| title = 2015 Point Beach Nuclear Plant Initial License Examination Administered In-Plant JPMs
| title = 2015 Point Beach Nuclear Plant Initial License Examination Administered In-Plant JPMs
| author name = McNeil D R
| author name = Mcneil D
| author affiliation = NRC/RGN-III/DRS/OLB
| author affiliation = NRC/RGN-III/DRS/OLB
| addressee name =  
| addressee name =  
Line 15: Line 15:


=Text=
=Text=
{{#Wiki_filter:JOB PERFORMANCE MEASURE JPM Page 1 of 10 TR-AA-230-1003-F10, Revision 2 JPM TITLE:
{{#Wiki_filter:JPM JOB PERFORMANCE MEASURE                                 Page 1 of 10 JPM TITLE:               Locally Operate the Atmospheric Steam Dump Control Valves JPM NUMBER:               PBN JPM P000.044a.AOT                         REV. 3 TASK NUMBER(S) /         PBN P000.044.AOT / Locally Operate the Atmospheric Steam Dump TASK TITLE(S):            Control Valves 035 K6.02                                    3.1/3.5 K/A NUMBERS:                                         K/A VALUE:
Locally Operate the Atmospheric Steam Dump Control Valves JPM NUMBER:
035 A3.02                                    3.7/3.5 Justification (FOR K/A VALUES <3.0):
PBN JPM P000.044a.AOT REV. 3   TASK NUMBER(S) / TASK TITLE(S):
TASK APPLICABILITY:
PBN P000.044.AOT / Locally Operate the Atmospheric Steam Dump Control Valves K/A NUMBERS:
RO           SRO           STA         Non-Lic       SRO CERT             OTHER:
035 K6.02 035 A3.02 K/A VALUE:
APPLICABLE METHOD OF TESTING:               Simulate/Walkthrough:   X       Perform:
3.1/3.5 3.7/3.5   Justification (FOR K/A VALUES <3.0):   TASK APPLICABILITY:
EVALUATION LOCATION:             In-Plant:     X             Control Room:
RO     SRO     STA     Non-Lic   SRO CERT OTHER:       APPLICABLE METHOD OF TESTING:
Simulator:                   Other:
Simulate/Walkthrough:
Lab:
X Perform:   EVALUATION LOCATION:
Time for Completion:           10     Minutes       Time Critical:           No Alternate Path [NRC]:                   No Alternate Path [INPO]:                 No TR-AA-230-1003-F10, Revision 2
In-Plant: X Control Room:
 
Simulator:
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric                 JPM Steam Dump Valves, Rev. 3                         Page 2 of 10 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED PRIOR TO USE.
Other:           Lab:       Time for Completion:
REVIEW STATEMENTS                                                               YES     NO   N/A
10 Minutes Time Critical:
: 1. Are all items on the signature page filled in correctly?
N o      Alternate Path [NRC]:
No   Alternate Path [INPO]:
No PBN JPM P000.044a.AOT, Locally Operate the Atmospheric Steam Dump Valves, Rev. 3 JPM Page 2 of 10 TR-AA-230-1003-F10, Revision 2 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED PRIOR TO USE.
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Do the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Do the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
Line 41: Line 37:
: 9. Is the K/A appropriate to the task and to the licensee level if required?
: 9. Is the K/A appropriate to the task and to the licensee level if required?
: 10. Is justification provided for tasks with K/A values less than 3.0?
: 10. Is justification provided for tasks with K/A values less than 3.0?
: 11. Have the performance steps been identified and classified (Critical / Sequence / Time Critical) appropriately?
: 11. Have the performance steps been identified and classified (Critical /
Sequence / Time Critical) appropriately?
: 12. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 12. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 13. Are all references identified, current, accurate, and available to the trainee?   14. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 13. Are all references identified, current, accurate, and available to the trainee?
: 15. Are all critical steps supported by procedural guidance? (e.g., if licensing, EP or other groups were needed to determine correct actions, then the answer should be NO.)  
: 14. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 16. If the JPM is to be administered to an LOIT student, has the required knowledge been taught to the individual prior to administering the JPM? TPE does not have to be completed, but the JPM evaluation may not be valid if they have not been taught the required knowledge.
: 15. Are all critical steps supported by procedural guidance? (e.g., if licensing, EP or other groups were needed to determine correct actions, then the answer should be NO.)
All questions/statements must be answered "YES" or "N/A" or the JPM is not valid for use. If all questions/statements are answered "YES" or "N/A," then the JPM is considered valid and can be performed as written. The individual(s) performing the initial validation shall sign and date the cover sheet.
: 16. If the JPM is to be administered to an LOIT student, has the required knowledge been taught to the individual prior to administering the JPM? TPE does not have to be completed, but the JPM evaluation may not be valid if they have not been taught the required knowledge.
All questions/statements must be answered YES or N/A or the JPM is not valid for use. If all questions/statements are answered YES or N/A, then the JPM is considered valid and can be performed as written. The individual(s) performing the initial validation shall sign and date the cover sheet.
Protected Content: (CAPRs, corrective actions, licensing commitments, etc. associated with this material)
{C001}
TR-AA-230-1003-F10, Revision 2


