|
---|
Category:Licensee Event Report (LER)
MONTHYEAR05000323/LER-2024-001, LCO 3.0.3 Completion Time Limits2024-05-17017 May 2024 LCO 3.0.3 Completion Time Limits 05000275/LER-2023-001, Unit 1 Manual Reactor Trip at Low Power2023-11-27027 November 2023 Unit 1 Manual Reactor Trip at Low Power 05000323/LER-2022-001, Reactor Coolant System Pressure Boundary Degradation2022-12-21021 December 2022 Reactor Coolant System Pressure Boundary Degradation 05000323/LER-2021-002, Manual Reactor Trip Due to Increased Water Level in a Feedwater Heater2021-12-14014 December 2021 Manual Reactor Trip Due to Increased Water Level in a Feedwater Heater 05000323/LER-2021-001, Emergency Diesel Generator Declared Inoperable Due to Low Frequency Condition Discovery During Routine Surveillance2021-09-20020 September 2021 Emergency Diesel Generator Declared Inoperable Due to Low Frequency Condition Discovery During Routine Surveillance 05000323/LER-2020-002, Manual Reactor Trip Due to Increased Main Generator Hydrogen Usage2020-09-15015 September 2020 Manual Reactor Trip Due to Increased Main Generator Hydrogen Usage 05000323/LER-2020-001, Shutdown Required by Technical Specifications2020-04-0909 April 2020 Shutdown Required by Technical Specifications 05000323/LER-2019-001, Containment Spray Inoperable in Mode 42020-01-29029 January 2020 Containment Spray Inoperable in Mode 4 05000323/LER-2018-001-01, Automatic Reactor Trip of Unit 2 Following a Load Rejection2019-04-11011 April 2019 Automatic Reactor Trip of Unit 2 Following a Load Rejection 05000323/LER-2018-001, Automatic Reactor Trip of Unit 2 Following a Load Rejection2019-01-30030 January 2019 Automatic Reactor Trip of Unit 2 Following a Load Rejection 05000323/LER-1917-001, Regarding Relief Valve Leakage Resulting in Inoperable Pressurizer Power Operated Relief Valve2017-10-0303 October 2017 Regarding Relief Valve Leakage Resulting in Inoperable Pressurizer Power Operated Relief Valve 05000323/LER-2016-001, Regarding Reactor Trip Breakers Manually Opened During Shutdown Due to a Control Rod Movable Gripper Fuse Failure2016-07-28028 July 2016 Regarding Reactor Trip Breakers Manually Opened During Shutdown Due to a Control Rod Movable Gripper Fuse Failure 05000275/LER-2015-002, Regarding Environmental Qualification of Wide Range Resistance Temperature Detectors Wiring Exceeded2015-12-0303 December 2015 Regarding Environmental Qualification of Wide Range Resistance Temperature Detectors Wiring Exceeded 05000323/LER-2014-002-01, Regarding Unit 2 Plant Shutdown Required by Technical Specifications2015-05-0707 May 2015 Regarding Unit 2 Plant Shutdown Required by Technical Specifications DCL-15-042, Supplemental Licensee Event Report 1-2014-004-01 for Diablo Canyon, Units 1 and 2 Regarding Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power2015-03-30030 March 2015 Supplemental Licensee Event Report 1-2014-004-01 for Diablo Canyon, Units 1 and 2 Regarding Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power DCL-15-041, Supplemental LER 2-13-004-01 for Diablo Canyon, Unit 2 Regarding Technical Specification 3.8.1 Not Met Due to Failed Wire Lug on Emergency Diesel Generator 2-32015-03-30030 March 2015 Supplemental LER 2-13-004-01 for Diablo Canyon, Unit 2 Regarding Technical Specification 3.8.1 Not Met Due to Failed Wire Lug on Emergency Diesel Generator 2-3 05000275/LER-2015-001, Regarding Both Trains of Residual Heat Removal Inoperable Due to Circumferential Crack on a Socket Weld2015-03-0202 March 2015 Regarding Both Trains of Residual Heat Removal Inoperable Due to Circumferential Crack on a Socket Weld 05000275/LER-2014-003-02, Regarding Unanalyzed Condition Affecting Emergency Diesel Generators, Tornado Missiles2015-02-0202 February 2015 Regarding Unanalyzed Condition Affecting Emergency Diesel Generators, Tornado Missiles 05000275/LER-2014-004, Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power2014-12-30030 