ML103300217: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
(Created page by program invented by StriderTol)
 
(2 intermediate revisions by the same user not shown)
Line 13: Line 13:
| page count = 6
| page count = 6
}}
}}
See also: [[followed by::IR 05000391/2010603]]


=Text=
=Text=
{{#Wiki_filter:Tennessee  
{{#Wiki_filter:Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 10 CFR 2.201 November 24, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391
Valley Authority, Post Office Box 2000, Spring City, Tennessee  
 
37381-2000
==Subject:==
10 CFR 2.201 November 24, 2010 U.S. Nuclear Regulatory  
Watts Bar Nuclear Plant Unit 2 - Reply to Notice of Violation 05000391/2010603 Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers
Commission
 
ATTN: Document Control Desk Washington, D.C. 20555-0001
==References:==
Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391 Subject: Watts Bar Nuclear Plant Unit 2 -Reply to Notice of Violation 05000391/2010603-08
: 1. NRC letter to TVA, 'Watts Bar Nuclear Plant Unit 2 Construction -
-Failure to Adequately  
NRC Integrated Inspection Report 05000391/2010603 and Notice of Violation," dated August 5, 2010 (ML102170465)
Evaluate and Qualify Molded Case Circuit Breakers References:  
: 2. TVA letter to NRC, "Watts Bar Nuclear Plant (WBN) Unit 2 - Denial of Notice of Violation (NOV) 05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers,"
1. NRC letter to TVA, 'Watts Bar Nuclear Plant Unit 2 Construction  
dated September 7, 2010 (ML102520435)
-NRC Integrated  
: 3. TVA letter to NRC, 'Watts Bar Nuclear Plant (WBN) Unit 2 - Denial of Notice of Violation (NOV) 05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers -
Inspection  
Additional Information," dated October 15, 2010 (ML102880493)
Report 05000391/2010603  
: 4. NRC letter to TVA, "Response to Disputed Notice of Violation (NOV) 05000391/2010603-08," dated October 19, 2010 (ML102920665)
and Notice of Violation," dated August 5, 2010 (ML1 02170465)2. TVA letter to NRC, "Watts Bar Nuclear Plant (WBN) Unit 2 -Denial of Notice of Violation (NOV) 05000391/2010603-08, Failure to Adequately  
The purpose of this letter is to further respond to Notice of Violation 391/2010603-08, "Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers." NRC issued the NOV in a letter dated August 5, 2010 (Reference 1). TVA initially denied the violation in a letter dated September 7, 2010 (Reference 2), and provided additional information in a letter dated October 15, 2010 (Reference 3). NRC subsequently
Evaluate and Qualify Molded Case Circuit Breakers," dated September  
 
7, 2010 (ML1 02520435)3. TVA letter to NRC, 'Watts Bar Nuclear Plant (WBN) Unit 2 -Denial of Notice of Violation (NOV) 05000391/2010603-08, Failure to Adequately  
U.S. Nuclear Regulatory Commission Page 2 November 24, 2010 concluded that the violation occurred as stated in a letter dated October 19, 2010 (Reference 4).
Evaluate and Qualify Molded Case Circuit Breakers -Additional  
TVA admits that the violation occurred and provides its reply in Enclosure 1. provides the list of commitments made in this letter.
Information," dated October 15, 2010 (ML102880493)
The schedule for submitting this reply was discussed between William Crouch and Mark Lesser on November 19, 2010. If you have any questions, please contact William Crouch at (423) 365-2004.
4. NRC letter to TVA, "Response  
I declare under penalty of perjury that the foregoing is true and correct. Executed on the 2 4 th day of November, 2010.
to Disputed Notice of Violation (NOV)05000391/2010603-08," dated October 19, 2010 (ML102920665)
Sincerely, 9/
The purpose of this letter is to further respond to Notice of Violation  
Masoud           stani Watts       r   nit 2 Vice President Encl     ures
391/2010603-08,"Failure to Adequately  
: 1.     TVA's Reply to the Notice of Violation 391/2010603-08
Evaluate and Qualify Molded Case Circuit Breakers." NRC issued the NOV in a letter dated August 5, 2010 (Reference  
: 2.     List of Commitments cc (Enclosures):
1). TVA initially  
U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381
denied the violation  
 
