Constellation" SVP-23-031 July 14, 2023 U. S. Nuclear Regulatory Commission A TIN: Document Control Desk Washington, D.C. 20555-0001 Quad Cities Nuclear Power Station, Units 1 and 2 Renewed Facility Operating License Nos. DPR-29 and DPR-30 NRC Docket Nos. 50-254 and 50-265

Subject:

Regulatory Commitment Change Summary Report This letter provides the Constellation Energy Generation, LLC (CEG) Regulatory Commitment Change Summary Report for Quad Cities Nuclear Power Station. Revisions to commitments are processed and reported in accordance with Nuclear Energy Institute (NEI) 99-04, "Guidelines for Managing NRC Commitment Changes." For the period from June 1, 2022, through May 31, 2023, no commitment changes were processed requiring NRC notification.

Should you have any questions concerning this letter, please contact Mark Humphrey at (309) 227-2800.

Brian Wake Site Vice President Quad Cities Nuclear Power Station cc: Regional Administrator - NRC Region Ill NRC Senior Resident Inspector - Quad Cities Nuclear Power Station