December 2014 Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power 05000275/LER-2014-003-01, Regarding Unanalyzed Condition Affecting Unit 1 and 2 Emergency Diesel Generators, Tornado Missiles2014-08-0404 August 2014 Regarding Unanalyzed Condition Affecting Unit 1 and 2 Emergency Diesel Generators, Tornado Missiles 05000275/LER-2013-009-01, Regarding Unanalyzed Condition Affecting Unit 1 Emergency Diesel Generators2014-05-14014 May 2014 Regarding Unanalyzed Condition Affecting Unit 1 Emergency Diesel Generators 05000275/LER-2014-003, Regarding Unanalyzed Condition Affecting Unit 1 and 2 Emergency Diesel Generators, Tornado Missiles2014-05-0505 May 2014 Regarding Unanalyzed Condition Affecting Unit 1 and 2 Emergency Diesel Generators, Tornado Missiles 05000323/LER-2014-001, Regarding Lightning Arrester Failure Resulting in Reactor Trip2014-04-0303 April 2014 Regarding Lightning Arrester Failure Resulting in Reactor Trip 05000275/LER-2014-001, Regarding Technical Specification 3.4.3, Reactor Coolant System Pressure Limit Violation During Vacuum Refill Due to Human Error2014-03-31031 March 2014 Regarding Technical Specification 3.4.3, Reactor Coolant System Pressure Limit Violation During Vacuum Refill Due to Human Error 05000275/LER-2013-010, Regarding Two Emergency Diesel Generators Inoperable Due to Operator Error2014-02-18018 February 2014 Regarding Two Emergency Diesel Generators Inoperable Due to Operator Error 05000275/LER-2013-009, Regarding Unanalyzed Condition Affecting Unit 1 Emergency Diesel Generators2014-02-11011 February 2014 Regarding Unanalyzed Condition Affecting Unit 1 Emergency Diesel Generators 05000275/LER-2013-006-01, Regarding Emergency Diesel Generators Valid Start Signal Due to Loss of Startup Power2014-01-30030 January 2014 Regarding Emergency Diesel Generators Valid Start Signal Due to Loss of Startup Power 05000275/LER-2013-008, Regarding Technical Specification 3.3.4 Not Met Due to Inoperable Remote Shutdown System Function2014-01-16016 January 2014 Regarding Technical Specification 3.3.4 Not Met Due to Inoperable Remote Shutdown System Function DCL-13-117, Re Auxiliary Feedwater Actuation Due to Main Feedwater Pump Trip2013-12-12012 December 2013 Re Auxiliary Feedwater Actuation Due to Main Feedwater Pump Trip 05000275/LER-2013-003-01, Regarding Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power2013-10-17017 October 2013 Regarding Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power 05000275/LER-2013-006, Regarding Emergency Diesel Generators Valid Start Signal Due to Loss of Startup Power2013-10-14014 October 2013 Regarding Emergency Diesel Generators Valid Start Signal Due to Loss of Startup Power 05000323/LER-2013-005, Regarding Unit 2 Reactor Trip Due to Lightning Arrester Flashover2013-09-0505 September 2013 Regarding Unit 2 Reactor Trip Due to Lightning Arrester Flashover 05000275/LER-2013-003, Regarding Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power2013-08-22022 August 2013 Regarding Actuation of Six Emergency Diesel Generators Due to Loss of Offsite Power 05000275/LER-2013-004, Regarding All Three Unit 1 Emergency Diesel Generators Momentarily Inoperable2013-08-22022 August 2013 Regarding All Three Unit 1 Emergency Diesel Generators Momentarily Inoperable 05000275/LER-2013-005, Both Trains of Residual Heat Removal Inoperable Due to Circumferential Crack on a Socket Weld2013-08-22022 August 2013 Both Trains of Residual Heat Removal Inoperable Due to Circumferential Crack on a Socket Weld 05000323/LER-2013-004, Regarding Technical Specification 3.8.1 Not Met Due to Failed Wire Lug on Emergency Diesel Generator 2-32013-07-30030 July 2013 Regarding Technical Specification 3.8.1 Not Met Due to Failed Wire Lug on Emergency Diesel Generator 2-3 05000275/LER-2012-005-01, Regarding Unanalyzed Condition Due to