 350 psig (more than 100 psi below its setpoint), causing RCS pressure to blowdown to approximately 100 psig. This valve was installed in the system during the February 13, 1989: Safety Injection and had not passed a surveillance lift since that time ýevery time it was tested it needed to be adjusted).
Callaway Plant management has known about this liability since September 22, 2006.
When the valve was disassembled in 1994, the assembly pin was found broken in five pieces. An inadequate PI&R failed to determine the cause of the valve failure and closed the issue stating: "Based on past history and the design of the valve, this incident is considered an isolated case."* Contrary to good engineering practice, the RHR Suction Relief valve surveillances are not performed on a staggered test basis. Performing these surveillances on a staggered test basis would have, resulted in the removal and testing of one of the valves damaged in the 2004 Safety Injection an entire cycle earlier., The valves removed in October 2005 were not tested until August 2006. It is not understood why this 10 month delay was necessary.
The liability was formally documente doio-CAR-z206071 Cause                          88 in October 2006. 1was the b)(7)c                         b)(7)c       I         1ln October 2006 b)(7)c                     e anager of Desig ngineenng (then Fadi Diya) that the piping arrangement was inadequate and needed to be corrected at the next opportunity (Refueling Outage 15).
After questioning the Root Cause Team's findings for three months, Callaway Plant approved Modification Package MP 07-0007 on January 26, 2007. 1 learned late in the evening on April 3 that MP 07-0007 has been removed from RF15.
Ogb)(7)C                       the Manager of Design Engineering (now Mark McLathlan) b)(7           .. ecision to not modify the PRT Common Relief Valve Discharge eader dumrig RF15 might not be viewed favorably by the NRC. Mr. McLachlan's response was that it was not the NRC's decision as to whether or not we performed the modification. Callaway Plant had evaluaed the Operability of the system with an Operability Determination and could decide to defer the modification based on a Probabilistic Risk Assessment. If the NRC disagreed with our decisions, they could challenge our decisions during their routine or special inspections. I was directed to CARS 200609805, Action 13 for the justification.
CARS 200609805, Action 13 states:
There were no instances where the set pressure of a relief was lowered, so loss of inventory from low pressure actuation is not considered credible.
I'am not satisfied that a low pressure actuation is not considered credible. The-events of February 11, 2004 caused the assembly pins of these valves to break into many pieces.
With assembly pin fragments (FME) present as the bellows assembly is moving up and
                                          /V-AW-4           0 q9 1
 
down due to the water hammer transient on the PRT Common Relief Discharge Header, I believe it is credible that an assembly pin fragment might lodge in such a manner that the full spring for'ce is no longer applied to the center of the disk. With metal FME present along wi'tAl b*liows movement, many things are credible.
  "b)(7)c                 o   neeIms were documented in CARS 200703254, Inadequate LTs                 0 1 ction to Safety Related System one cycle. CARS 200703254 was screened a Sig 4 (Corrective Action Only) meaning no investigation of the inadequacy of the CARS 200609805, Action 13 response nor any investigation of the inadequacy of our PI&R and modification processes is necessary.
Note that Callaway Plant has had many opportunities to discover and corrept the. design deficiencies of the PRT Common Relief Valve Discharge Header:
In 1993, while pressurizing the RCS to start Reactor Coolant Pumps fbr the RF6 heatup, a RHR Suction Relief Valve lifted at 350 psig (more than 100 psi below its setpoint), causing RCS pressure to blowdown to approximately 100 psig. This valve was installed in the system during the February 13, 1989: Safety Injection and had not passed a surveillance lift since that time ýevery time it was tested it needed to be adjusted). When the valve was disassembled in 1994, the assembly pin was found broken in five pieces. An inadequate PI&R failed to determine the cause of the valve failure and closed the issue stating: "Based on past history and the design of the valve, this incident is considered an isolated case."
* Contrary to good engineering practice, the RHR Suction Relief valve surveillances are not performed on a staggered test basis. Performing these surveillances on a staggered test basis would have, resulted in the removal and testing of one of the valves damaged in the 2004 Safety Injection an entire cycle earlier.
        , The valves removed in October 2005 were not tested until August 2006. It is not understood why this 10 month delay was necessary.
Instead of suffering for having an inadequate PI&R process, Callaway Plant benefits from it. Had one~of the damaged valves been removed in RF13 and failed its bench test during cycle 14, Callaway Plant may have been forced into a mid-cycle outage to replace the other valve. Had the valves removed in RFI 4 been bench tested earlier in the cyclei Callaway Plant may have been expected to makemore of an effort to correct the design deficiencies of the PRT Common Relief Valve Discharge Header during RFI 5, incurring unbudgeted expenditures.
Instead of suffering for having an inadequate PI&R process, Callaway Plant benefits from it. Had one~of the damaged valves been removed in RF13 and failed its bench test during cycle 14, Callaway Plant may have been forced into a mid-cycle outage to replace the other valve. Had the valves removed in RFI 4 been bench tested earlier in the cyclei Callaway Plant may have been expected to makemore of an effort to correct the design deficiencies of the PRT Common Relief Valve Discharge Header during RFI 5, incurring unbudgeted expenditures.
It appears Callaway Plant has made a sound business decision.
It appears Callaway Plant has made a sound business decision. Delaying exit from RF1 5 potentially costs Ameren $1 million/day in lost generation. Due to our procrastination mad inadequate decision making, MP 07-0007 could delay our exit from RF1 5 were we to attempt to perform itJduring this outage. We have once again decided that it is worth the regulatory risk to not do the right thing (correct known deficiencies with safety related equipment). This is a sound business decision because if the NRC were: to challenge our response to CARS 200609805, Action 13, and if the NRC were to issue a finding and fine 2
Delaying exit from RF1 5 potentially costs Ameren $1 million/day in lost generation.
 