Protected Content:
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric                           JPM Steam Dump Valves, Rev. 3                             Page 3 of 10 UPDATE LOG: Indicate in the following table any minor changes or major revisions (as defined in TR-AA-230-1003) made to the material after initial approval. Or use separate Update Log form TR-AA-230-1003-F16.
  (CAPRs, corrective actions, licensing commitments, etc. associated with this material)
REASON FOR           AR/TWR     PREPARER       DATE
  {C001}
    #      DESCRIPTION OF CHANGE CHANGE                #      SUPERVISOR     DATE Rev. 0   See microfilm.
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric Steam Dump Valves, Rev. 3 JPM Page 3 of 10 TR-AA-230-1003-F10, Revision 2 UPDATE LOG: Indicate in the following table any minor changes or major revisions (as defined in TR
Rev. 1   Revised cue for the 2012 NRC ILT Exam.
-AA-230-1003) made to the material after initial approval. Or use separate Update Log form TR
Rev. 2   Unknown Rev. 3   Updated for the 2014 operational exam.
-AA-230-1003-F16. # DESCRIPTION OF CHANGE REASON FOR CHANGE AR/TWR# PREPARER DATE SUPERVISOR DATE Rev. 0 See microfilm.
Cue added if examinee                J Hinze Rev 3                                           questions the Added a evaluator cue to step 1                                   N/A Pen/Ink                                          applicability of AOP-10C                                 T Larson TR-AA-230-1003-F10, Revision 2
Rev. 1 Revised cue for the 2012 NRC ILT Exam.
 
Rev. 2 Unknown Rev. 3 Updated for the 2014 operational exam.
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric             JPM Steam Dump Valves, Rev. 3                   Page 4 of 10 SIMULATOR SET-UP: (Only required for simulator JPMs)
Rev 3 Pen/Ink Added a evaluator cue to step 1 Cue added if examinee questions the applicability of AOP
-10C N/A J Hinze      T Larson PBN JPM P000.044a.AOT, Locally Operate the Atmospheric Steam Dump Valves, Rev. 3 JPM Page 4 of 10 TR-AA-230-1003-F10, Revision 2 SIMULATOR SET
-UP:   (Only required for simulator JPMs)
Simulator Setup Instructions:
Simulator Setup Instructions:
None
* None SIMULATOR MALFUNCTIONS:
 
* None SIMULATOR OVERRIDES:
SIMULATOR MALFUNCTIONS:
* None SIMULATOR REMOTE FUNCTIONS:
None
* None Required Materials:       FOP 1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H - Unit 2 Facade) page 108 Unit 2 Secondary System Isolation General  
 
SIMULATOR OVERRIDES:
None
 
SIMULATOR REMOTE FUNCTIONS:
None
 
Required Material s: FOP 1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H  
- Unit 2 Facade) page 108 Unit 2 Secondary System Isolation General  


==References:==
==References:==
FOP 1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H - Unit 2 Facade)
Task Standards:          Locally operate 2MS-2015 per FOP 1.2 using the gagging device.
TR-AA-230-1003-F10, Revision 2


FOP 1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric                       JPM Steam Dump Valves, Rev. 3                           Page 5 of 10 I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues.
- Unit 2 Facade)
Task Standards:
Locally operate 2MS
-2015 per FOP 1.2 using the gagging device.
 
