Letter Sequence Meeting |
---|
|
|
MONTHYEARML20092F0802020-04-20020 April 2020 Proprietary Determination for Draft, Submittal of WAAP-11711-P and WAAP-11711-NP, Common Qualified Platform Topical Report (WCAP-16097-P-A) Planned Revisions NRC Meeting April 2020 ML20097B9142020-04-21021 April 2020 Proprietary Determination for Submittal Handout for Pre-Submittal Meeting on Common Qualified Platfonn Topical Report (WCAP-16097-P-A) Planned Revisions NRC Meeting April 2020 Project stage: Meeting ML20069A7452020-05-14014 May 2020 Summary of Closed Pre-Submittal Meeting with Westinghouse Electric Company to Discuss WCAP-16097, Revision 5, Common Q Platform Topical Report Project stage: Meeting 2020-04-21
[Table View] |
|
---|
Category:Meeting Summary
MONTHYEARML20083F1492020-07-0606 July 2020 Summary of Meeting to Discuss Digital Instrumentation and Control, Integrated Action Plan, Modernization Plan #3, Acceptance of Digital Equipment, Nuclear Energy Institute 17-06 ML20069A7452020-05-14014 May 2020 Summary of Closed Pre-Submittal Meeting with Westinghouse Electric Company to Discuss WCAP-16097, Revision 5, Common Q Platform Topical Report ML19273A8942020-01-15015 January 2020 November 6, 2019, Summary of Meeting to Discuss Nuclear Energy Institute 17-06 ML19247C0532019-09-24024 September 2019 Summary of Meeting Between the NRC Staff and NEI to Discuss Revised Guidance Documents: Inspection Manual Chapter (IMC) 0326 and NEI 18-03 ML19226A1102019-09-0909 September 2019 Summary of August 21, 2019, Meeting to Discuss the Nuclear Procurement Issues Corporation Process and the Plans for Nuclear Energy Institute 17-06 ML19151A7552019-06-17017 June 2019 Summary of Meeting to Discuss Nuclear Energy Institute'S Perspective of American Society of Mechanical Engineers Code Compliance and Operability Determinations ML19064B4042019-03-13013 March 2019 Summary of Meeting Between the NRC Staff and the Nuclear Energy Institute Regarding Nei'S Perspective of ASME Code Compliance and Operability Determinations ML18302A0032019-01-15015 January 2019 Summary of Meeting to Discuss Operability Determination/Corrective Action Program Interface Definitions ML18305A7552019-01-15015 January 2019 Summary of Closed Teleconference on PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance. ML18267A0042018-10-0303 October 2018 Summary of Meeting to Discuss Digital Instrumentation and Control Integrated Action Plan, Modernization Plan #3 ML18204A0222018-10-0101 October 2018 August 30, 2018, Summary of Meeting to Discuss the Nuclear Energy Institute Introduction of Entry Criteria for Operability Determinations ML18232A1082018-09-26026 September 2018 Summary of 08/30/2018, Meeting to Discuss the Draft Safety Evaluation for PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance (CAC No. MF8075; EPID L-2016-TOP-0006) ML18179A3622018-07-16016 July 2018 June 28, 2018, Operability Meeting Summary ML18155A0042018-07-0909 July 2018 Summary of May 24, 2018, Meeting to Discuss Digital Instrumentation and Control Common Cause Failure ML18142A2502018-06-0707 June 2018 Summary of Meeting with Nuclear Energy Institute and Industry to Discuss Anchor Darling Fate Valve Draft Temporary Instruction ML18136A5052018-05-30030 May 2018 Summary of Conference Call to Discuss the Use of Strategic Alliance for FLEX Emergency Response Resources to Support Exigent Situations ML18082A0292018-04-23023 April 2018 March 29, 2018, Summary of Meeting to Discuss the Roadmap for Proposed Industry-Wide Monitoring Program and RAI Response Templates ML18009A6382018-04-0909 April 2018 Summary of Biweekly Conference Calls to Discuss Fleet-Wide Response to Draft Requests for Additional Information Related to Generic Letter 2016-01 ML18065A0402018-03-26026 March 2018 February 14, 2018, Summary of Meeting with the Nuclear Encergy Institute and Industry to Discuss Anchor Darling Gate Valve Part 21 Issues ML17335A4232018-01-22022 January 2018 Summary for 12/13/2017 NEI 16-16 Meeting ML17331A4852017-12-22022 December 2017 Summary of 11/30/2017 Meeting on NEI 96-07, App D, Section 4.3.6 2020-07-06
[Table view] Category:Memoranda
MONTHYEARML20083F1492020-07-0606 July 2020 Summary of Meeting to Discuss Digital Instrumentation and Control, Integrated Action Plan, Modernization Plan #3, Acceptance of Digital Equipment, Nuclear Energy Institute 17-06 ML20069A7452020-05-14014 May 2020 Summary of Closed Pre-Submittal Meeting with Westinghouse Electric Company to Discuss WCAP-16097, Revision 5, Common Q Platform Topical Report ML19273A8942020-01-15015 January 2020 November 6, 2019, Summary of Meeting to Discuss Nuclear Energy Institute 17-06 ML19247C0532019-09-24024 September 2019 Summary of Meeting Between the NRC Staff and NEI to Discuss Revised Guidance Documents: Inspection Manual Chapter (IMC) 0326 and NEI 18-03 ML19226A1102019-09-0909 September 2019 Summary of August 21, 2019, Meeting to Discuss the Nuclear Procurement Issues Corporation Process and the Plans for Nuclear Energy Institute 17-06 ML19151A7552019-06-17017 June 2019 Summary of Meeting to Discuss Nuclear Energy Institute'S Perspective of American Society of Mechanical Engineers Code Compliance and Operability Determinations