Due to our procrastination mad inadequate decision making, MP 07-0007 could delay our exit from RF1 5 were we to attempt to perform itJduring this outage. We have once again decided that it is worth the regulatory risk to not do the right thing (correct known deficiencies with safety related equipment).
due tO inadequate technical rigor in our response, it is extremely unlikely the amount of the fine the NRC could level would -be any comparison to the loss generation the company could suffer by delaying its exit from RFI5.
This is a sound business decision because if the NRC were: to challenge our response to CARS 200609805, Action 13, and if the NRC were to issue a finding and fine 2 due tO inadequate technical rigor in our response, it is extremely unlikely the amount of the fine the NRC could level would -be any comparison to the loss generation the company could suffer by delaying its exit from RFI5.Another item of note is the response to CARS 200607188, Action. 11.4. This action requested the surveillance frequency for testing the RHR Suction Relief Valves be performed on a staggered test basis. The response clearly indicates the reason the company does not wish to perform the surveillance on a staggered test basis is because we would be better off not knowing of a potential problem with the other train's valve until the valve is no longer in the system and current (vice past) operability is no longer an issue. Again, based on the limited regulatory fallout from having no opemble.RHR Suction Relief Valves and no operable (for COMS) PORVs for morelthan anmentire fuel cycle, theyrefusal to perform these surveillances on a staggered test basis appears to be a sound business decision.I have attempted to address the inadequacy of the PRT Common i .ar with my management through sever m hods: b)(7)c or AR b)()L in.Z o er2006, b)(7)- NIr. ...er an esi en ineer: for MP .07-0007 ou nter mo b)(7)c b)() r. McLachlan b)(7)c ARS 254. allaway Plant. managment  
Another item of note is the response to CARS 200607188, Action. 11.4. This action requested the surveillance frequency for testing the RHR Suction Relief Valves be performed on a staggered test basis. The response clearly indicates the reason the company does not wish to perform the surveillance on a staggered test basis is because we would be better off not knowing of a potential problem with the other train's valve until the valve is no longer in the system and current (vice past) operability is no longer an issue. Again, based on the limited regulatory fallout from having no opemble.RHR Suction Relief Valves and no operable (for COMS) PORVs for morelthan anmentire fuel cycle, theyrefusal to perform these surveillances on a staggered test basis appears to be a sound business decision.
.e *eves it is doing e n t thing in-delaying MP 07-0007 until R-F16. I would like verification freim the NRC that they agree with Callaway's actions. I recognize the'NRC has 30 days to respond to me. If possible, I would like an answer before the plant is next in MODE 5 -ascending (currently scheduled for April 20,2007).Please contact me a f you have any questions regarding this issue.Thank you,.3}}
I have attempted to address the inadequacy of the PRT Common i .arwith my management through sever m hods: b)(7)c or AR       b)()L                               in.Z o er2006, b)(7)-             NIr. . er an       esi     en ineer: for MP .07-0007 ou             nter mo     b)(7)c       b)()           r. McLachlan b)(7)c ARS         254. allaway Plant. managment         .
e *eves it is doing e n t thing in-delaying MP 07-0007 until R-F16. I would like verification freim the NRC that they agree with Callaway's actions. I recognize the'NRC has 30 days to respond to me. If possible, I would like an answer before the plant is next in MODE 5 - ascending (currently scheduled for April 20,2007).
Please contact me a                     f you have any questions regarding this issue.
Thank you,.
3}}

