ML062900037: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
Line 18: Line 18:


=Text=
=Text=
{{#Wiki_filter:October 20, 2006MEMORANDUM TO:FileFROM:Mahesh Chawla, Project Manager, Section 1 /RA/Plant Licensing Branch III-1Division of Operating Reactor Licensing
{{#Wiki_filter:October 20, 2006 MEMORANDUM TO: File FROM:                   Mahesh Chawla, Project Manager, Section 1 /RA/
Plant Licensing Branch III-1 Division of Operating Reactor Licensing


==SUBJECT:==
==SUBJECT:==
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 -TELEPHONE CONFERENCE TO DISCUSS EXTENSION OF RELIEF REQUESTS 2 AND 3 FOR THE FOURTH 10-YEAR INSERVICE TESTING PROGRAM INTERVAL (TAC NOS. MD3123 AND MD3124)On September 21, 2006, a conference call was held between the Nuclear RegulatoryCommission (NRC) staff and the representatives of Nuclear Management Company (NMC)(the licensee), to discuss the status of an interim relief granted until September 30, 2006, to Prairie Island Nuclear Generating Plant, Units 1 and 2, for Relief Requests 2 and 3 associated with the fourth 10-year inservice testing interval. In a letter dated June 28, 2004, NMC requested relief for Diesel-driven cooling water pumps 12and 22, and motor-driven cooling water pump 121. Relief was requested from ISTB-3550, which requires that a rate or quantity meter be installed in each of the pump test circuits. If a meter does not indicate the flow directly, the record shall include the method used to reduce the data. The Licensee proposed alternative pump testing using non-instrumented bypass lines that feed a jacket cooler and a gear oil cooler. Additional unmetered flow feeds the chemical treatment, and filtered water system. In a letter dated July 25, 2005, the staff evaluated these alternate methods and concluded thatthe bypass lines are not fixed resistance systems and fouling of the associated equipment could change the resistance of the bypass lines and potentially mask pump degradation. Long-term relief could not be granted due to the lack of information in the relief request explaining how the testing will account for potential masking of degrading flow rates. However, interim relief was granted pursuant to 10CFR50.55a(f)(6)(i) based on theimpracticality of the design and the burden that would result if the Code requirements were immediately imposed, such as a plant shutdown because testing in accordance with the Code could not be performed. The staff also concluded that the current test method will identify significant degrading trends for an interim period, providing an adequate level of assurance of the operational readiness of the pumps.The staff further concluded that granting relief would not endanger life or property or thecommon defense and security and was otherwise in the public interest, giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility. The licensee was requested to respond prior to September 30, 2006, to inform the staff of actions taken to achieve compliance with the code requirements. The licensee responded in a letter dated September 19, 2006, and requested an extension of the interim relief for ReliefRequests 2 and 3 until May 30, 2007. The reason for the teleconference was to request a verbal approval of an extension for Relief Requests 2 and 3 until May 30, 2007. The licensee determined that a modification to the system piping was necessary to comply withthe Code requirements. Implementation of the modification was originally planned so that the requirements of the Code could be met prior to the expiration of the interim relief period.
PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 -
However, the licensee recently identified that some components received for the modification do not reflect parameters assumed in the modification design and therefore, portions of the modification require re-analysis that will delay installation of the modification. Additionally, the onset of colder weather will decrease plant cooling water loads, thus making it difficult to achieve adequate flows for the required pump tests. The licensee requested an extension of  interim Relief Requests 2 and 3 until May 30, 2007, toallow completion of the modification and to allow testing during a period of higher cooling water loads. The staff has determined that the proposed extension to May 30, 2007, of interim Relief Requests 2 and 3 is acceptable based on the time frame required to complete installation of the modification package and to allow testing of the pumps during a period of higher cooling water loads. The current test method will continue to identify any significant degrading trends during the extension period, which will provide an adequate level of assurance of the operational readiness of the pumps. Verbal relief was granted to Prairie Island Unit 1 and 2, during the telephone conference on September 21, 2006.     
TELEPHONE CONFERENCE TO DISCUSS EXTENSION OF RELIEF REQUESTS 2 AND 3 FOR THE FOURTH 10-YEAR INSERVICE TESTING PROGRAM INTERVAL (TAC NOS. MD3123 AND MD3124)
On September 21, 2006, a conference call was held between the Nuclear Regulatory Commission (NRC) staff and the representatives of Nuclear Management Company (NMC)(the licensee), to discuss the status of an interim relief granted until September 30, 2006, to Prairie Island Nuclear Generating Plant, Units 1 and 2, for Relief Requests 2 and 3 associated with the fourth 10-year inservice testing interval.
In a letter dated June 28, 2004, NMC requested relief for Diesel-driven cooling water pumps 12 and 22, and motor-driven cooling water pump 121. Relief was requested from ISTB-3550, which requires that a rate or quantity meter be installed in each of the pump test circuits. If a meter does not indicate the flow directly, the record shall include the method used to reduce the data. The Licensee proposed alternative pump testing using non-instrumented bypass lines that feed a jacket cooler and a gear oil cooler. Additional unmetered flow feeds the chemical treatment, and filtered water system.
In a letter dated July 25, 2005, the staff evaluated these alternate methods and concluded that the bypass lines are not fixed resistance systems and fouling of the associated equipment could change the resistance of the bypass lines and potentially mask pump degradation. Long-term relief could not be granted due to the lack of information in the relief request explaining how the testing will account for potential masking of degrading flow rates.
However, interim relief was granted pursuant to 10CFR50.55a(f)(6)(i) based on the impracticality of the design and the burden that would result if the Code requirements were immediately imposed, such as a plant shutdown because testing in accordance with the Code could not be performed. The staff also concluded that the current test method will identify significant degrading trends for an interim period, providing an adequate level of assurance of the operational readiness of the pumps.
The staff further concluded that granting relief would not endanger life or property or the common defense and security and was otherwise in the public interest, giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility. The licensee was requested to respond prior to September 30, 2006, to inform the staff of actions taken to achieve compliance with the code requirements. The licensee responded in


