{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 11, 2012
Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville, IL  60555
==SUBJECT:==
QUAD CITIES NUCLEAR POWER STATION REQUEST FOR INFORMATION FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL
==Dear Mr. Pacilio:==
On October 22, 2012, the U.S. Nuclear Regulatory Commission (NRC) will begin a Post-Approval Site Inspection for License Renewal at your Quad Cities Nuclear Power Station.
This inspection will be performed in accordance with NRC Inspection Procedure (IP) 71003.
This inspection will focus on verifying that license conditions added as part of your renewed license and a sample of license renewal commitments have been implemented. In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for the inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector. The information request has been divided into two groups:
* The first group lists information necessary for our initial inspection scoping and in-office preparation activities. During the in-office preparation activities, the team will identify as much as possible the information and activities to be reviewed during the inspection. This information should be provided to the lead inspector by October 4, 2012.
* The second group includes the additional information required for the team to review selected activities. This information should be available to the team onsite October 22, 2012. It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated. The lead inspector for this inspection is Caroline Tilton. We understand that our licensing contact for this inspection is Mr. Mark Wagner of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact the lead inspector at (630) 829-9718 or via e-mail at Caroline.Tilton@nrc.gov.
M. Pacilio    This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Offi ce of Management and Budget control number. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Record s System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,  /RA/
Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety
Docket Nos. 50-254; 50-265 License No. DPR-29; DPR-30
==Enclosure:==
Post-Approval Site Inspection  for License Renewal for Request for Information cc w/encl: Distribution via ListServŽ POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL  REQUEST FOR INFORMATION 1 Enclosure Inspection Report
:  05000254/2012007(DRS); 05000265/2012007 Inspection Dates
:  October 22, 2012 - November 9, 2012 Inspection Procedure
:  Inspection Procedure (IP) 71003 "Post-Approval Site Inspection for License Renewal" Lead Inspector
:  Caroline Tilton, Lead Inspector (630) 829-9718 Caroline.Tilton@nrc.gov I. Information Requested Prior to the On-site Inspection Week on October 4, 2012 The following information is requested by October 4, 2012, or sooner, to facilitate inspection preparation. If you have any questions regarding this information, please call the team leader as soon as possible.  (Please provide the information electronically in "pdf" files, Excel, or other searchable formats, preferably on some portable electronic media (e.g., CDROM, DVD, flash drive, etc.). The portable electronic media should be identified by unit, contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in "lists" should contain enough information to be easily understood by someone who has knowledge of light water reactor technology). 1. Provide a list of your license renewal commitments with an approximate completion status of each. 2. Provide a list of your Aging Management Programs (AMPs), copies of the program basis documents for each, and a listing of the action tracking items for each. 3. For AMPs that are one-time inspection programs, provide a list of completed work order numbers for inspections that have been completed. This may be incorporated with the previous item and should include identification of the inspected component. 4. Provide current management and license renewal organizational charts. 5. Provide electronic copies of Updated Final Safety Analysis Report, Technical Specifications, Technical Specifications Bases, and Technical Requirements
Manual. 6. Provide copies of any internal/external self-assessments and associated corrective action documents generated in preparation for the inspection.
POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL  REQUEST FOR INFORMATION 2 Enclosure II. Information Requested to be Available When the Inspectors Arrive On-Site on October 22, 2012  1. Documentation demonstrating completion of license renewal commitments completed as of the inspection date. For example, this may be in the form of a binder for each commitment which includes the implementing documentation and references. III. Information Requested to be Provided Throughout the Inspection 1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection. 2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member). If you have questions regarding the information requested, please contact the lead inspector.
M. Pacilio   
This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Offi ce of Management and Budget control number. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Record s System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
/RA/
Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-254; 50-265 License No. DPR-29; DPR-30
==Enclosure:==
Post-Approval Site Inspection  for License Renewal for Request for Information cc w/encl: Distribution via ListServŽ
DISTRIBUTION
: See next page
DOCUMENT NAME:  Ltr  06-11-12 Quad Cities LR Request for Information CET.docx Publicly Available  Non-Publicly Available Sensitive  Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII  RIII  RIII  RIII NAME CTilton:ls AMStone  DATE 05/31/12 06/11/12  OFFICIAL RECORD COPY
Letter to Mr. Michael J. Pacilio from Ms. Ann Marie Stone dated June 11, 2012.
==SUBJECT:==
QUAD CITIES NUCLEAR POWER STATION REQUEST FOR INFORMATION FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL DISTRIBUTION
: Michael McCoppin 
RidsNrrDorlLpl3-2 Resource
RidsNrrPMQuadCities Resource
RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Jared Heck
Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak}}

Revision as of 12:13, 28 July 2018

Ltr 06/11/12 Quad Cities Nuclear Power Station Request for Information for an NRC Post-Approval Site Inspection for License Renewal
ML12164A326
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 06/11/2012
From: Stone A M
NRC/RGN-III/DRS/EB2
To: Pacilio M J
Exelon Generation Co, Exelon Nuclear
References
Download: ML12164A326 (6)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE ROAD, SUITE 210 LISLE, IL 60532-4352 June 11, 2012

Mr. Michael J. Pacilio Senior Vice President, Exelon Generation Company, LLC President and Chief Nuclear Officer (CNO), Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

QUAD CITIES NUCLEAR POWER STATION REQUEST FOR INFORMATION FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL

Dear Mr. Pacilio:

On October 22, 2012, the U.S. Nuclear Regulatory Commission (NRC) will begin a Post-Approval Site Inspection for License Renewal at your Quad Cities Nuclear Power Station.