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric Steam Dump Valves, Rev. 3 JPM Page 5 of 10 TR-AA-230-1003-F10, Revision 2 I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.  
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
 
INITIAL CONDITIONS:
INITIAL CONDITIONS:
Unit 2 tripped from full power due to a fire in the Unit 2 Facade.
* Unit 2 tripped from full power due to a fire in the Unit 2 Facade.
2MS-2015 'B' SG Atmospheric Steam Dump Valve is operating sporadically and currently is partially open.
* 2MS-2015 'B' SG Atmospheric Steam Dump Valve is operating sporadically and currently is partially open.
The fire is OUT and the Fire Brigade Leader has determined it is safe for personnel to access the facade area to perform any needed actions.
* The fire is OUT and the Fire Brigade Leader has determined it is safe for personnel to access the facade area to perform any needed actions.
INITIATING CUES (IF APPLICABLE):
* OS2 directs you to fail shut 2MS-2015, 'B' SG Atmospheric Steam Dump Valve per FOP-1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H-Unit 2 Facade) and notify the Control Room when the valve it is shut.
NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
TR-AA-230-1003-F10, Revision 2


INITIATING CUES (IF APPLICABLE):  OS2 directs you to fail shut 2MS
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric                   JPM Steam Dump Valves, Rev. 3                         Page 6 of 10 JPM PERFORMANCE INFORMATION Start Time:
-2015, 'B' SG Atmospheric Steam Dump Valve per FOP
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e., the examinee looks or asks for the indication).
-1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
-Unit 2 Facade) and notify the Control Room when the valve it is shut.
Performance Step: 1       1. Fail 2MS-2015, 'B' SG Atmospheric Dump Valve SHUT by:
 
Critical Y
NOTE:  Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
* Shut IA-872, SG B Atmospheric Steam Dump Operating Air Inlet The examinee shuts IA-872, SG B Atmospheric Steam Dump Standard:
 
Operating Air Inlet.
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric Steam Dump Valves, Rev. 3 JPM Page 6 of 10 TR-AA-230-1003-F10, Revision 2 JPM PERFORMANCE INFORMATION Start Time:
If asked, control air is reading approximately half scale.
NOTE: When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e., the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a "Y" below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Performance Step:
1 Critical  Y
: 1. Fail 2MS-2015, 'B' SG Atmospheric Dump Valve SHUT by:
Shut IA-872, SG B Atmospheric Steam Dump Operating Air Inlet   Standard: The examinee shuts IA
-872, SG B Atmospheric Steam Dump Operating Air Inlet.
Evaluator Cue:
Evaluator Cue:
If asked, control air is reading approximately half scale.
IA-872 valve handwheel is fully inserted.
IA-872 valve handwheel is fully inserted.
Evaluator Cue:
IF ASKED, AOP-10C (AS REFERENCED IN FOP 1.2) IS NOT Evaluator Cue:            APPLICABLE DUE TO THE LOCATION OF THE FIRE. THIS CUE IS APPLICABLE FOR THE DURATION OF THE JPM.
IF ASKED, AOP
Performance:               SATISFACTORY                 UNSATISFACTORY Comments:                 ______________________________________________________
-10C (AS REFERENCED IN FOP 1.2) IS NOT APPLICABLE DUE TO THE LOCATION OF THE FIRE. THIS CUE IS APPLICABLE FOR THE DURATION OF THE JPM.
TR-AA-230-1003-F10, Revision 2
Performance:
SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________