Docket Nos. 50-282 and 50-306  Requests 2 and 3 until May 30, 2007. The reason for the teleconference was to request averbal approval of an extension for Relief Requests 2 and 3 until May 30, 2007. The licensee determined that a modification to the system piping was necessary to comply withthe Code requirements. Implementation of the modification was originally planned so that the requirements of the Code could be met prior to the expiration of the interim relief period.
a letter dated September 19, 2006, and requested an extension of the interim relief for Relief Requests 2 and 3 until May 30, 2007. The reason for the teleconference was to request a verbal approval of an extension for Relief Requests 2 and 3 until May 30, 2007.
However, the licensee recently identified that some components received for the modification do not reflect parameters assumed in the modification design and therefore, portions of the modification require re-analysis that will delay installation of the modification. Additionally, the onset of colder weather will decrease plant cooling water loads, thus making it difficult to achieve adequate flows for the required pump tests. The licensee requested an extension of interim Relief Requests 2 and 3 until May 30, 2007, toallow completion of the modification and to allow testing during a period of higher cooling water loads. The staff has determined that the proposed extension to May 30, 2007, of interim Relief Requests 2 and 3 is acceptable based on the time frame required to complete installation of the modification package and to allow testing of the pumps during a period of higher cooling water loads. The current test method will continue to identify any significant degrading trends during the extension period, which will provide an adequate level of assurance of the operational readiness of the pumps. Verbal relief was granted to Prairie Island Unit 1 and 2, during the telephone conference on September 21, 2006.    
The licensee determined that a modification to the system piping was necessary to comply with the Code requirements. Implementation of the modification was originally planned so that the requirements of the Code could be met prior to the expiration of the interim relief period.
However, the licensee recently identified that some components received for the modification do not reflect parameters assumed in the modification design and therefore, portions of the modification require re-analysis that will delay installation of the modification. Additionally, the onset of colder weather will decrease plant cooling water loads, thus making it difficult to achieve adequate flows for the required pump tests.
The licensee requested an extension of interim Relief Requests 2 and 3 until May 30, 2007, to allow completion of the modification and to allow testing during a period of higher cooling water loads. The staff has determined that the proposed extension to May 30, 2007, of interim Relief Requests 2 and 3 is acceptable based on the time frame required to complete installation of the modification package and to allow testing of the pumps during a period of higher cooling water loads. The current test method will continue to identify any significant degrading trends during the extension period, which will provide an adequate level of assurance of the operational readiness of the pumps. Verbal relief was granted to Prairie Island Unit 1 and 2, during the telephone conference on September 21, 2006.
Docket Nos. 50-282 and 50-306