in a letter dated September  
Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV) 05000391/2010603-08" Description of the Violation "10 CFR 50, Appendix B, Criterion Ill, "Design Control,"states that measures shall be establishedfor the review for suitabilityof applicationof materials,parts, and equipment that are essentialto the safety-related functions of the structures,systems, and components (SSCs). The design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternateor simplified calculationalmethods, or by the performance of a suitable testing program. Where a test program is used to verify the adequacy of a specific design feature in lieu of other verifying or checking processes,it shall include suitable qualificationstesting of a prototype unit under the most adverse design conditions.
7, 2010 (Reference  
Contraryto the above, measures used to review the suitabilityof application of materials, parts, and equipment essential to the safety-related functions of molded case circuit breakers and measures to provide for the verification of checking the adequacy of design, such as, calculationalmethods, performing a suitable test program,including qualificationstesting of a prototype unit under the most adverse design conditions, were not adequate in that:
2), and provided additional
Example I On October 5, 2009, the applicantinstalledmolded case circuit breakers into the 120VAC vital instrument power boards;however, the test program used to seismically qualify a prototype circuit breaker failed to use a suitable mounting method that reflected the most adverse mounting condition."
information  
TVA Response:
in a letter dated October 15, 2010 (Reference  
TVA admits that the violation occurred.
3). NRC subsequently  
Reason For The Violation - Example 1:
U.S. Nuclear Regulatory  
The reason for this violation is that Calculation WCG-ACQ-1 004 failed to fully establish that (1) the 1992 test mounting represented a suitable mounting method and that (2) the 1992 test bounded the configuration of the breakers installed in 2009. The calculation should have identified that the method of support for breakers within the board was a rigid mounting system which would have justified the 1992 testing for replacement breakers.
Commission
Corrective Steps That Have Been Taken And The Results Achieved (Example 1):
Page 2 November 24, 2010 concluded  
: 1. TVA performed Calculation WCG-ACQ-1301 to verify the rigidity of the panel assembly.
that the violation  
Corrective Steps That Will Be Taken:
occurred as stated in a letter dated October 19, 2010 (Reference  
: 1. TVA will revise calculation WCG-ACQ-1004 to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement breaker testing.
4).TVA admits that the violation  
E1-1
occurred and provides its reply in Enclosure  
 
1.Enclosure
Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV) 05000391/2010603-08"
2 provides the list of commitments  
: 2. As an enhancement to address any potentially misaligned breakers, TVA will review WBN maintenance and Unit 2 refurbishment procedures to ensure that the design basis for the breakers is maintained by: 1) that the procedures provide sufficient guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately through the front-face panel openings after any maintenance involving full or partial removal of the front-face panel. In addition, the review will determine whether directions are needed to avoid excessive clamping pressure and to implement simple checks to status and correct for minor irregularities in contact between the Micarta insulation board and rear angles. Based on this review, TVA will determine the appropriate implementing documents to be revised.
made in this letter.The schedule for submitting  
: 3. TVA will evaluate the installed breakers to ensure breaker operation will not be affected by the applied clamping breakers.
this reply was discussed  
Date When Full Compliance Will Be Achieved.
between William Crouch and Mark Lesser on November 19, 2010. If you have any questions, please contact William Crouch at (423) 365-2004.I declare under penalty of perjury that the foregoing  
TVA will be in full compliance by March 18, 2011.
is true and correct. Executed on the 2 4 th day of November, 2010.Sincerely, 9/Masoud stani Watts r nit 2 Vice President Encl ures 1. TVA's Reply to the Notice of Violation  
Example 2 "On September 3, 2009, the applicantfailed to perform an adequate review for suitability of applicationparts and materialused to modify dimensional criticalcharacteristicsin molded case circuit breakers; further, the applicant failed to verify the adequacy of design for the modification and the effects on essential safety related functions of the circuit breakers."
391/2010603-08
Reason For The Violation - Example 2:
2. List of Commitments
The reason for this violation is that the manufacturer made a production change to the breaker configuration but did not revise the model number or publish schematics to reflect a component change. As a result, TVA failed to identify a change in a critical characteristic (i.e., the required mounting depth between the front face and the rear angles) and the resulting impact on device seismic qualification and functionality. Rather than performing a new equivalency evaluation, TVA applied a technical evaluation for the original breakers and concluded that the breakers were seismically and functionally qualified.
cc (Enclosures):
Corrective Steps That Have Been Taken And The Results Achieved (Example 2):
U. S. Nuclear Regulatory  
: 1. TVA performed an equivalency evaluation for the reconfigured Heinemann breakers that identifies the critical characteristics, addresses the role of the Micarta insulation board in restoring the needed mounting depth for contact between the rear angles and front-face panel, and addresses seismic qualification requirements.
Commission
: 2. A unique identifier (CATID) was established for the reconfigured breaker to be used for future purchases of reconfigured breakers for WBN Units 1 and 2. Use of a unique ID will distinguish the reconfigured breakers from the original breakers.
Region II Marquis One Tower 245 Peachtree  
E1-2
Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257
 