PBN JPM P000.044a.AOT, Locally Operate the Atmospheric Steam Dump Valves, Rev. 3 JPM Page 7 of 10 TR-AA-230-1003-F10, Revision 2 Performance Step:
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric                       JPM Steam Dump Valves, Rev. 3                             Page 7 of 10 Performance Step: 2       2. Fail 2MS-2015, 'B' SG Atmospheric Dump Valve SHUT by:
2 Critical Y
Critical Y
: 2. Fail 2MS-2015, 'B' SG Atmospheric Dump Valve SHUT by:
* Open moisture trap filter plug for 2MS-2015 to vent air Standard:                 The examinee vents air for 2MS-2015 Evaluator Cue:             The moisture trap filter plug is open. Initially there was a sound of air venting, after several seconds it has stopped.
Open moisture trap filter plug for 2MS
If asked, control air pressure is reading zero.
-2015 to vent air Standard: The examinee vents air for 2MS
If asked, 2MS-2015 indicates shut locally.
-2015   Evaluator Cue:
Performance:               SATISFACTORY                 UNSATISFACTORY Comments:                 ______________________________________________________
The moisture trap filter plug is open. Initially there was a sound of air venting, after several seconds it has stopped. If asked, control air pressure is reading zero.
Performance Step: 3         3. Report the status of 2MS-2015 to the Control Room.
If asked, 2MS
Critical N Standard:                 The examinee notifies the Control Room that 2MS-2015 is shut locally.
-2015 indicates shut locally.
Evaluator Cue:             The Control Room acknowledges your report and OS2 directs you to locally throttle 2MS-2015 five turns open using the gagging handwheel.
Performance:
If asked, there are no further actions required by AOP-10C Attachment C.
SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________
Performance:               SATISFACTORY                 UNSATISFACTORY Comments:                 ______________________________________________________
Performance Step:
TR-AA-230-1003-F10, Revision 2
3 Critical N
: 3. Report the status of 2MS
-2015 to the Control Room.
Standard: The examinee notifies the Control Room that 2MS
-2015 is shut locally. Evaluator Cue:
The Control Room acknowledges your report and OS2 directs you to locally throttle 2MS
-2015 five turns open using the gagging handwheel.
If asked, there are no further actions required by AOP
-10C Attachment C.
Performance:
SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________


PBN JPM P000.044a.AOT, Locally Operate the Atmospheric Steam Dump Valves, Rev. 3 JPM Page 8 of 10 TR-AA-230-1003-F10, Revision 2 Performance Step:
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric                 JPM Steam Dump Valves, Rev. 3                       Page 8 of 10 Performance Step: 4         4. Using the gagging handwheel, open 2MS-2015, 'B' SG Critical Y                      Atmospheric Dump Valve 5 turns.
4 Critical Y
Standard:                 The examinee opens 2MS-2015 five turns using the manual gagging device.
: 4. Using the gagging handwheel, open 2MS
Evaluator Note:           The handwheel must be turned clockwise to gag the valve open.
-2015, 'B' SG Atmospheric Dump Valve 5 turns.
If the examinee indicates the handwheel is being turned counter-clockwise, provide a cue that the handwheel did not move.
Standard: The examinee opens 2MS
Evaluator Cue:             2MS-2015 gagging handwheel is turned five turns open and the sound of steam flow is heard.
-2015 five turns using the manual gagging device. Evaluator Note:
Performance:               SATISFACTORY               UNSATISFACTORY Comments:                 ______________________________________________________
The handwheel must be turned clockwise to gag the valve open. If the examinee indicates the handwheel is being turned counter
Performance Step: 5         5. Inform the Control Room the status of 2MS-2015.
-clockwise, provide a cue that the handwheel did not move.
Critical N Standard:                 The examinee notifies the Control Room that 2MS-2015 is gagged open five turns.
Evaluator Cue:
Evaluator Cue:             The Control Room acknowledges your report.
2MS-2015 gagging handwheel is turned five turns open and the sound of steam flow is heard.
Performance:               SATISFACTORY               UNSATISFACTORY Comments:                 ______________________________________________________
Performance:
Terminating Cues:     THIS COMPLETES THE JPM NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________
Stop Time:
Performance Step:
TR-AA-230-1003-F10, Revision 2
5 Critical N
: 5. Inform the Control Room the status of 2MS
-2015. Standard: The examinee notifies the Control Room that 2MS
-2015 is gagged open five turns.
Evaluator Cue:
The Control Room acknowledges your report.
Performance:
SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________
Terminating Cues:
THIS COMPLETES THE JPM


NOTE:  Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric             JPM Steam Dump Valves, Rev. 3                       Page 9 of 10 Examinee:                                           Evaluator:
Stop Time:
RO     SRO       STA     Non-Lic  SRO CERT         Date:
 
LOIT RO       LOIT SRO PERFORMANCE RESULTS:                   SAT:                       UNSAT:
PBN JPM P000.044a.AOT, Locally Operate the Atmospheric Steam Dump Valves, Rev. 3 JPM Page 9 of 10 TR-AA-230-1003-F10, Revision 2 Examinee:       Evaluator:
Remediation required:           YES                     NO COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
RO   SRO   STA   Non-Lic  SRO CERT Date:         LOIT RO   LOIT SRO   PERFORMANCE RESULTS:
EXAMINER NOTE:       ENSURE ALL EXAM MATERIAL IS COLLECTED AND PROCEDURES CLEANED, AS APPROPRIATE.
SAT:       UNSAT:       Remediation required:
EVALUATORS SIGNATURE:
YES   NO         COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
EXAMINER NOTE:   ENSURE ALL EXAM MATERIAL IS COLLECTED AND PROCEDURES CLEANED, AS APPROPRIATE.
TR-AA-230-1003-F10, Revision 2
 
