Line 2: |
Line 2: |
| | number = ML18305A755 | | | number = ML18305A755 |
| | issue date = 01/15/2019 | | | issue date = 01/15/2019 |
| | title = 11/06/2018 Summary of Closed Teleconference on PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance. | | | title = Summary of Closed Teleconference on PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance. |
| | author name = Holonich J | | | author name = Holonich J |
| | author affiliation = NRC/NRR/DLP/PLPB | | | author affiliation = NRC/NRR/DLP/PLPB |
Latest revision as of 07:27, 30 November 2019
|
---|
Category:Meeting Summary
MONTHYEARML20083F1492020-07-0606 July 2020 Summary of Meeting to Discuss Digital Instrumentation and Control, Integrated Action Plan, Modernization Plan #3, Acceptance of Digital Equipment, Nuclear Energy Institute 17-06 ML20069A7452020-05-14014 May 2020 Summary of Closed Pre-Submittal Meeting with Westinghouse Electric Company to Discuss WCAP-16097, Revision 5, Common Q Platform Topical Report ML19273A8942020-01-15015 January 2020 November 6, 2019, Summary of Meeting to Discuss Nuclear Energy Institute 17-06 ML19247C0532019-09-24024 September 2019 Summary of Meeting Between the NRC Staff and NEI to Discuss Revised Guidance Documents: Inspection Manual Chapter (IMC) 0326 and NEI 18-03 ML19226A1102019-09-0909 September 2019 Summary of August 21, 2019, Meeting to Discuss the Nuclear Procurement Issues Corporation Process and the Plans for Nuclear Energy Institute 17-06 ML19151A7552019-06-17017 June 2019 Summary of Meeting to Discuss Nuclear Energy Institute'S Perspective of American Society of Mechanical Engineers Code Compliance and Operability Determinations ML19064B4042019-03-13013 March 2019 Summary of Meeting Between the NRC Staff and the Nuclear Energy Institute Regarding Nei'S Perspective of ASME Code Compliance and Operability Determinations ML18302A0032019-01-15015 January 2019 Summary of Meeting to Discuss Operability Determination/Corrective Action Program Interface Definitions ML18305A7552019-01-15015 January 2019 Summary of Closed Teleconference on PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance. ML18267A0042018-10-0303 October 2018 Summary of Meeting to Discuss Digital Instrumentation and Control Integrated Action Plan, Modernization Plan #3 ML18204A0222018-10-0101 October 2018 August 30, 2018, Summary of Meeting to Discuss the Nuclear Energy Institute Introduction of Entry Criteria for Operability Determinations ML18232A1082018-09-26026 September 2018 Summary of 08/30/2018, Meeting to Discuss the Draft Safety Evaluation for PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance (CAC No. MF8075; EPID L-2016-TOP-0006) ML18179A3622018-07-16016 July 2018 June 28, 2018, Operability Meeting Summary ML18155A0042018-07-0909 July 2018 Summary of May 24, 2018, Meeting to Discuss Digital Instrumentation and Control Common Cause Failure ML18142A2502018-06-0707 June 2018 Summary of Meeting with Nuclear Energy Institute and Industry to Discuss Anchor Darling Fate Valve Draft Temporary Instruction ML18136A5052018-05-30030 May 2018 Summary of Conference Call to Discuss the Use of Strategic Alliance for FLEX Emergency Response Resources to Support Exigent Situations ML18082A0292018-04-23023 April 2018 March 29, 2018, Summary of Meeting to Discuss the Roadmap for Proposed Industry-Wide Monitoring Program and RAI Response Templates ML18009A6382018-04-0909 April 2018 Summary of Biweekly Conference Calls to Discuss Fleet-Wide Response to Draft Requests for Additional Information Related to Generic Letter 2016-01 ML18065A0402018-03-26026 March 2018 February 14, 2018, Summary of Meeting with the Nuclear Encergy Institute and Industry to Discuss Anchor Darling Gate Valve Part 21 Issues ML17335A4232018-01-22022 January 2018 Summary for 12/13/2017 NEI 16-16 Meeting ML17331A4852017-12-22022 December 2017 Summary of 11/30/2017 Meeting on NEI 96-07, App D, Section 4.3.6 2020-07-06
[Table view] Category:Memoranda