Docket Nos. 50-282 and 50-306DISTRIBUTION
Requests 2 and 3 until May 30, 2007. The reason for the teleconference was to request a verbal approval of an extension for Relief Requests 2 and 3 until May 30, 2007.
:PUBLICLPLIII-1 R/FRidsNrrPMMChawlaRidsNrrLATHarris RidsNrrDorlLpleRidsOgcRpTLiuWPoertner RidsAcrsAcnwMailCenterRidsRgn3MailCenterTBloomer, EDO RIIIAccession No. ML062900037OFFICELPL3-1/PMLPL3-1/LACPTB:BCLPL3-1/BC (A)NAMEMChawlaTHarrisTLiuMMurphy DATE 10 /20/0610 /20/0610 /17/0610 /20/06OFFICIAL RECORD COPY}}
The licensee determined that a modification to the system piping was necessary to comply with the Code requirements. Implementation of the modification was originally planned so that the requirements of the Code could be met prior to the expiration of the interim relief period.
However, the licensee recently identified that some components received for the modification do not reflect parameters assumed in the modification design and therefore, portions of the modification require re-analysis that will delay installation of the modification. Additionally, the onset of colder weather will decrease plant cooling water loads, thus making it difficult to achieve adequate flows for the required pump tests.
The licensee requested an extension of interim Relief Requests 2 and 3 until May 30, 2007, to allow completion of the modification and to allow testing during a period of higher cooling water loads. The staff has determined that the proposed extension to May 30, 2007, of interim Relief Requests 2 and 3 is acceptable based on the time frame required to complete installation of the modification package and to allow testing of the pumps during a period of higher cooling water loads. The current test method will continue to identify any significant degrading trends during the extension period, which will provide an adequate level of assurance of the operational readiness of the pumps. Verbal relief was granted to Prairie Island Unit 1 and 2, during the telephone conference on September 21, 2006.
Docket Nos. 50-282 and 50-306 DISTRIBUTION:
PUBLIC                LPLIII-1 R/F            RidsNrrPMMChawla                RidsNrrLATHarris RidsNrrDorlLple        RidsOgcRp              TLiu                            WPoertner RidsAcrsAcnwMailCenter                        RidsRgn3MailCenter              TBloomer, EDO RIII Accession No. ML062900037 OFFICE    LPL3-1/PM            LPL3-1/LA              CPTB:BC              LPL3-1/BC (A)
NAME      MChawla              THarris                TLiu                MMurphy DATE       10 /20/06            10 /20/06              10 /17/06            10 /20/06 OFFICIAL RECORD COPY}}

Latest revision as of 13:07, 23 November 2019

Summary of 09/21/2006 Teleconference Re Extension of Relief Requests 2 & 3 for the Fourth 10-Year Inservice Testing Program Interval
ML062900037
Person / Time
Site: Prairie Island  Xcel Energy icon.png
Issue date: 10/20/2006
From: Mahesh Chawla
NRC/NRR/ADRO/DORL/LPLIII-1
To:
Plant Licensing Branch III-2
M. Chawla LPL3-1
References
TAC MD3123, TAC MD3124
Download: ML062900037 (3)


Text

October 20, 2006 MEMORANDUM TO: File FROM: Mahesh Chawla, Project Manager, Section 1 /RA/

Plant Licensing Branch III-1 Division of Operating Reactor Licensing

SUBJECT:

PRAIRIE ISLAND NUCLEAR GENERATING PLANT, UNITS 1 AND 2 -

TELEPHONE CONFERENCE TO DISCUSS EXTENSION OF RELIEF REQUESTS 2 AND 3 FOR THE FOURTH 10-YEAR INSERVICE TESTING PROGRAM INTERVAL (TAC NOS. MD3123 AND MD3124)

On September 21, 2006, a conference call was held between the Nuclear Regulatory Commission (NRC) staff and the representatives of Nuclear Management Company (NMC)(the licensee), to discuss the status of an interim relief granted until September 30, 2006, to Prairie Island Nuclear Generating Plant, Units 1 and 2, for Relief Requests 2 and 3 associated with the fourth 10-year inservice testing interval.

In a letter dated June 28, 2004, NMC requested relief for Diesel-driven cooling water pumps 12 and 22, and motor-driven cooling water pump 121. Relief was requested from ISTB-3550, which requires that a rate or quantity meter be installed in each of the pump test circuits. If a meter does not indicate the flow directly, the record shall include the method used to reduce the data. The Licensee proposed alternative pump testing using non-instrumented bypass lines that feed a jacket cooler and a gear oil cooler. Additional unmetered flow feeds the chemical treatment, and filtered water system.