ML19064B4042019-03-13013 March 2019 Summary of Meeting Between the NRC Staff and the Nuclear Energy Institute Regarding Nei'S Perspective of ASME Code Compliance and Operability Determinations ML18305A7552019-01-15015 January 2019 Summary of Closed Teleconference on PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance. ML18302A0032019-01-15015 January 2019 Summary of Meeting to Discuss Operability Determination/Corrective Action Program Interface Definitions ML18267A0042018-10-0303 October 2018 Summary of Meeting to Discuss Digital Instrumentation and Control Integrated Action Plan, Modernization Plan #3 ML18204A0222018-10-0101 October 2018 August 30, 2018, Summary of Meeting to Discuss the Nuclear Energy Institute Introduction of Entry Criteria for Operability Determinations ML18232A1082018-09-26026 September 2018 Summary of 08/30/2018, Meeting to Discuss the Draft Safety Evaluation for PWROG-15060, Pump Suction Gas Accumulation Operability Criteria Guidance (CAC No. MF8075; EPID L-2016-TOP-0006) ML18213A2852018-08-13013 August 2018 Aug. 1, 2018 Summary of Closed Meeting with Doosan Hf Controls to Discuss the Revision of Amendment 4 to the Doosan Hf Controls-6000 Safety System ML18179A3622018-07-16016 July 2018 June 28, 2018, Operability Meeting Summary ML18155A0042018-07-0909 July 2018 Summary of May 24, 2018, Meeting to Discuss Digital Instrumentation and Control Common Cause Failure ML18082A0292018-04-23023 April 2018 March 29, 2018, Summary of Meeting to Discuss the Roadmap for Proposed Industry-Wide Monitoring Program and RAI Response Templates ML18065A0402018-03-26026 March 2018 February 14, 2018, Summary of Meeting with the Nuclear Encergy Institute and Industry to Discuss Anchor Darling Gate Valve Part 21 Issues ML17335A4232018-01-22022 January 2018 Summary for 12/13/2017 NEI 16-16 Meeting 2020-07-06
[Table view] |
Text
May 14, 2020 MEMORANDUM TO: Dennis C. Morey, Chief Licensing Processes Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM: Joseph J. Holonich, Senior Project Manager /RA/
Licensing Processes Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
SUBJECT:
SUMMARY
OF APRIL 8, 2020, CLOSED PRE-SUBMITTAL MEETING WITH WESTINGHOUSE ELECTRIC COMPANY TO DISCUSS WCAP-16097, REVISION 5, COMMON QUALIFIED PLATFORM TOPICAL REPORT (EPID L-2020-TOP-0010)
On April 8, 2020, the U.S. Nuclear Regulatory Commission (NRC) staff held a conference call with representatives of Westinghouse Electric Company (Westinghouse). The call was a pre-submittal meeting to discuss revisions to WCAP-16097, Revision 5, Common Qualified Platform Topical Report [(TR)]. The information related to the meeting can be found in the Agencywide Documents Access and Management System Package Accession No. ML20069A663.
At the meeting, Westinghouse announced the signing of an agreement to acquire the AC160 nuclear technology from ABB. In the open portion of the meeting, Westinghouse representatives made a presentation on the proposed changes to the TR. During the discussion, the NRC staff and Westinghouse representatives engaged in numerous clarifications and questions and answers.
The NRC staff asked about the reason for NRC staff review of this revision. Westinghouse noted that a commercial grade dedication process for the ABB technology is specified in the current version of the TR. The Westinghouse representatives stated that the TR revision was removing all references to ABB in the TR. The Westinghouse representatives also explained that the Westinghouse TR change process requires NRC acceptance for any changes to the TR that are no longer correct.
The Westinghouse representatives further stated that though no impact to previous NRC safety conclusions were expected, the NRC safety evaluation (SE) needed to be updated to reflect the CONTACT: Joseph Holonich, NRR/DORL 301-415-7297
D. Morey changes to platform development processes. The current NRC SE refers to the Westinghouse commercial grade dedication processes as a basis for its safety conclusions.
In the open portion of the meeting, Westinghouse representative reported that Westinghouse planned to submit the TR in June. The Westinghouse representatives said that a minimal TR revision review would be requested in the transmittal letter and would address the questions to demonstrate that the minimal TR revision review could be used.
The Westinghouse representatives explained that the current plan was to request NRC staff approval in late 2020. Further, the Westinghouse representatives said that it needed NRC acceptance to be able to perform platform maintenance or design changes and the timing of NRC acceptance should be aligned with that need.
In the closed portion of the meeting, the Westinghouse representatives provided more details on the changes and the proposed schedule. The information discussed was proprietary, so no details are provided here.
There were no actions from the meeting.
Docket No. 99902038
Pkg: ML20069A663 Summary: ML20069A745 *concurrence via email OFFICE NRR/DORL/LLPB/PM* NRR/DORL/LLPB/LA* NRR/DE/EICB/BC*
NAME JHolonich DHarrison MWaters DATE 04/13/2020 05/11/2020 04/16/2020 OFFICE NRR/DORL/LLPB/BC* NRR/DORL/LLPB/PM*
NAME DMorey JHolonich DATE 05/13/2020 05/14/2020