Nonconservative Change in Atmospheric Dispersion Factor2013-06-0303 June 2013 Regarding Unanalyzed Condition Due to Nonconservative Change in Atmospheric Dispersion Factor 05000323/LER-2013-002, Both Source Range Nuclear Instruments Inoperable While in Mode 62013-05-0909 May 2013 Both Source Range Nuclear Instruments Inoperable While in Mode 6 05000323/LER-2013-001, Regarding Valid EDG 2-1 Start Signal Caused by a Loss of 4KV Class 1E Bus G2013-04-29029 April 2013 Regarding Valid EDG 2-1 Start Signal Caused by a Loss of 4KV Class 1E Bus G 05000275/LER-2013-001, Noncompliance with TS 3.4.12, Low Temperature Overpressure Protection System Due to Human Error2013-03-0404 March 2013 Noncompliance with TS 3.4.12, Low Temperature Overpressure Protection System Due to Human Error 05000275/LER-2012-007-01, Inadequately Compensated Non-Conformances in the Fire Protection Program2013-02-0808 February 2013 Inadequately Compensated Non-Conformances in the Fire Protection Program 05000275/LER-2011-008-01, Control Room Ventilation System Design Vulnerability2013-01-24024 January 2013 Control Room Ventilation System Design Vulnerability 05000275/LER-2012-008, Regarding Loss of Control Room Ventilation System Due to Inadequate Design Control2013-01-24024 January 2013 Regarding Loss of Control Room Ventilation System Due to Inadequate Design Control 05000275/LER-2011-007-02, Inadequate Control Room Envelope Testing Due to Inadequately-Documented In-leakage Test Data2013-01-24024 January 2013 Inadequate Control Room Envelope Testing Due to Inadequately-Documented In-leakage Test Data 05000323/LER-2012-002, Regarding Coupling Capacitor Voltage Transformer Bushing Failure Causes Reactor Trip2012-12-10010 December 2012 Regarding Coupling Capacitor Voltage Transformer Bushing Failure Causes Reactor Trip 05000275/LER-2012-007, Regarding Inadequately Compensated Non-Conformances in the Fire Protection Program2012-12-0707 December 2012 Regarding Inadequately Compensated Non-Conformances in the Fire Protection Program 05000275/LER-2012-006, Regarding Violation of Technical Specifications Due to Incorrect Bases2012-10-16016 October 2012 Regarding Violation of Technical Specifications Due to Incorrect Bases 05000323/LER-2012-001, Regarding Failure to Meet Emergency Diesel Generator Technical Specifications2012-10-16016 October 2012 Regarding Failure to Meet Emergency Diesel Generator Technical Specifications 05000275/LER-2012-005, Regarding Unanalyzed Condition Due to Nonconservative Change in Atmospheric Dispersion Factor2012-08-31031 August 2012 Regarding Unanalyzed Condition Due to Nonconservative Change in Atmospheric Dispersion Factor 05000275/LER-2012-004, Regarding Mode Transition with Turbine-Driven Auxiliary Feedwater Pump 1-1 Inoperable2012-08-13013 August 2012 Regarding Mode Transition with Turbine-Driven Auxiliary Feedwater Pump 1-1 Inoperable 2024-05-17
[Table view] |
text
Pacific Gas and Electric Company' James R. Becker Diablo Canyon Power Plant Vice President P. 0. Box 56 Diablo Canyon Operations and Avila Beach, CA 93424 Station Director 805.545.3462 February 12, 2007 Fax: 805.545.4234 PG&E Letter DCL-07-015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Docket No. 50-323, OL-DPR-82 Diablo Canyon Unit 2 Licensee Event Report 2-2006-004-00 Automatic Reactor Trip due to Circulating Water Pump Surge Capacitor Failure
Dear Commissioners and Staff:
In accordance with 10 CFR 50.73 (a)(2)(iv) Pacific Gas and Electric Company is submitting the enclosed Licensee Event Report regarding an automatic reactor trip due to circulating water pump surge capacitor failure.
In accordance with 10 CFR 50.72(a)(1)(i), Emergency Declared, 50.72 (b)(2)(iv)(B), Reactor Protection System Actuation while critical, and 50.72 (b)(3)(iv)(A), Actuation of the Auxiliary Feedwater System, an Emergency Notification System report was made as Event Number 43047.