Latest revision as of 15:15, 22 March 2020

ARB Summary, RIV-2007-A-0048 for Callaway
ML073270113
Person / Time
Site: Callaway Ameren icon.png
Issue date: 04/17/2007
From:
NRC Region 4
To:
References
RIV-2007-A-0048, FOIA/PA-2008-0011
Download: ML073270113 (8)


Text

ARB

SUMMARY

Responsible RPBB RIV-2007-A-0048 Branch Facility Name Callaway ARB Date: April 17, 2007 Docket Number 050-483 01 Case No.:

ARB DECISION Purpose of ARB Initial Previous N/A Decisions Today's Decision RPBB to inspect all 3 concerns.

Basis for Another ARB REFERRAL Refer to: Criteria Reviewed?

Referral Rationale 01 INVESTIGATION Priority Rationale DOL Deferral Rationale ARB PARTICIPANTS (' denotes.ARB Chairman Approval)

JWalker HFreeman KFuller DWhite AHowell*

DChamberiain MVasquez W VGaddy MBloodgood I Information in this record was deleted in accordance with the Freedom of Informatiorn se-G Iv 3cu.rift lestodInforM-8tirin Act, exemptions ')C S"0fA- o___ ,_o_-____

CONCERNS LIST RIv-2007-A-0048 Concern (Brief Statement) Reulatory Requirement Branch Action (Inspect, Refer, Planned.. Significance 01 Prority Investigate, No Action) Completion * ' Normal) ((High, (H,N, L) 1 The licensee decided, due to economic reasons, to not 10 CFR 50 App. B correct a long standing design deficiency on the RHR Criterion XVI suction relief valves' discharge piping during the spring 2007 p_ (,

refueling outage but wait until the next refueling outage.

RPBB Inspect 5/17/07 Normal L 2 The licensee changed the RHR suction relief valve 10 CFR 50 App. B surveillance from a staggered test basis to reduce the Criterion XI probability of identifying a failed valve while the valve is in the system. This again was an economic decision.

RPBB Inspect 5/17/07 Normal L 3 The licensee delayed testing RHR suction relief valve that 10 CFR 50 App. B had been previously removed. A mid-cycle outage would Criterion Xl have been required to replace the other valve ifthe valve had failed its test.

RPBB Inspect 5/17/07 Normal L 4

5 6

Revised 5/22/02 Indirect Charaes Direct Inspection Activities Al 0304 Support for Allegations (Reactors) AF Allegation Followup Al 0191 Support for Allegations (Materials) BJ2 Allegation Prep/Doc AFT Allegation Travel

ALLEGATION RECEIPT FORM Page 24 Received By: Michael Peck Receipt Date: April 6, 2007 Receipt Method (meeting, phone call, letter, Plant Mail - Letter etc.)

FACILITY Facility Name Callaway Plant Location Fulton, Missouri Docket(s) 50-483 CONCERN Summary the of Concerns (be brief)

  • AmerenUE deferred corrective action for a potentially significant design deficiency from the current refueling outage until the next refueling outage.

This design deficiency has been a long standing problem (please see attached letter).

    • Delay in testing RHR relief valves (removed October 2005, not tested until August 2006).
  • AmerenUE changed RHR relief valve surveillance from a staggered test bases to reduce the probability of identifying a failed valve.

,Obtain concern specifics. What Is the concern, when did It occur, who was Involved, oft. t the conoern Involves dtrimlrnation.'fll In the last section o1 the torm.

The Callaway RHR suction relief and PORV discharge are routed through a common discharge line into the PRT. During operating cycle 14, the PORV lifted several times during a plant transient. The PRT pressurized, lifting a column of water up the common discharge line. This water collected on the backside of the RHR relief valve. A subsequent PORV lift caused a significant water hammer against the back side of the RHR relief valve, damaging the valve internals. The licensee's interim corrective action was to declare the RHR relief valves inoperable ifthe PORV should lift. AmerenUE had scheduled modification to correct the design problem this outage, but deferred the modification until the following refueling outage.

