| number = ML15336A894
| number = ML15336A894
| issue date = 11/20/2015
| issue date = 11/20/2015
| title = Ltr 11/20/15 Scheduling of Initial Operator License Examinations: Quad Cities Nuclear Power Station, Units 1 and 2. (Rkw)
| title = Scheduling of Initial Operator License Examinations: Quad Cities Nuclear Power Station, Units 1 and 2. (Rkw)
| author name = Peterson H
| author name = Peterson H
| author affiliation = NRC/RGN-III/DRS/OB
| author affiliation = NRC/RGN-III/DRS/OB
| addressee name = Hanson B C
| addressee name = Hanson B
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| addressee affiliation = Exelon Generation Co, LLC, Exelon Nuclear
| docket = 05000254, 05000265
| docket = 05000254, 05000265
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUIT E 210 LISLE, IL 60532
{{#Wiki_filter:UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 November 20, 2015 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555
-4352 November 20, 2015 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road
 
Warrenville, IL 60555


==SUBJECT:==
==SUBJECT:==
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS:
: QUAD CITIES NUCLEAR POWER STATION, UNIT S 1 AND 2  
QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2


==Dear Mr. Hanson:==
==Dear Mr. Hanson:==
We have received your corporate letter RS-2015-05, dated May 20, 2015
 
, and site letter MRD-15-001 dated August 20, 2015
We have received your corporate letter RS-2015-05, dated May 20, 2015, and site letter MRD-15-001 dated August 20, 2015, in response to U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations. In the letters, you requested initial operator licensing examinations be scheduled for March 2018, and March 2020 at the Quad Cities Nuclear Power Station.
, in response to U.S. Nuclear Regulatory Commission (N RC) Regulatory Issue Summary 2015
-05, "Preparation and Scheduling of Operator Licensing Examinations.In the letter s, you requested initial operator licensing examinations be scheduled for March 2018
, and March 2020 at the Quad Cities Nuclear Power Station.
In\ response, we have scheduled initial operator licensing examinations for the weeks of:
In\ response, we have scheduled initial operator licensing examinations for the weeks of:
April 9 , and 16, 2018 , with an onsite validation date the week of March 12, 2018. With consideration for future NRC resource challenges, we have adjusted your requested exam dates from your last letter dated August 20, 2015. Based on these anticipated resources challenges, the above dates have changed. Additionally we have scheduled an initial operator licensing examination for the weeks of:
* April 9, and 16, 2018, with an onsite validation date the week of March 12, 2018.
March 16 , and 23, 2020 , with an onsite validation date the week of February 1 7, 2020. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately
With consideration for future NRC resource challenges, we have adjusted your requested exam dates from your last letter dated August 20, 2015. Based on these anticipated resources challenges, the above dates have changed. Additionally we have scheduled an initial operator licensing examination for the weeks of:
, upon discovery
* March 16, and 23, 2020, with an onsite validation date the week of February 17, 2020.
, of such conditions, and make arrangements to administer the examination at a mutually acceptable date.
In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately, upon discovery, of such conditions, and make arrangements to administer the examination at a mutually acceptable date.
We understand that your staff will develop the se examination s unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than nine applicants being considered for each of these examinations, the examinations were each scheduled for two weeks. Please inform us if the number of candidates decline below nine for any examination, as this will impact the examination schedule.
We understand that your staff will develop these examinations unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than nine applicants being considered for each of these examinations, the examinations were each scheduled for two weeks. Please inform us if the number of candidates decline below nine for any examination, as this will impact the examination schedule.
Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.
Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.