This event did not adversely affect the health and safety of the public. There are no new or revised regulatory commitments in this report.
Sincer ly, James R.
cker dd m/2246/A0684385 Enclosure cc/enc:
Terry W. Jackson, NRC Senior Resident Inspector Bruce S. Mallett, NRC Region IV Alan B. Wang, NRR Project Manager Diablo Distribution INPO A member of the STARS (Strategic Teaming and Resource Sharing) Alliance Caltaway e Comanche Peak
- Diablo Canyon e Palo Verde
- ?,
LICENSEE EVENT REPORT (LER)
FACILITY NAME (1)
DOCKET NUMBER (2)
PAGE(3)
Diablo Canyon Unit 2 015101010131213 1
OF 5
TITLE (4)
Automatic Reactor Trip due to Circulating Water Pump Surge Capacitor Failure EVENT LER NUMBER (6)
REPORT OTHER FACILITIES INVOLVED (8)
DATE (5)
DATE (7)
MO DAY YEAR YEAR SEQUENTIAL NUMBER REVISION MO DAY YEAR FACILITY NAME DOCKET NUMBER NUMBER 12 1220062006 -
0014 -0002 122007 05000000 OPERATING THIS REPORT IS SUBMITTED PURSUANT TO THE REQUIREMENTS OF 10 CFR: (11)
MODE (9) 1 X
10 CFR 50.73 (a)(2)(iv)(A)
POWER LEVEL (10)X
_______FL 10 CFR 50.73 (a)(2)(iv)(B) 1 0, 0, (SPECIFY IN ABSTRACT BELOW AND IN TEXT, NRC FORM 366A)
LICENSEE CONTACT FOR THIS LER (12)
TELEPHONE NUMBER AREA CODE Lawrence M. Parker - Senior Regulatory Services Engineer 805 1545-3386 COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT (13)
CAUSE
SYSTEM COMPONENT MANUFACTURER REPORTABLE
CAUSE
SYSTEM COMPONENT MANUFACTURER REPORTABLE TO EPIX TO EPIX X KIE ICIAIP 716101A I
I KIJI III SUPPLEMENTAL REPORT EXPECTED (14)
EXPECTED MONR YES (If yes, complete EXPECTED SUBMISSION DATE)
[X] NO SUBMISSION DATE (15)
ABSTRACT (Limit to 1400 spaces. i.e., approximately 15 single-spaced typewritten lines.) (16)
On December 12, 2006, at 1322 PST, with Unit 2 at approximately 25 percent power, an electrical failure occurred in the circulating water pump (CWP) motor enclosure for CWP 2-1. An Emergency Notification System (ENS) Notice of Unusual Event (NUE), Number 23, Confirmed Explosion Onsite, was reported in accordance with 10 CFR 50.72 (a)(1)(i) at 1359 PST. The NUE was terminated at 1430 PST following confirmation that the initial report was due to a CWP 2-1 electrical discharge and fire, that was extinguished.
On December 12, 2006, at 1541 PST, ENS Event Number 43047 was updated to include a 4-hour report in accordance with 10 CFR 50.72 (b)(2)(iv)(B) due to a Reactor Protection System actuation while critical, and an 8-hour notification in accordance with 10 CFR 50.72 (b)(3)(iv)(A) due to the actuation of the auxiliary feedwater system. All equipment responded as designed.
The CWP 2-1 surge capacitor was replaced and the associated electrical system was repaired. The cause of the failure was a single random failure of the surge capacitor. Corrective actions will include replacing the 12kV three phase surge capacitors with more reliable single phase surge capacitors and enhancing the preventive maintenance program.
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
YEAR SEQUENTIAL NUMBER REVISION NUMBER DiabloCanyonUnit2 0 5o0o0o0 3 2 2006
- - 2 0 04 I
0 0
2 OFL5 TEXT I.
Plant Conditions
Pacific Gas and Electric Company (PG&E) Unit 2 was in Mode 1 (Power Operation) at approximately 25 percent reactor power prior to the event.
I1.
Description of Problem A.
Background
The circulating water system [KE] provides a continuous ocean water cooling supply to the main condenser [COND], condensate cooler [CLR],
service water cooling system [KG], and intake cooling system [KE]. Each unithas two single-stage circulating water pumps (CWP). The CWPs are nominal 12kV motors with local surge capacitors installed to modify steep fronted electrical waves and prevent damage to the turn-to-turn insulation of the motor. The locally mounted surge capacitors are routinely inspected each refueling outage. The surge capacitors are replaced only when found damaged or leaking.