This inspection will be performed in accordance with NRC Inspection Procedure (IP) 71003.

This inspection will focus on verifying that license conditions added as part of your renewed license and a sample of license renewal commitments have been implemented. In order to minimize the inspection impact on the site and to ensure a productive inspection for both parties, we have enclosed a request for information needed for the inspection. It is important that all of these documents are up to date and complete in order to minimize the number of additional documents requested during the preparation and/or the on-site portions of the inspection. Insofar as possible, this information should be provided electronically to the lead inspector. The information request has been divided into two groups:

  • The first group lists information necessary for our initial inspection scoping and in-office preparation activities. During the in-office preparation activities, the team will identify as much as possible the information and activities to be reviewed during the inspection. This information should be provided to the lead inspector by October 4, 2012.
  • The second group includes the additional information required for the team to review selected activities. This information should be available to the team onsite October 22, 2012. It is also requested that corrective action documents and/or questions developed during the inspection be provided to the lead inspector as the documents are generated. The lead inspector for this inspection is Caroline Tilton. We understand that our licensing contact for this inspection is Mr. Mark Wagner of your organization. If there are any questions about the inspection or the material requested in the enclosure, please contact the lead inspector at (630) 829-9718 or via e-mail at Caroline.Tilton@nrc.gov.

M. Pacilio This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Offi ce of Management and Budget control number. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Record s System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely, /RA/

Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety

Docket Nos. 50-254; 50-265 License No. DPR-29; DPR-30

Enclosure:

Post-Approval Site Inspection for License Renewal for Request for Information cc w/encl: Distribution via ListServŽ POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL REQUEST FOR INFORMATION 1 Enclosure Inspection Report : 05000254/2012007(DRS); 05000265/2012007 Inspection Dates

October 22, 2012 - November 9, 2012 Inspection Procedure
Inspection Procedure (IP) 71003 "Post-Approval Site Inspection for License Renewal" Lead Inspector
Caroline Tilton, Lead Inspector (630) 829-9718 Caroline.Tilton@nrc.gov I. Information Requested Prior to the On-site Inspection Week on October 4, 2012 The following information is requested by October 4, 2012, or sooner, to facilitate inspection preparation. If you have any questions regarding this information, please call the team leader as soon as possible. (Please provide the information electronically in "pdf" files, Excel, or other searchable formats, preferably on some portable electronic media (e.g., CDROM, DVD, flash drive, etc.). The portable electronic media should be identified by unit, contain descriptive names, and be indexed and hyperlinked to facilitate ease of use. Information in "lists" should contain enough information to be easily understood by someone who has knowledge of light water reactor technology). 1. Provide a list of your license renewal commitments with an approximate completion status of each. 2. Provide a list of your Aging Management Programs (AMPs), copies of the program basis documents for each, and a listing of the action tracking items for each. 3. For AMPs that are one-time inspection programs, provide a list of completed work order numbers for inspections that have been completed. This may be incorporated with the previous item and should include identification of the inspected component. 4. Provide current management and license renewal organizational charts. 5. Provide electronic copies of Updated Final Safety Analysis Report, Technical Specifications, Technical Specifications Bases, and Technical Requirements

Manual. 6. Provide copies of any internal/external self-assessments and associated corrective action documents generated in preparation for the inspection.

POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL REQUEST FOR INFORMATION 2 Enclosure II. Information Requested to be Available When the Inspectors Arrive On-Site on October 22, 2012 1. Documentation demonstrating completion of license renewal commitments completed as of the inspection date. For example, this may be in the form of a binder for each commitment which includes the implementing documentation and references. III. Information Requested to be Provided Throughout the Inspection 1. Copies of any corrective action documents generated as a result of the team's questions or queries during this inspection. 2. Copies of the list of questions submitted by the team members and the status/resolution of the information requested (provide daily during the inspection to each team member). If you have questions regarding the information requested, please contact the lead inspector.

M. Pacilio

This letter does not contain new or amended information collection requirements subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). Existing information collection requirements were approved by the Office of Management and Budget, Control Number 3150-0011. The NRC may not conduct or sponsor, and a person is not required to respond to, a request for information or an information collection requirement unless the requesting document displays a currently valid Offi ce of Management and Budget control number. In accordance with 10 CFR 2.390 of the NRC's "Rules of Practice," a copy of this letter and its enclosure will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Record s System (PARS) component of NRC's Agencywide Documents Access and Management System (ADAMS), accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Ann Marie Stone, Chief Engineering Branch 2 Division of Reactor Safety Docket Nos. 50-254; 50-265 License No. DPR-29; DPR-30

Enclosure:

Post-Approval Site Inspection for License Renewal for Request for Information cc w/encl: Distribution via ListServŽ

DISTRIBUTION

See next page

DOCUMENT NAME: Ltr 06-11-12 Quad Cities LR Request for Information CET.docx Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME CTilton:ls AMStone DATE 05/31/12 06/11/12 OFFICIAL RECORD COPY

Letter to Mr. Michael J. Pacilio from Ms. Ann Marie Stone dated June 11, 2012.

SUBJECT:

QUAD CITIES NUCLEAR POWER STATION REQUEST FOR INFORMATION FOR AN NRC POST-APPROVAL SITE INSPECTION FOR LICENSE RENEWAL DISTRIBUTION

Michael McCoppin

RidsNrrDorlLpl3-2 Resource

RidsNrrPMQuadCities Resource

RidsNrrDirsIrib Resource Chuck Casto Cynthia Pederson Steven Orth Jared Heck

Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Patricia Buckley Tammy Tomczak