What Is the potential safety impact? Is this an ongolna concern?

1. Unavailability of the RHR suction relief valves for cold pressure over protection (Technical Specification 3.4.12).
2. Potential loss of RHR pressure boundary - RWST drains to PRT (loss of both cold leg injection and cold leg recirculation modes of ECCS).

What requlrement/reauiation governs this concern?

50.50.a, ASME Code (relief valve discharge must have a drain path),

50, App B,Criteria 16, prompt corrective actions What records should the NRC review?

CARS 200703254, 200609805, 200607188, Mod MP 07-0007, LER 05000483/2006-008-00 NRC Component Design Bases Inspection Report 05000483/2006009 What other Individuals could the NRC contact for Information?

n/a How did the Individual find out about the concern?

ALLEGATION RECEIPT FORM Page 25 Served on as Root Cause Team Member Was the concern brought to management's attention? If so. what actions have been taken, If not, why not?

Why was the concern brmuaht to the NRCs attention?

ALLEGATION RECEIPT FORM Page 26 ALLEGER INFORMATION Full Name "Redacted] Employer AmerenUE Mailing Address (Home) [Redacted] Occupation Engineer Telephone (Daytime) odace Relationship to facility Employee (Other)

Preference for method and time n/a Was the Individual advised of no of contact identity protection Referral Explain that If the concerns are referred to the licensee, that alleger's Identity will not be revealed and that the NRC will review and evaluate the thoroughness and adequacy of the licensee's response. Nfthe concerns are an agreement state issue or the )urlsdiction of another agency, explain that we will rater the concern to the appropriate agency, and Ifthe alleger agrees, we will provide the alleger's Identity for followup.

Does the Individual object to the n/a Does the Individual object to n/a referral? releasing their identity?

Regulations prohibit NRC licensees (including contractors and subcontractors) from discriminating against Individuals who engage In protected activities (alleging violations of regulatory requirements, refusing to engage in practices made unlawful by statues, etc.).

Does the concern involve n/a Was the Individual advised of the No discrimination? DOL process?

What was the protected activity?

Yes What adverse actions have been taken? When?

n/a Why does the individual believe the actions were taken as a result of en-,aging in a protected activit?

Revised 9/3/0.

April 5, 2007 Michael Peck Nuclear Regulatory Commission Senior Resident Inspector Callaway Plant Mr. Peck The Primary Relief Tank Common Relief Valve Discharge Header at Callaway Plant is not properly designed: the arrangement of the piping permits the RHR Suction Relief Valves to be damaged by a water slug propelled down the pipe when a Pressurizer PORV is actuated at Normal Operating Pressure.

Callaway Plant management has known about this liability since September 22, 2006.

The liability was formally documente doio-CAR-z206071 Cause 88 in October 2006. 1was the b)(7)c b)(7)c I 1ln October 2006 b)(7)c e anager of Desig ngineenng (then Fadi Diya) that the piping arrangement was inadequate and needed to be corrected at the next opportunity (Refueling Outage 15).

After questioning the Root Cause Team's findings for three months, Callaway Plant approved Modification Package MP 07-0007 on January 26, 2007. 1 learned late in the evening on April 3 that MP 07-0007 has been removed from RF15.

Ogb)(7)C the Manager of Design Engineering (now Mark McLathlan) b)(7 .. ecision to not modify the PRT Common Relief Valve Discharge eader dumrig RF15 might not be viewed favorably by the NRC. Mr. McLachlan's response was that it was not the NRC's decision as to whether or not we performed the modification. Callaway Plant had evaluaed the Operability of the system with an Operability Determination and could decide to defer the modification based on a Probabilistic Risk Assessment. If the NRC disagreed with our decisions, they could challenge our decisions during their routine or special inspections. I was directed to CARS 200609805, Action 13 for the justification.

CARS 200609805, Action 13 states:

There were no instances where the set pressure of a relief was lowered, so loss of inventory from low pressure actuation is not considered credible.

I'am not satisfied that a low pressure actuation is not considered credible. The-events of February 11, 2004 caused the assembly pins of these valves to break into many pieces.