Each unit has two non-vital 12kV Buses. Non-vital Bus D provides power to CWP 2-1 and Reactor Coolant Pumps (RCPs) 2-2 and 2-4. A reactor trip signal is initiated upon opening of any 2 of 4 RCP motor breakers.
B.
Event Description
On December 12, 2006, at 1322 PST, while conducting power ascension operations with Unit 2 at approximately 25 percent power, an electrical failure occurred in the circulating water pump (CWP 2-1) 12 kV motor enclosure. A loud bang and explosion was reported to licensed plant operators in the Unit 2 control room. The electrical transient experienced on the 12 kV non-vital bus D actuated an undervoltage protection relay tripping the load breakers for CWP 2-1, as well as RCP 2-2 and RCP 2-4.
The reactor trip signal was initiated when 2 out of 4 RCP motor breakers opened. All control rods fully inserted in response to the reactor trip and all plant systems functioned as required. The auxiliary feedwater system for Unit 2 was manually actuated per plant procedures, before an auto-start signal for this system was generated.
On December 12, 2006, at 1340 PST, licensed plant operators declared a Notice of Unusual Event (NUE), Number 23, Confirmed Explosion Onsite.
On December 12, 2006, at 1356 PST, the Diablo Canyon Power Plant (DCPP) Fire Department first responders reported that the fire was out.
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
YEAR SEQUENTIAL NUMBER REVISION NUMBER DiabloCanyonUnit2 0 51 0 1o0 1 301 2006 1° 0
I -
01 0 3
3 F5 TEXT On December 12, 2006, at 1359 PST, an Emergency Notification System (ENS) report was made in accordance with 10 CFR 50.72 (a)(1)(i) as Event Number43047.
Decay heat was removed via auxiliary feedwater to the steam generators steaming to the atmospheric dump valves. Emergency power was supplied to DCPP via offsite electrical transmission system power.
On December 12, 2006, at 1430 PST, DCPP terminated the NUE following confirmation that the initial report was due to a CWP 2-1 electrical discharge and fire, which was extinguished.
On December 12, 2006, at 1541 PST, ENS EN 43047 was updated to include a 4-hour report in accordance with 10 CFR 50.72 (b)(2)(iv)(B) due to a Reactor Protection System actuation while critical, and an 8-hour notification in accordance with 10 CFR 50.72 (b)(3)(iv)(A) due to the actuation of the auxiliary feedwater system.
C.
Status of Inoperable Structures, Systems, or Components that Contributed to the Event None.
D.
Other Systems or Secondary Functions Affected
None.
E.
Method of Discovery
The automatic actuations were immediately known to licensed plant operators in the control room by alarms and indications. Onsite reports by operators and security personnel provided immediate reports of CWP 2-1 condition and the DCPP Fire Department lead provided detailed information regarding the fire suppression and termination.
F.
Operator Actions
Plant operators responded to alarms and indications provided in the control room, entered approved plant procedures, and initiated auxiliary feedwater prior to automatic actuation.
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
YEAR SEQUENTIAL NUMBER REVISION NUMBER DiabloCanyonUnit2 1 o0 101 0
1 23 2006
°10 1 4 0
°0 14 OF TEXT G.
Safety System Responses The reactor trip signal was initiated when 2 out of 4 RCP motor breakers opened. All control rods fully inserted in response to the reactor trip and all plant systems functioned as required. The auxiliary feedwater system was manually actuated per plant procedures, before an auto-start signal for this system was generated.
I1l.
Cause of the Problem A.
Immediate Cause The CWP 2-1 surge capacitor failed causing a phase to phase electrical short resulting in a 12kV electrical discharge and localized fire.
B.
Root Cause The root cause of the surge capacitor phase-to-phase internal fault was an inservice insulation breakdown, a single random electrical failure. No adverse industry or site surge capacitor failure trend was identified.
C.
Contributing Causes
An engineering replacement part evaluation issued in 1993 allowed the use of a single three phase capacitor in lieu of the more reliable single phase capacitors. Also, the surge capacitor maintenance program was inadequate to ensure replacement consistent with testing or industry data.
IV.