NRC Resident Inspector  
Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV) 05000391/2010603-08"
Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee  
: 3. As an enhancement, TVA updated both the TVA and Westinghouse drawings to ensure consistency between drawings and with the installed configuration.
37381
Corrective Steps That Will Be Taken:
Enclosure  
: 1. Instructions will be issued to procurement and engineering organizations providing the necessary direction to use the unique CATID described above which will distinguish the reconfigured breakers from the original breakers. The CATID for original breakers will be retained to support the existing qualification of replacement original breakers procured in the past.
I Watts Bar Nuclear Plant (WBN) Unit 2"Response  
: 2. TVA will revise calculation WCG-ACQ-1004 to confirm the design basis performance of the reconfigured breaker in support of the equivalency evaluation (i.e.,
to Notice of Violation (NOV) 05000391/2010603-08" Description  
demonstrate the breaker will function as designed with the current configuration of breaker and spacer board attachment in the clamping arrangement of rear angles and front-face panel sections).
of the Violation"10 CFR 50, Appendix B, Criterion  
Date When Full Compliance Will Be Achieved.
Ill, "Design Control, "states that measures shall be established
TVA will be in full compliance by March 18, 2011.
for the review for suitability
E1-3
of application
 
of materials, parts, and equipment that are essential
I ý Enclosure 2 List of Commitments Example 1
to the safety-related  
: 1. TVA will revise calculation WCG-ACQ-1004 to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement breaker testing.
functions  
: 2. As an enhancement to address any potentially misaligned breakers, TVA will review WBN maintenance and Unit 2 refurbishment procedures to ensure that the design basis for the breakers is maintained by the following: 1) that the procedures provide sufficient guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately through the front-face panel openings after any maintenance involving full or partial removal of the front-face panel. In addition, the review will determine whether directions are needed to avoid excessive clamping pressure and to implement simple checks to status and correct for minor irregularities in contact between the Micarta insulation board and rear angles. Based on the above review, TVA will determine the appropriate implementing documents to be revised.
of the structures, systems, and components (SSCs). The design control measures shall provide for verifying  
: 3. TVA will evaluate the installed breakers to ensure breaker operation will not be affected by the applied clamping breakers.
or checking the adequacy of design, such as by the performance  
Example 2
of design reviews, by the use of alternate
: 1. Instructions will be issued to procurement and engineering organizations providing the necessary direction to use the unique CATID described above which will distinguish the reconfigured breakers from the original breakers. The CATID for original breakers will be retained to support the existing qualification of replacement original breakers procured in the past.
or simplified  
: 2. TVA will revise calculation WCG-ACQ-1004 to confirm the design basis performance of the reconfigured breaker in support of the equivalency evaluation (i.e.,
calculational
demonstrate the breaker will function as designed with the current configuration of breaker and spacer board attachment in the clamping arrangement of rear angles and front-face panel sections).
methods, or by the performance  
Date When Full Compliance Will Be Achieved.
of a suitable testing program. Where a test program is used to verify the adequacy of a specific design feature in lieu of other verifying  
TVA will be in full compliance by March 18, 2011.
or checking processes, it shall include suitable qualifications
E2-1}}
testing of a prototype  
unit under the most adverse design conditions.
Contrary to the above, measures used to review the suitability
of application  
of materials, parts, and equipment  
essential  
to the safety-related  
functions  
of molded case circuit breakers and measures to provide for the verification  
of checking the adequacy of design, such as, calculational
methods, performing  
a suitable test program, including qualifications
testing of a prototype  
unit under the most adverse design conditions, were not adequate in that: Example I On October 5, 2009, the applicant
installed
molded case circuit breakers into the 120VAC vital instrument  
power boards; however, the test program used to seismically
qualify a prototype  
circuit breaker failed to use a suitable mounting method that reflected the most adverse mounting condition." TVA Response: TVA admits that the violation  
occurred.Reason For The Violation  
-Example 1: The reason for this violation  
is that Calculation  
WCG-ACQ-1  
004 failed to fully establish that (1) the 1992 test mounting represented  
a suitable mounting method and that (2) the 1992 test bounded the configuration  
of the breakers installed  
in 2009. The calculation
should have identified  
that the method of support for breakers within the board was a rigid mounting system which would have justified  
the 1992 testing for replacement
breakers.Corrective  
Steps That Have Been Taken And The Results Achieved (Example 1): 1. TVA performed  
Calculation  
WCG-ACQ-1301  
to verify the rigidity of the panel assembly.Corrective  
Steps That Will Be Taken: 1. TVA will revise calculation  
WCG-ACQ-1004  
to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement  
breaker testing.E1-1  
Enclosure  
I Watts Bar Nuclear Plant (WBN) Unit 2"Response  
to Notice of Violation (NOV) 05000391/2010603-08" 2. As an enhancement  
to address any potentially  
misaligned  
breakers, TVA will review WBN maintenance  