In a letter dated July 25, 2005, the staff evaluated these alternate methods and concluded that the bypass lines are not fixed resistance systems and fouling of the associated equipment could change the resistance of the bypass lines and potentially mask pump degradation. Long-term relief could not be granted due to the lack of information in the relief request explaining how the testing will account for potential masking of degrading flow rates.

However, interim relief was granted pursuant to 10CFR50.55a(f)(6)(i) based on the impracticality of the design and the burden that would result if the Code requirements were immediately imposed, such as a plant shutdown because testing in accordance with the Code could not be performed. The staff also concluded that the current test method will identify significant degrading trends for an interim period, providing an adequate level of assurance of the operational readiness of the pumps.

The staff further concluded that granting relief would not endanger life or property or the common defense and security and was otherwise in the public interest, giving due consideration to the burden upon the licensee that could result if the requirements were imposed on the facility. The licensee was requested to respond prior to September 30, 2006, to inform the staff of actions taken to achieve compliance with the code requirements. The licensee responded in

a letter dated September 19, 2006, and requested an extension of the interim relief for Relief Requests 2 and 3 until May 30, 2007. The reason for the teleconference was to request a verbal approval of an extension for Relief Requests 2 and 3 until May 30, 2007.

The licensee determined that a modification to the system piping was necessary to comply with the Code requirements. Implementation of the modification was originally planned so that the requirements of the Code could be met prior to the expiration of the interim relief period.

However, the licensee recently identified that some components received for the modification do not reflect parameters assumed in the modification design and therefore, portions of the modification require re-analysis that will delay installation of the modification. Additionally, the onset of colder weather will decrease plant cooling water loads, thus making it difficult to achieve adequate flows for the required pump tests.

The licensee requested an extension of interim Relief Requests 2 and 3 until May 30, 2007, to allow completion of the modification and to allow testing during a period of higher cooling water loads. The staff has determined that the proposed extension to May 30, 2007, of interim Relief Requests 2 and 3 is acceptable based on the time frame required to complete installation of the modification package and to allow testing of the pumps during a period of higher cooling water loads. The current test method will continue to identify any significant degrading trends during the extension period, which will provide an adequate level of assurance of the operational readiness of the pumps. Verbal relief was granted to Prairie Island Unit 1 and 2, during the telephone conference on September 21, 2006.

Docket Nos. 50-282 and 50-306

Requests 2 and 3 until May 30, 2007. The reason for the teleconference was to request a verbal approval of an extension for Relief Requests 2 and 3 until May 30, 2007.

The licensee determined that a modification to the system piping was necessary to comply with the Code requirements. Implementation of the modification was originally planned so that the requirements of the Code could be met prior to the expiration of the interim relief period.

However, the licensee recently identified that some components received for the modification do not reflect parameters assumed in the modification design and therefore, portions of the modification require re-analysis that will delay installation of the modification. Additionally, the onset of colder weather will decrease plant cooling water loads, thus making it difficult to achieve adequate flows for the required pump tests.

The licensee requested an extension of interim Relief Requests 2 and 3 until May 30, 2007, to allow completion of the modification and to allow testing during a period of higher cooling water loads. The staff has determined that the proposed extension to May 30, 2007, of interim Relief Requests 2 and 3 is acceptable based on the time frame required to complete installation of the modification package and to allow testing of the pumps during a period of higher cooling water loads. The current test method will continue to identify any significant degrading trends during the extension period, which will provide an adequate level of assurance of the operational readiness of the pumps. Verbal relief was granted to Prairie Island Unit 1 and 2, during the telephone conference on September 21, 2006.

Docket Nos. 50-282 and 50-306 DISTRIBUTION:

PUBLIC LPLIII-1 R/F RidsNrrPMMChawla RidsNrrLATHarris RidsNrrDorlLple RidsOgcRp TLiu WPoertner RidsAcrsAcnwMailCenter RidsRgn3MailCenter TBloomer, EDO RIII Accession No. ML062900037 OFFICE LPL3-1/PM LPL3-1/LA CPTB:BC LPL3-1/BC (A)

NAME MChawla THarris TLiu MMurphy DATE 10 /20/06 10 /20/06 10 /17/06 10 /20/06 OFFICIAL RECORD COPY