A supplementary letter will be sent to the training department approximately 1 50 days prior to the examination informing the training manager of the chief examiner's name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
B. Hanson                                        A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy  
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
 
Sincerely,
of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
                                                  /RA/
-rm/adams.html (the Public Electronic Reading Room).
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254, 50-265 License Nos. DPR-29; DPR-30 cc w/encl: Distribution via LISTSERV
Sincerely, /RA/   Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50
-254, 50-265  License Nos. DPR
-29; DPR-30 cc w/encl:  Distribution via LISTSERV A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiner's name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy
 
of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
-rm/adams.html (t he Public Electronic Reading Room).
Sincerely,  /RA/  Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50
-254, 50-265 License Nos. DPR
-29; DPR-30 cc w/encl: Distribution via LISTSERV DISTRIBUTION
: Janelle Jessie RidsNrrDorlLpl3
-2 Resource RidsNrrPMQuadCities Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15336A894 Publicly Available Non-Publicly Available Sensitive  Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII  RIII  RIII  RIII  NAME RKWalton: cl HPeterson  DATE 11/20/15 11/20/15  OFFICIAL RECORD COPY


UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUIT E 210 LISLE, IL  60532
B. Hanson                                                                  A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
-4352  November 20, 2015 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely,
                                                                          /RA/
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254, 50-265 License Nos. DPR-29; DPR-30 cc w/encl: Distribution via LISTSERV DISTRIBUTION:
Janelle Jessie RidsNrrDorlLpl3-2 Resource RidsNrrPMQuadCities Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15336A894 Publicly Available                          Non-Publicly Available                    Sensitive                Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE              RIII                                RIII                                RIII                          RIII NAME                RKWalton:cl                        HPeterson DATE                11/20/15                            11/20/15 OFFICIAL RECORD COPY


Warrenville, IL 60555
UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 November 20, 2015 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555


==SUBJECT:==
==SUBJECT:==
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS
SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS:
: QUAD CITIES NUCLEAR POWER STATION, UNIT S 1 AND 2  
QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2


==Dear Mr. Hanson:==
==Dear Mr. Hanson:==
We have received your corporate letter RS-2015-05, dated May 20, 2015
 
, and site letter MRD-15-001 dated August 20, 2015
We have received your corporate letter RS-2015-05, dated May 20, 2015, and site letter MRD-15-001 dated August 20, 2015, in response to U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations. In the letters, you requested initial operator licensing examinations be scheduled for March 2018, and March 2020 at the Quad Cities Nuclear Power Station.
, in response to U.S. Nuclear Regulatory Commission (N RC) Regulatory Issue Summary 2015
-05, "Preparation and Scheduling of Operator Licensing Examinations.In the letter s, you requested initial operator licensing examinations be scheduled for March 2018
, and March 2020 at the Quad Cities Nuclear Power Station.
In\ response, we have scheduled initial operator licensing examinations for the weeks of:
In\ response, we have scheduled initial operator licensing examinations for the weeks of:
April 9 , and 16, 2018 , with an onsite validation date the week of March 12, 2018. With consideration for future NRC resource challenges, we have adjusted your requested exam dates from your last letter dated August 20, 2015. Based on these anticipated resources challenges, the above dates have changed. Additionally we have scheduled an initial operator licensing examination for the weeks of:
* April 9, and 16, 2018, with an onsite validation date the week of March 12, 2018.
March 16 , and 23, 2020 , with an onsite validation date the week of February 1 7, 2020. In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately
With consideration for future NRC resource challenges, we have adjusted your requested exam dates from your last letter dated August 20, 2015. Based on these anticipated resources challenges, the above dates have changed. Additionally we have scheduled an initial operator licensing examination for the weeks of:
, upon discovery
* March 16, and 23, 2020, with an onsite validation date the week of February 17, 2020.
, of such conditions, and make arrangements to administer the examination at a mutually acceptable date.
In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately, upon discovery, of such conditions, and make arrangements to administer the examination at a mutually acceptable date.
We understand that your staff will develop the se examination s unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than nine applicants being considered for each of these examinations, the examinations were each scheduled for two weeks. Please inform us if the number of candidates decline below nine for any examination, as this will impact the examination schedule.
We understand that your staff will develop these examinations unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than nine applicants being considered for each of these examinations, the examinations were each scheduled for two weeks. Please inform us if the number of candidates decline below nine for any examination, as this will impact the examination schedule.
Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.
Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.


