ENS 43047: Difference between revisions
Jump to navigation
Jump to search
StriderTol (talk | contribs) (Created page by program invented by Mark Hawes) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 16: | Line 16: | ||
| event date = 12/12/2006 13:22 PST | | event date = 12/12/2006 13:22 PST | ||
| last update date = 12/12/2006 | | last update date = 12/12/2006 | ||
| title = Circulating Water Pump Failure Causes Explosion | | title = Circulating Water Pump Failure Causes Explosion in Intake Structure | ||
| event text = On December 12, 2006, at 1322 PST, while conducting power ascension operations with Unit 2 at approximately 25 percent power, an electrical failure occurred in the Unit 2 circulating water pump motor enclosure (CWP) 2-1. A loud bang and explosion was reported to the Unit 2 control room. At 1322 PST, an electrical transient was experienced on Unit 2 12-Kv non-vital bus 'D' which in turn caused reactor coolant pump (RCP) 2-2 and RCP 2-4 motor breakers to trip on 12kV non-vital bus 'D' undervoltage, initiating an automatic reactor trip. The reactor trip signal was initiated when 2 out of 4 RCP motor breakers opened. All control rods fully inserted in response to the reactor trip and all plant systems functioned as required. The auxiliary feedwater system for Unit 2 was manually actuated per plant procedures, before an auto-start signal for this system was generated. At 1356 PST, DCPP Fire Department first responders reported that the fire was out. | | event text = On December 12, 2006, at 1322 PST, while conducting power ascension operations with Unit 2 at approximately 25 percent power, an electrical failure occurred in the Unit 2 circulating water pump motor enclosure (CWP) 2-1. A loud bang and explosion was reported to the Unit 2 control room. At 1322 PST, an electrical transient was experienced on Unit 2 12-Kv non-vital bus 'D' which in turn caused reactor coolant pump (RCP) 2-2 and RCP 2-4 motor breakers to trip on 12kV non-vital bus 'D' undervoltage, initiating an automatic reactor trip. The reactor trip signal was initiated when 2 out of 4 RCP motor breakers opened. All control rods fully inserted in response to the reactor trip and all plant systems functioned as required. The auxiliary feedwater system for Unit 2 was manually actuated per plant procedures, before an auto-start signal for this system was generated. At 1356 PST, DCPP Fire Department first responders reported that the fire was out. | ||
At 1340 the licensee declared a Notice of Unusual Event (NUE), number 23, 'Confirmed Explosion Onsite'. | At 1340 the licensee declared a Notice of Unusual Event (NUE), number 23, 'Confirmed Explosion Onsite'. |
Latest revision as of 21:17, 1 March 2018
Where | |
---|---|
Diablo Canyon California (NRC Region 4) | |
Reporting | |
Emergency class: | Unusual Event |
10 CFR 50.72(a) (1) (i), Emergency Class Declaration 10 CFR 50.72(b)(2)(iv)(B), RPS Actuation 10 CFR 50.72(b)(3)(iv)(A), System Actuation | |
LER: | 05000323/LER-2006-004 |
Time - Person (Reporting Time:+-4.38 h-0.183 days <br />-0.0261 weeks <br />-0.006 months <br />) | |
Opened: | Tony Chitwood 16:59 Dec 12, 2006 |
NRC Officer: | Pete Snyder |
Last Updated: | Dec 12, 2006 |
43047 - NRC Website
| |