and Unit 2 refurbishment  
procedures  
to ensure that the design basis for the breakers is maintained  
by: 1) that the procedures  
provide sufficient
guidance that the breakers make positive contact with the angles in the rear, and 2)that the breakers project appropriately  
through the front-face  
panel openings after any maintenance  
involving  
full or partial removal of the front-face  
panel. In addition, the review will determine  
whether directions  
are needed to avoid excessive  
clamping pressure and to implement  
simple checks to status and correct for minor irregularities  
in contact between the Micarta insulation  
board and rear angles. Based on this review, TVA will determine  
the appropriate  
implementing  
documents  
to be revised.3. TVA will evaluate the installed  
breakers to ensure breaker operation  
will not be affected by the applied clamping breakers.Date When Full Compliance  
Will Be Achieved.TVA will be in full compliance  
by March 18, 2011.Example 2"On September  
3, 2009, the applicant
failed to perform an adequate review for suitability
of application
parts and material used to modify dimensional  
critical characteristics
in molded case circuit breakers;  
further, the applicant  
failed to verify the adequacy of design for the modification  
and the effects on essential  
safety related functions  
of the circuit breakers." Reason For The Violation  
-Example 2: The reason for this violation  
is that the manufacturer  
made a production  
change to the breaker configuration  
but did not revise the model number or publish schematics  
to reflect a component  
change. As a result, TVA failed to identify a change in a critical characteristic (i.e., the required mounting depth between the front face and the rear angles) and the resulting  
impact on device seismic qualification  
and functionality.  
Rather than performing  
a new equivalency  
evaluation, TVA applied a technical  
evaluation  
for the original breakers and concluded  
that the breakers were seismically  
and functionally
qualified.
Corrective  
Steps That Have Been Taken And The Results Achieved (Example 2): 1. TVA performed  
an equivalency  
evaluation  
for the reconfigured  
Heinemann  
breakers that identifies  
the critical characteristics, addresses  
the role of the Micarta insulation
board in restoring  
the needed mounting depth for contact between the rear angles and front-face  
panel, and addresses  
seismic qualification  
requirements.
2. A unique identifier (CATID) was established  
for the reconfigured  
breaker to be used for future purchases  
of reconfigured  
breakers for WBN Units 1 and 2. Use of a unique ID will distinguish  
the reconfigured  
breakers from the original breakers.E1-2  
Enclosure  
I Watts Bar Nuclear Plant (WBN) Unit 2"Response  
to Notice of Violation (NOV) 05000391/2010603-08" 3. As an enhancement, TVA updated both the TVA and Westinghouse  
drawings to ensure consistency  
between drawings and with the installed  
configuration.
Corrective  
Steps That Will Be Taken: 1. Instructions  
will be issued to procurement  
and engineering  
organizations  
providing the necessary  
direction  
to use the unique CATID described  
above which will distinguish  
the reconfigured  
breakers from the original breakers.  
The CATID for original breakers will be retained to support the existing qualification  
of replacement
original breakers procured in the past.2. TVA will revise calculation  
WCG-ACQ-1004  
to confirm the design basis performance
of the reconfigured  
breaker in support of the equivalency  
evaluation (i.e., demonstrate  
the breaker will function as designed with the current configuration  
of breaker and spacer board attachment  
in the clamping arrangement  
of rear angles and front-face  
panel sections).
Date When Full Compliance  
Will Be Achieved.TVA will be in full compliance  
by March 18, 2011.E1-3  
I ýEnclosure  
2 List of Commitments
Example 1 1. TVA will revise calculation  
WCG-ACQ-1004  
to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement  
breaker testing.2. As an enhancement  
to address any potentially  
misaligned  
breakers, TVA will review WBN maintenance  
and Unit 2 refurbishment  
procedures  
to ensure that the design basis for the breakers is maintained  
by the following:  
1) that the procedures  
provide sufficient  
guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately  
through the front-face  
panel openings after any maintenance  
involving  
full or partial removal of the front-face
panel. In addition, the review will determine  
whether directions  
are needed to avoid excessive  
clamping pressure and to implement  
simple checks to status and correct for minor irregularities  
in contact between the Micarta insulation  
board and rear angles. Based on the above review, TVA will determine  
the appropriate
implementing  
documents  
to be revised.3. TVA will evaluate the installed  
breakers to ensure breaker operation  
will not be affected by the applied clamping breakers.Example 2 1. Instructions  
will be issued to procurement  
and engineering  
organizations  
providing the necessary  
direction  
to use the unique CATID described  
above which will distinguish  
the reconfigured  
breakers from the original breakers.  
The CATID for original breakers will be retained to support the existing qualification  
of replacement
original breakers procured in the past.2. TVA will revise calculation  
WCG-ACQ-1004  
to confirm the design basis performance
of the reconfigured  
breaker in support of the equivalency  
evaluation (i.e., demonstrate  
the breaker will function as designed with the current configuration  
of breaker and spacer board attachment  
in the clamping arrangement  
of rear angles and front-face  
panel sections).
Date When Full Compliance  
Will Be Achieved.TVA will be in full compliance  
by March 18, 2011.E2-1
}}