Assessment of Safety Consequences
There were no actual safety consequences involved in this event since the nonsafety-related plant electrical systems responded as designed automatically terminating the 12kV power to the fault. All safety-related systems responded as designed by tripping the reactor and would have automatically started the auxiliary feedwater pumps, in the event the licensed plant operators did not manually initiate them via approved plant procedures.
Final Safety Analysis Report (FSAR) Update, Section 15.2.9, Loss of Offsite Power to the Station Auxiliaries, previously analyzed the total loss of offsite power, and bounds the partial loss of forced circulation experienced in this event.
The FSAR Update concluded that "for the loss-of offsite power to station auxiliaries event, all safety criteria are met."
LICENSEE EVENT REPORT (LER) TEXT CONTINUATION FACILITY NAME (1)
DOCKET NUMBER (2)
LER NUMBER (6)
PAGE (3)
YEAR SEQUENTIAL NUMBER REVISION NUMBER DiabloCanyonUnit2 05 000 2 3 2006 0 101 4 01 0 5
OF 5
TEXT This condition is not considered a Safety System Functional Failure as the loss of one of two nonsafety-related CWPs is a previously analyzed transient that does not create a significant condition adverse to safety.
Therefore, the event is not considered risk significant, and it did not adversely affect the health and safety of the public.
V.
Corrective Actions
A.
Immediate Corrective Actions
The CWP 2-1 surge capacitor was replaced and the associated electrical system was repaired.
B.
Corrective Actions
PG&E will replace the 12kV three phase surge capacitors with more reliable single phase surge capacitors.
PG&E will enhance the surge capacitor preventive maintenance program to include periodic replacement of the 12kV and 4kV surge capacitors based upon testing and/or industry data.
VI.
Additional Information
A.
Component:
The component is an ABB 3-phase 13.8 kV Capacitor, Part# ESG3180A39, and was last replaced in 1996.
B.
Previous Similar Events
None.
|
---|
|
|
|
05000275/LER-2006-001, Regarding Excessive Dead Birds Found at the Pacific Ocean Cooling Water Intake | Regarding Excessive Dead Birds Found at the Pacific Ocean Cooling Water Intake | | 05000323/LER-2006-001, CFR 21 Notification of a Defective Residual Heat Removal Check Valve | CFR 21 Notification of a Defective Residual Heat Removal Check Valve | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(ii)(B), Unanalyzed Condition 10 CFR 50.73(a)(2)(v)(A), Loss of Safety Function - Shutdown the Reactor 10 CFR 50.73(a)(2)(v)(B), Loss of Safety Function - Remove Residual Heat 10 CFR 50.73(a)(2)(v), Loss of Safety Function 10 CFR 50.73(a)(2)(vii), Common Cause Inoperability 10 CFR 50.73(a)(2)(i)(B), Prohibited by Technical Specifications 10 CFR 50.73(a)(2)(i) 10 CFR 50.73(a)(2)(x) 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.73(a)(2)(iii) 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown 10 CFR 50.73(a)(2)(ix)(A), Prevented Safety Function in Multiple System 10 CFR 21.21(d)(3)(ii), Failure to Comply or Defect 10 CFR 50.73(a)(2)(viii)(A) 10 CFR 50.73(a)(2)(viii)(B) 10 CFR 21.21(d)(1) | 05000323/LER-2006-002, Re Steam Generator Tube Plugging Due to Stress Corrosion Cracking | Re Steam Generator Tube Plugging Due to Stress Corrosion Cracking | 10 CFR 50.73(a)(2)(ii)(A), Seriously Degraded 10 CFR 50.72(b)(3)(ii), Degraded or Unanalyzed Condition | 05000323/LER-2006-003, Re Manual Reactor Trip Due to Reactor Coolant Pump High Temperature Indication | Re Manual Reactor Trip Due to Reactor Coolant Pump High Temperature Indication | 10 CFR 50.73(a)(2)(i)(A), Completion of TS Shutdown | 05000323/LER-2006-004, Regarding Automatic Reactor Trip Due to Circulating Water Pump Surge Capacitor Failure | Regarding Automatic Reactor Trip Due to Circulating Water Pump Surge Capacitor Failure | 10 CFR 50.73(a)(2)(iv)(A), System Actuation 10 CFR 50.73(a)(2)(iv), System Actuation |
|