A supplementary letter will be sent to the training department approximately 1 50 days prior to the examination informing the training manager of the chief examiner's name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
B. Hanson                                        A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy  
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
 
Sincerely,
of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
                                                  /RA/
-rm/adams.html (the Public Electronic Reading Room).
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254, 50-265 License Nos. DPR-29; DPR-30 cc w/encl: Distribution via LISTSERV
Sincerely, /RA/   Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50
-254, 50-265 License Nos. DPR
-29; DPR-30 cc w/encl: Distribution via LISTSERV A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiner's name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, "Public Inspections, Exemptions, Requests for Withholding," of the NRC's "Rules of Practice," a copy


of this letter will be available electronically for public inspection in the NRC's Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading
B. Hanson                                                                  A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.
-rm/adams.html (t he Public Electronic Reading Room).
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Sincerely, /RA/   Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50
Sincerely,
-254, 50-265 License Nos. DPR
                                                                          /RA/
-29; DPR-30 cc w/encl: Distribution via LISTSERV DISTRIBUTION
Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254, 50-265 License Nos. DPR-29; DPR-30 cc w/encl: Distribution via LISTSERV DISTRIBUTION:
: Janelle Jessie RidsNrrDorlLpl3
Janelle Jessie RidsNrrDorlLpl3-2 Resource RidsNrrPMQuadCities Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15336A894 Publicly Available                           Non-Publicly Available                     Sensitive               Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE             RIII                               RIII                                 RIII                           RIII NAME               RKWalton:cl                         HPeterson DATE               11/20/15                           11/20/15 OFFICIAL RECORD COPY}}
-2 Resource RidsNrrPMQuadCities Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15336A894 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME RKWalton: cl HPeterson   DATE 11/20/15 11/20/15   OFFICIAL RECORD COPY}}

Latest revision as of 22:03, 16 November 2019

Scheduling of Initial Operator License Examinations: Quad Cities Nuclear Power Station, Units 1 and 2. (Rkw)
ML15336A894
Person / Time
Site: Quad Cities  Constellation icon.png
Issue date: 11/20/2015
From: Hironori Peterson
Operations Branch III
To: Bryan Hanson
Exelon Generation Co, Exelon Nuclear
References
Download: ML15336A894 (3)


Text

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 November 20, 2015 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS:

QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2

Dear Mr. Hanson:

We have received your corporate letter RS-2015-05, dated May 20, 2015, and site letter MRD-15-001 dated August 20, 2015, in response to U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations. In the letters, you requested initial operator licensing examinations be scheduled for March 2018, and March 2020 at the Quad Cities Nuclear Power Station.

In\ response, we have scheduled initial operator licensing examinations for the weeks of:

  • April 9, and 16, 2018, with an onsite validation date the week of March 12, 2018.

With consideration for future NRC resource challenges, we have adjusted your requested exam dates from your last letter dated August 20, 2015. Based on these anticipated resources challenges, the above dates have changed. Additionally we have scheduled an initial operator licensing examination for the weeks of:

  • March 16, and 23, 2020, with an onsite validation date the week of February 17, 2020.

In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately, upon discovery, of such conditions, and make arrangements to administer the examination at a mutually acceptable date.

We understand that your staff will develop these examinations unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than nine applicants being considered for each of these examinations, the examinations were each scheduled for two weeks. Please inform us if the number of candidates decline below nine for any examination, as this will impact the examination schedule.

Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.