Latest revision as of 05:45, 13 November 2019

Reply to Notice of Violation 05000391/2010603-08 - Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers
ML103300217
Person / Time
Site: Watts Bar Tennessee Valley Authority icon.png
Issue date: 11/24/2010
From: Bajestani M
Tennessee Valley Authority
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
Download: ML103300217 (6)


Text

Tennessee Valley Authority, Post Office Box 2000, Spring City, Tennessee 37381-2000 10 CFR 2.201 November 24, 2010 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D.C. 20555-0001 Watts Bar Nuclear Plant, Unit 2 NRC Docket No. 50-391

Subject:

Watts Bar Nuclear Plant Unit 2 - Reply to Notice of Violation 05000391/2010603 Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers

References:

1. NRC letter to TVA, 'Watts Bar Nuclear Plant Unit 2 Construction -

NRC Integrated Inspection Report 05000391/2010603 and Notice of Violation," dated August 5, 2010 (ML102170465)

2. TVA letter to NRC, "Watts Bar Nuclear Plant (WBN) Unit 2 - Denial of Notice of Violation (NOV)05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers,"

dated September 7, 2010 (ML102520435)

3. TVA letter to NRC, 'Watts Bar Nuclear Plant (WBN) Unit 2 - Denial of Notice of Violation (NOV)05000391/2010603-08, Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers -

Additional Information," dated October 15, 2010 (ML102880493)

4. NRC letter to TVA, "Response to Disputed Notice of Violation (NOV)05000391/2010603-08," dated October 19, 2010 (ML102920665)

The purpose of this letter is to further respond to Notice of Violation 391/2010603-08, "Failure to Adequately Evaluate and Qualify Molded Case Circuit Breakers." NRC issued the NOV in a letter dated August 5, 2010 (Reference 1). TVA initially denied the violation in a letter dated September 7, 2010 (Reference 2), and provided additional information in a letter dated October 15, 2010 (Reference 3). NRC subsequently

U.S. Nuclear Regulatory Commission Page 2 November 24, 2010 concluded that the violation occurred as stated in a letter dated October 19, 2010 (Reference 4).

TVA admits that the violation occurred and provides its reply in Enclosure 1. provides the list of commitments made in this letter.

The schedule for submitting this reply was discussed between William Crouch and Mark Lesser on November 19, 2010. If you have any questions, please contact William Crouch at (423) 365-2004.

I declare under penalty of perjury that the foregoing is true and correct. Executed on the 2 4 th day of November, 2010.

Sincerely, 9/

Masoud stani Watts r nit 2 Vice President Encl ures

1. TVA's Reply to the Notice of Violation 391/2010603-08
2. List of Commitments cc (Enclosures):

U. S. Nuclear Regulatory Commission Region II Marquis One Tower 245 Peachtree Center Ave., NE Suite 1200 Atlanta, Georgia 30303-1257 NRC Resident Inspector Unit 2 Watts Bar Nuclear Plant 1260 Nuclear Plant Road Spring City, Tennessee 37381

Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV)05000391/2010603-08" Description of the Violation "10 CFR 50, Appendix B, Criterion Ill, "Design Control,"states that measures shall be establishedfor the review for suitabilityof applicationof materials,parts, and equipment that are essentialto the safety-related functions of the structures,systems, and components (SSCs). The design control measures shall provide for verifying or checking the adequacy of design, such as by the performance of design reviews, by the use of alternateor simplified calculationalmethods, or by the performance of a suitable testing program. Where a test program is used to verify the adequacy of a specific design feature in lieu of other verifying or checking processes,it shall include suitable qualificationstesting of a prototype unit under the most adverse design conditions.

Contraryto the above, measures used to review the suitabilityof application of materials, parts, and equipment essential to the safety-related functions of molded case circuit breakers and measures to provide for the verification of checking the adequacy of design, such as, calculationalmethods, performing a suitable test program,including qualificationstesting of a prototype unit under the most adverse design conditions, were not adequate in that:

Example I On October 5, 2009, the applicantinstalledmolded case circuit breakers into the 120VAC vital instrument power boards;however, the test program used to seismically qualify a prototype circuit breaker failed to use a suitable mounting method that reflected the most adverse mounting condition."

TVA Response:

TVA admits that the violation occurred.

Reason For The Violation - Example 1:

The reason for this violation is that Calculation WCG-ACQ-1 004 failed to fully establish that (1) the 1992 test mounting represented a suitable mounting method and that (2) the 1992 test bounded the configuration of the breakers installed in 2009. The calculation should have identified that the method of support for breakers within the board was a rigid mounting system which would have justified the 1992 testing for replacement breakers.

Corrective Steps That Have Been Taken And The Results Achieved (Example 1):

1. TVA performed Calculation WCG-ACQ-1301 to verify the rigidity of the panel assembly.

Corrective Steps That Will Be Taken:

1. TVA will revise calculation WCG-ACQ-1004 to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement breaker testing.

E1-1

Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV)05000391/2010603-08"

2. As an enhancement to address any potentially misaligned breakers, TVA will review WBN maintenance and Unit 2 refurbishment procedures to ensure that the design basis for the breakers is maintained by: 1) that the procedures provide sufficient guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately through the front-face panel openings after any maintenance involving full or partial removal of the front-face panel. In addition, the review will determine whether directions are needed to avoid excessive clamping pressure and to implement simple checks to status and correct for minor irregularities in contact between the Micarta insulation board and rear angles. Based on this review, TVA will determine the appropriate implementing documents to be revised.
3. TVA will evaluate the installed breakers to ensure breaker operation will not be affected by the applied clamping breakers.