EVALUATOR'S SIGNATURE:     NOTE: Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
JOB PERFORMANCE MEASURE  JPM Page 10 of 10  TR-AA-230-1003-F10, Revision 2 TURNOVER SHEET
 
INITIAL CONDITIONS:
Unit 2 tripped from full power due to a fire in the Unit 2 Facade.
2MS-2015 'B' SG Atmospheric Steam Dump Valve is operating sporadically and currently is partially open.
The fire is OUT and the Fire Brigade Leader has determined it is safe for personnel to access the facade area to perform any needed actions


JPM JOB PERFORMANCE MEASURE                              Page 10 of 10 TURNOVER SHEET INITIAL CONDITIONS:
* Unit 2 tripped from full power due to a fire in the Unit 2 Facade.
* 2MS-2015 'B' SG Atmospheric Steam Dump Valve is operating sporadically and currently is partially open.
* The fire is OUT and the Fire Brigade Leader has determined it is safe for personnel to access the facade area to perform any needed actions.
INITIATING CUES (IF APPLICABLE):
INITIATING CUES (IF APPLICABLE):
OS2 directs you to fail shut 2MS
* OS2 directs you to fail shut 2MS-2015, 'B' SG Atmospheric Steam Dump Valve per FOP-1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H-Unit 2 Facade) and notify the Control Room when the valve it is shut.
-2015, 'B' SG Atmospheric Steam Dump Valve per FOP
NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
-1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H
TR-AA-230-1003-F10, Revision 2
-Unit 2 Facade) and notify the Control Room when the valve it is shut
.


NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
JPM JOB PERFORMANCE MEASURE                                    Page 1 of 17 JPM TITLE:               Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D-02)
JPM NUMBER:              PBN JPM P063.003a.AOT                            REV. 8 TASK NUMBER(S) /          PBN P063.003.AOT / Shift Battery Chargers TASK TITLE(S):
2.1.30                                          4.4 / 4.0 K/A NUMBERS:                                          K/A VALUE:
063 K1.03                                        2.9 / 3.5 Justification (FOR K/A VALUES <3.0):
TASK APPLICABILITY:
RO          SRO            STA          Non-Lic        SRO CERT              OTHER:
APPLICABLE METHOD OF TESTING:                  Simulate/Walkthrough:    X      Perform:
EVALUATION LOCATION:              In-Plant:      X            Control Room:
Simulator:                    Other:
Lab:
Time for Completion:            30      Minutes          Time Critical:            No Alternate Path [NRC]:                    No Alternate Path [INPO]:                  No Developed by:                              Jeffrey Hinze Instructor/Developer                                Date Reviewed by:                          Andrew Zommers Instructor (Instructional Review)                        Date Validated by:                              Jeff Baugniet SME (Technical Review)                                Date Approved by:                          Randy Amundson Training Supervision                                Date Approved by:                              Tom Larson Training Program Owner                                Date TR-AA-230-1003-F10, Revision 2