MONTHYEARML20083F1492020-07-0606 July 2020 Summary of Meeting to Discuss Digital Instrumentation and Control, Integrated Action Plan, Modernization Plan #3, Acceptance of Digital Equipment, Nuclear Energy Institute 17-06 ML20069A7452020-05-14014 May 2020 Summary of Closed Pre-Submittal Meeting with Westinghouse Electric Company to Discuss WCAP-16097, Revision 5, Common Q Platform Topical Report ML19273A8942020-01-15015 January 2020 November 6, 2019, Summary of Meeting to Discuss Nuclear Energy Institute 17-06 ML19247C0532019-09-24024 September 2019 Summary of Meeting Between the NRC Staff and NEI to Discuss Revised Guidance Documents: Inspection Manual Chapter (IMC) 0326 and NEI 18-03 ML19226A1102019-09-0909 September 2019 Summary of August 21, 2019, Meeting to Discuss the Nuclear Procurement Issues Corporation Process and the Plans for Nuclear Energy Institute 17-06 ML19151A7552019-06-17017 June 2019 Summary of Meeting to Discuss Nuclear Energy Institute'S Perspective of American Society of Mechanical Engineers Code Compliance and Operability Determinations ML19064B4042019-03-13013 March 2019 Summary of Meeting Between the NRC Staff and the Nuclear Energy Institute Regarding Nei'S Perspective of ASME Code Compliance and Operability Determinations ML18305A7552019-01-15015 January 2019 Summary of Closed Teleconference on PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance. ML18302A0032019-01-15015 January 2019 Summary of Meeting to Discuss Operability Determination/Corrective Action Program Interface Definitions ML18267A0042018-10-0303 October 2018 Summary of Meeting to Discuss Digital Instrumentation and Control Integrated Action Plan, Modernization Plan #3 ML18204A0222018-10-0101 October 2018 August 30, 2018, Summary of Meeting to Discuss the Nuclear Energy Institute Introduction of Entry Criteria for Operability Determinations ML18232A1082018-09-26026 September 2018 Summary of 08/30/2018, Meeting to Discuss the Draft Safety Evaluation for PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance (CAC No. MF8075; EPID L-2016-TOP-0006) ML18213A2852018-08-13013 August 2018 Aug. 1, 2018 Summary of Closed Meeting with Doosan Hf Controls to Discuss the Revision of Amendment 4 to the Doosan Hf Controls-6000 Safety System ML18179A3622018-07-16016 July 2018 June 28, 2018, Operability Meeting Summary ML18155A0042018-07-0909 July 2018 Summary of May 24, 2018, Meeting to Discuss Digital Instrumentation and Control Common Cause Failure ML18082A0292018-04-23023 April 2018 March 29, 2018, Summary of Meeting to Discuss the Roadmap for Proposed Industry-Wide Monitoring Program and RAI Response Templates ML18065A0402018-03-26026 March 2018 February 14, 2018, Summary of Meeting with the Nuclear Encergy Institute and Industry to Discuss Anchor Darling Gate Valve Part 21 Issues ML17335A4232018-01-22022 January 2018 Summary for 12/13/2017 NEI 16-16 Meeting 2020-07-06
[Table view] |
Text
January 15, 2019 MEMORANDUM TO: Dennis C. Morey, Chief Licensing Processes Branch Division of Licensing Projects Office of Nuclear Reactor Regulation FROM: Joseph J. Holonich, Senior Project Manager Licensing Processes Branch /RA/
Division of Licensing Projects Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF NOVEMBER 6, 2018, CLOSED TELECONFERENCE ON PWROG-15060, "PUMP SUCTION GAS ACCUMULATION OPERABILITY CRITERIA GUIDANCE" On November 6, 2018, the U. S. Nuclear Regulatory Commission (NRC) staff held a closed teleconference with representatives of the Pressurized Water Reactor Owners Group (PWROG) and the Nuclear Energy Institute (NEI). These organizations will be known collectively as the industry. The meeting was to discuss several clarifications related to PWROG comments on the draft safety evaluation (DSE) for PWROG-15060, "Pump Suction Gas Accumulation Operability Criteria Guidance," (Agencywide Document Access and Management System Package Accession No.: ML18290A527).
During the call, the NRC staff and industry engaged in a number of clarification discussions, questions, and answers. The focus of the discussions was understanding the data used to support figures in the equation. The NRC staff was not sure how the several data points were developed and used. It appeared to the NRC staff that figures did not reflect the data provided in the DSE comments. The details of the discussion were proprietary so no additional information is provided.
No actions were identified from the call.
Attendees on the call were: NRC: Joseph Holonich, Jennifer Whitman, Terence Brimfield, Diana Woodyatt; PWROG: Jay Boardman; NEI: Frankie Pimentel CONTACT: Joseph Holonich, NRR/DLP 301-415-7297 Docket No. 99902028