Date When Full Compliance Will Be Achieved.

TVA will be in full compliance by March 18, 2011.

Example 2 "On September 3, 2009, the applicantfailed to perform an adequate review for suitability of applicationparts and materialused to modify dimensional criticalcharacteristicsin molded case circuit breakers; further, the applicant failed to verify the adequacy of design for the modification and the effects on essential safety related functions of the circuit breakers."

Reason For The Violation - Example 2:

The reason for this violation is that the manufacturer made a production change to the breaker configuration but did not revise the model number or publish schematics to reflect a component change. As a result, TVA failed to identify a change in a critical characteristic (i.e., the required mounting depth between the front face and the rear angles) and the resulting impact on device seismic qualification and functionality. Rather than performing a new equivalency evaluation, TVA applied a technical evaluation for the original breakers and concluded that the breakers were seismically and functionally qualified.

Corrective Steps That Have Been Taken And The Results Achieved (Example 2):

1. TVA performed an equivalency evaluation for the reconfigured Heinemann breakers that identifies the critical characteristics, addresses the role of the Micarta insulation board in restoring the needed mounting depth for contact between the rear angles and front-face panel, and addresses seismic qualification requirements.
2. A unique identifier (CATID) was established for the reconfigured breaker to be used for future purchases of reconfigured breakers for WBN Units 1 and 2. Use of a unique ID will distinguish the reconfigured breakers from the original breakers.

E1-2

Enclosure I Watts Bar Nuclear Plant (WBN) Unit 2 "Response to Notice of Violation (NOV)05000391/2010603-08"

3. As an enhancement, TVA updated both the TVA and Westinghouse drawings to ensure consistency between drawings and with the installed configuration.

Corrective Steps That Will Be Taken:

1. Instructions will be issued to procurement and engineering organizations providing the necessary direction to use the unique CATID described above which will distinguish the reconfigured breakers from the original breakers. The CATID for original breakers will be retained to support the existing qualification of replacement original breakers procured in the past.
2. TVA will revise calculation WCG-ACQ-1004 to confirm the design basis performance of the reconfigured breaker in support of the equivalency evaluation (i.e.,

demonstrate the breaker will function as designed with the current configuration of breaker and spacer board attachment in the clamping arrangement of rear angles and front-face panel sections).

Date When Full Compliance Will Be Achieved.

TVA will be in full compliance by March 18, 2011.

E1-3

I ý Enclosure 2 List of Commitments Example 1

1. TVA will revise calculation WCG-ACQ-1004 to address the method of support for breakers within the board as a rigid mounting system which will validate taking credit for the 1992 replacement breaker testing.
2. As an enhancement to address any potentially misaligned breakers, TVA will review WBN maintenance and Unit 2 refurbishment procedures to ensure that the design basis for the breakers is maintained by the following: 1) that the procedures provide sufficient guidance that the breakers make positive contact with the angles in the rear, and 2) that the breakers project appropriately through the front-face panel openings after any maintenance involving full or partial removal of the front-face panel. In addition, the review will determine whether directions are needed to avoid excessive clamping pressure and to implement simple checks to status and correct for minor irregularities in contact between the Micarta insulation board and rear angles. Based on the above review, TVA will determine the appropriate implementing documents to be revised.
3. TVA will evaluate the installed breakers to ensure breaker operation will not be affected by the applied clamping breakers.

Example 2

1. Instructions will be issued to procurement and engineering organizations providing the necessary direction to use the unique CATID described above which will distinguish the reconfigured breakers from the original breakers. The CATID for original breakers will be retained to support the existing qualification of replacement original breakers procured in the past.
2. TVA will revise calculation WCG-ACQ-1004 to confirm the design basis performance of the reconfigured breaker in support of the equivalency evaluation (i.e.,

demonstrate the breaker will function as designed with the current configuration of breaker and spacer board attachment in the clamping arrangement of rear angles and front-face panel sections).

Date When Full Compliance Will Be Achieved.

TVA will be in full compliance by March 18, 2011.

E2-1