JOB PERFORMANCE MEASURE JPM Page 1 of 17  TR-AA-230-1003-F10, Revision 2 JPM TITLE:
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                 JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8             Page 2 of 17 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED PRIOR TO USE.
Shift Battery Chargers (Battery Charger D
REVIEW STATEMENTS                                                               YES     NO   N/A
-09 Supplying Power to Bus D-02)  JPM NUMBER:
: 1. Are all items on the signature page filled in correctly?
PBN JPM P063.003a.AOT REV. 8  TASK NUMBER(S) / TASK TITLE(S):
PBN P063.003.AOT / Shift Battery Chargers K/A NUMBERS:
2.1.30 063 K1.03 K/A VALUE:
4.4 / 4.0 2.9 / 3.5  Justification (FOR K/A VALUES <3.0):
TASK APPLICABILITY:
RO    SRO    STA    Non-Lic    SRO CERT OTHER:        APPLICABLE METHOD OF TESTING:
Simulate/Walkthrough:
X  Perform:    EVALUATION LOCATION:
In-Plant: X  Control Room:
Simulator:
Other:          Lab:      Time for Completion:
30 Minutes Time Critical:
No      Alternate Path [NRC]:
No  Alternate Path [INPO]:
No        Developed by:
Jeffrey Hinze Instructor/Developer Date    Reviewed by:
Andrew Zommers Instructor (Instructional Review)
Date Validated  by:
Jeff Baugniet SME (Technical Review)
Date Approved by:
Randy Amundson Training Supervision Date Approved by:
Tom Larson Training Program Owner Date PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
-02), Rev.
8 JPM Page 2 of 17 TR-AA-230-1003-F10, Revision 2 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED PRIOR TO USE.
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Do the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Do the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
Line 227: Line 163:
: 9. Is the K/A appropriate to the task and to the licensee level if required?
: 9. Is the K/A appropriate to the task and to the licensee level if required?
: 10. Is justification provided for tasks with K/A values less than 3.0?
: 10. Is justification provided for tasks with K/A values less than 3.0?
: 11. Have the performance steps been identified and classified (Critical / Sequence / Time Critical) appropriately?
: 11. Have the performance steps been identified and classified (Critical /
Sequence / Time Critical) appropriately?
: 12. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 12. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 13. Are all references identified, current, accurate, and available to the trainee?   14. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 13. Are all references identified, current, accurate, and available to the trainee?
: 15. Are all critical steps supported by procedural guidance? (e.g., if licensing, EP or other groups were needed to determine correct actions, then the answer should be NO.)  
: 14. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 16. If the JPM is to be administered to an LOIT student, has the required knowledge been taught to the individual prior to administering the JPM? TPE does not have to be completed, but the JPM evaluation may not be valid if they have not been taught the required knowledge.
: 15. Are all critical steps supported by procedural guidance? (e.g., if licensing, EP or other groups were needed to determine correct actions, then the answer should be NO.)
All questions/statements must be answered "YES" or "N/A" or the JPM is not valid for use. If all questions/statements are answered "YES" or "N/A," then the JPM is considered valid and can be performed as written. The individual(s) performing the initial validation shall sign and date the cover sheet.
: 16. If the JPM is to be administered to an LOIT student, has the required knowledge been taught to the individual prior to administering the JPM? TPE does not have to be completed, but the JPM evaluation may not be valid if they have not been taught the required knowledge.
 
All questions/statements must be answered YES or N/A or the JPM is not valid for use. If all questions/statements are answered YES or N/A, then the JPM is considered valid and can be performed as written. The individual(s) performing the initial validation shall sign and date the cover sheet.
Protected Content:
Protected Content: (CAPRs, corrective actions, licensing commitments, etc. associated with this material)
  (CAPRs, corrective actions, licensing commitments, etc. associated with this material)
{C001}
  {C001}
TR-AA-230-1003-F10, Revision 2
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
-02), Rev.
8 JPM Page 3 of 17  TR-AA-230-1003-F10, Revision 2 UPDATE LOG:  Indicate in the following table any minor changes or major revisions (as defined in TR
-AA-230-1003) made to the material after initial approval. Or use separate Update Log form TR
-AA-230-1003-F16. # DESCRIPTION OF CHANGE REASON FOR CHANGE AR/TWR# PREPARER DATE SUPERVISOR DATE Rev. 0-2 See historical records.
Rev. 3 Reformatted to the current revision of QF
-1075-01. Revised to Rev. 10 of 0
-SOP-DC-002, 125 VDC System, Bus D
-02 & Components.
Rev. 4 JPM updated to new format. Editorial changes made to JPM.
Rev. 5 Corrected typographical error.
Verified correct for Rev 16 of 0
-SOP-DC-002. Rev. 6 Updated due to procedure revision. Verified correct for revision 18 of 0
-SOP-DC-002. Rev. 7 Updated for the 2014 operational exam.
Rev 8 Updated for 2015 NRC ILT Exam due to procedure change
 
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
-02), Rev.
8 JPM Page 4 of 17  TR-AA-230-1003-F10, Revision 2 SIMULATOR SET
-UP:  (Only required for simulator JPMs)
SIMULATOR SETUP INSTRUCTIONS
:  None 