B. Hanson A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254, 50-265 License Nos. DPR-29; DPR-30 cc w/encl: Distribution via LISTSERV

B. Hanson A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254, 50-265 License Nos. DPR-29; DPR-30 cc w/encl: Distribution via LISTSERV DISTRIBUTION:

Janelle Jessie RidsNrrDorlLpl3-2 Resource RidsNrrPMQuadCities Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15336A894 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME RKWalton:cl HPeterson DATE 11/20/15 11/20/15 OFFICIAL RECORD COPY

UNITED STATES NUCLEAR REGULATORY COMMISSION REGION III 2443 WARRENVILLE RD. SUITE 210 LISLE, IL 60532-4352 November 20, 2015 Mr. Bryan C. Hanson Senior VP, Exelon Generation Company, LLC President and CNO, Exelon Nuclear 4300 Winfield Road Warrenville, IL 60555

SUBJECT:

SCHEDULING OF INITIAL OPERATOR LICENSE EXAMINATIONS:

QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2

Dear Mr. Hanson:

We have received your corporate letter RS-2015-05, dated May 20, 2015, and site letter MRD-15-001 dated August 20, 2015, in response to U.S. Nuclear Regulatory Commission (NRC) Regulatory Issue Summary 2015-05, Preparation and Scheduling of Operator Licensing Examinations. In the letters, you requested initial operator licensing examinations be scheduled for March 2018, and March 2020 at the Quad Cities Nuclear Power Station.

In\ response, we have scheduled initial operator licensing examinations for the weeks of:

  • April 9, and 16, 2018, with an onsite validation date the week of March 12, 2018.

With consideration for future NRC resource challenges, we have adjusted your requested exam dates from your last letter dated August 20, 2015. Based on these anticipated resources challenges, the above dates have changed. Additionally we have scheduled an initial operator licensing examination for the weeks of:

  • March 16, and 23, 2020, with an onsite validation date the week of February 17, 2020.

In the unlikely event that we are unable to support the examination during the scheduled weeks, we will inform you immediately, upon discovery, of such conditions, and make arrangements to administer the examination at a mutually acceptable date.

We understand that your staff will develop these examinations unless we determine it is necessary for the NRC to develop an examination in which case, we will notify you immediately upon discovery of that need. Because your letter indicated that there were more than nine applicants being considered for each of these examinations, the examinations were each scheduled for two weeks. Please inform us if the number of candidates decline below nine for any examination, as this will impact the examination schedule.

Also, please inform us at your earliest opportunity if you discover you need to change the scheduled dates for the examinations.

B. Hanson A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254, 50-265 License Nos. DPR-29; DPR-30 cc w/encl: Distribution via LISTSERV

B. Hanson A supplementary letter will be sent to the training department approximately 150 days prior to the examination informing the training manager of the chief examiners name. This corporate notification letter will also outline examination security expectations, list the materials required by the NRC to conduct the examination, reconfirm the examination date, and reconfirm the number of candidates you have in the Training Program.

In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390, Public Inspections, Exemptions, Requests for Withholding, of the NRC's "Rules of Practice," a copy of this letter will be available electronically for public inspection in the NRCs Public Document Room or from the Publicly Available Records (PARS) component of the NRC's Agencywide Documents Access and Management System (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).

Sincerely,

/RA/

Hironori Peterson, Chief Operations Branch Division of Reactor Safety Docket Nos. 50-254, 50-265 License Nos. DPR-29; DPR-30 cc w/encl: Distribution via LISTSERV DISTRIBUTION:

Janelle Jessie RidsNrrDorlLpl3-2 Resource RidsNrrPMQuadCities Resource RidsNrrDirsIrib Resource Cynthia Pederson Darrell Roberts Richard Skokowski Allan Barker Carole Ariano Linda Linn DRPIII DRSIII Jim Clay Carmen Olteanu ADAMS Accession Number ML15336A894 Publicly Available Non-Publicly Available Sensitive Non-Sensitive To receive a copy of this document, indicate in the concurrence box "C" = Copy without attach/encl "E" = Copy with attach/encl "N" = No copy OFFICE RIII RIII RIII RIII NAME RKWalton:cl HPeterson DATE 11/20/15 11/20/15 OFFICIAL RECORD COPY