With assembly pin fragments (FME) present as the bellows assembly is moving up and

/V-AW-4 0 q9 1

down due to the water hammer transient on the PRT Common Relief Discharge Header, I believe it is credible that an assembly pin fragment might lodge in such a manner that the full spring for'ce is no longer applied to the center of the disk. With metal FME present along wi'tAl b*liows movement, many things are credible.

"b)(7)c o neeIms were documented in CARS 200703254, Inadequate LTs 0 1 ction to Safety Related System one cycle. CARS 200703254 was screened a Sig 4 (Corrective Action Only) meaning no investigation of the inadequacy of the CARS 200609805, Action 13 response nor any investigation of the inadequacy of our PI&R and modification processes is necessary.

Note that Callaway Plant has had many opportunities to discover and corrept the. design deficiencies of the PRT Common Relief Valve Discharge Header:

In 1993, while pressurizing the RCS to start Reactor Coolant Pumps fbr the RF6 heatup, a RHR Suction Relief Valve lifted at 350 psig (more than 100 psi below its setpoint), causing RCS pressure to blowdown to approximately 100 psig. This valve was installed in the system during the February 13, 1989: Safety Injection and had not passed a surveillance lift since that time ýevery time it was tested it needed to be adjusted). When the valve was disassembled in 1994, the assembly pin was found broken in five pieces. An inadequate PI&R failed to determine the cause of the valve failure and closed the issue stating: "Based on past history and the design of the valve, this incident is considered an isolated case."

  • Contrary to good engineering practice, the RHR Suction Relief valve surveillances are not performed on a staggered test basis. Performing these surveillances on a staggered test basis would have, resulted in the removal and testing of one of the valves damaged in the 2004 Safety Injection an entire cycle earlier.

, The valves removed in October 2005 were not tested until August 2006. It is not understood why this 10 month delay was necessary.

Instead of suffering for having an inadequate PI&R process, Callaway Plant benefits from it. Had one~of the damaged valves been removed in RF13 and failed its bench test during cycle 14, Callaway Plant may have been forced into a mid-cycle outage to replace the other valve. Had the valves removed in RFI 4 been bench tested earlier in the cyclei Callaway Plant may have been expected to makemore of an effort to correct the design deficiencies of the PRT Common Relief Valve Discharge Header during RFI 5, incurring unbudgeted expenditures.

It appears Callaway Plant has made a sound business decision. Delaying exit from RF1 5 potentially costs Ameren $1 million/day in lost generation. Due to our procrastination mad inadequate decision making, MP 07-0007 could delay our exit from RF1 5 were we to attempt to perform itJduring this outage. We have once again decided that it is worth the regulatory risk to not do the right thing (correct known deficiencies with safety related equipment). This is a sound business decision because if the NRC were: to challenge our response to CARS 200609805, Action 13, and if the NRC were to issue a finding and fine 2

due tO inadequate technical rigor in our response, it is extremely unlikely the amount of the fine the NRC could level would -be any comparison to the loss generation the company could suffer by delaying its exit from RFI5.

Another item of note is the response to CARS 200607188, Action. 11.4. This action requested the surveillance frequency for testing the RHR Suction Relief Valves be performed on a staggered test basis. The response clearly indicates the reason the company does not wish to perform the surveillance on a staggered test basis is because we would be better off not knowing of a potential problem with the other train's valve until the valve is no longer in the system and current (vice past) operability is no longer an issue. Again, based on the limited regulatory fallout from having no opemble.RHR Suction Relief Valves and no operable (for COMS) PORVs for morelthan anmentire fuel cycle, theyrefusal to perform these surveillances on a staggered test basis appears to be a sound business decision.

I have attempted to address the inadequacy of the PRT Common i .arwith my management through sever m hods: b)(7)c or AR b)()L in.Z o er2006, b)(7)- NIr. . er an esi en ineer: for MP .07-0007 ou nter mo b)(7)c b)() r. McLachlan b)(7)c ARS 254. allaway Plant. managment .

e *eves it is doing e n t thing in-delaying MP 07-0007 until R-F16. I would like verification freim the NRC that they agree with Callaway's actions. I recognize the'NRC has 30 days to respond to me. If possible, I would like an answer before the plant is next in MODE 5 - ascending (currently scheduled for April 20,2007).

Please contact me a f you have any questions regarding this issue.

Thank you,.

3