SIMULATOR MALFUNCTIONS:
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                          JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8                        Page 3 of 17 UPDATE LOG: Indicate in the following table any minor changes or major revisions (as defined in TR-AA-230-1003) made to the material after initial approval. Or use separate Update Log form TR-AA-230-1003-F16.
None 
REASON FOR          AR/TWR      PREPARER      DATE
    #        DESCRIPTION OF CHANGE CHANGE                  #    SUPERVISOR      DATE Rev. 0-2 See historical records.
Reformatted to the current revision of QF-1075-01. Revised to Rev. 10 of 0-SOP-DC-002, 125 VDC Rev. 3 System, Bus D-02 & Components.
Rev. 4  JPM updated to new format. Editorial changes made to JPM.
Rev. 5  Corrected typographical error. Verified correct for Rev 16 of 0-SOP-DC-002.
Rev. 6  Updated due to procedure revision. Verified correct for revision 18 of 0-SOP-DC-002.
Rev. 7  Updated for the 2014 operational exam.
Rev 8    Updated for 2015 NRC ILT Exam due to procedure change TR-AA-230-1003-F10, Revision 2


SIMULATOR OVERRIDES:
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8              Page 4 of 17 SIMULATOR SET-UP: (Only required for simulator JPMs)
None
SIMULATOR SETUP INSTRUCTIONS:
 
* None SIMULATOR MALFUNCTIONS:
SIMULATOR REMOTE FUNCTIONS:
* None SIMULATOR OVERRIDES:
None
* None SIMULATOR REMOTE FUNCTIONS:
 
* None Required Materials:       0-SOP-DC-002, 125 VDC System Bus D-02 & Components General  
Required Materials:
0-SOP-DC-002, 125 VDC System Bus D
-02 & Components General  


==References:==
==References:==
0-SOP-DC-002, 125 VDC System Bus D-02 & Components Task Standards:          The examinee places Battery Charger D-09 in service for Battery Charger D-08 (D-09 initially supplying Battery D-305) in accordance with the applicable steps of 0-SOP-DC-002.
TR-AA-230-1003-F10, Revision 2


0-SOP-DC-002, 125 VDC System Bus D
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                     JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8                   Page 5 of 17 I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues.
-02 & Components Task Standards:
The examinee places Battery Charger D
-09 in service for Battery Charger D-08 (D-09 initially supplying Battery D
-305) in accordance with the applicable steps of 0
-SOP-DC-002.
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
-02), Rev.
8 JPM Page 5 of 17 TR-AA-230-1003-F10, Revision 2 I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.  
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
 
INITIAL CONDITIONS:
INITIAL CONDITIONS: The DC Distribution system is operating under normal conditions.
* The DC Distribution system is operating under normal conditions.
Battery Charger D
* Battery Charger D-09 is supplying Battery D-305.
-09 is supplying Battery D
* Battery Charger D-09 is being supplied from 1B-49.
-305. Battery Charger D
* D-109 Battery Charger is OOS for maintenance.
-09 is being supplied from 1B
-49. D-109 Battery Charger is OOS for maintenance.
 
INITIATING CUES (IF APPLICABLE):
INITIATING CUES (IF APPLICABLE):
OS1 directs you to place Battery Charger D
* OS1 directs you to place Battery Charger D-09 in service for Battery Charger D-08 in accordance with 0-SOP-DC-002, 125 VDC System, Bus D-02 & Components section 5.2, Placing Battery Charger D-09 in Service for Battery Charger D-08 (D-09 initially supplying battery D-305).
-09 in service for Battery Charger D
NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
-08 in accordance with 0
TR-AA-230-1003-F10, Revision 2
-SOP-DC-002, 125 VDC System, Bus D
-02 & Components section 5.2, Placing Battery Charger D
-09 in Service for Battery Charger D
-08 (D-09 initially supplying battery D-305).


NOTE:  Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                   JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8                 Page 6 of 17 JPM PERFORMANCE INFORMATION Start Time:
 
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e., the examinee looks or asks for the indication).
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
-02), Rev.
8 JPM Page 6 of 17 TR-AA-230-1003-F10, Revision 2 JPM PERFORMANCE INFORMATION Start Time:
NOTE: When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e., the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a "Y" below the performance step number. Failur e to meet the standard for any critical step shall result in failure of this JPM.
NOTE: The Evaluator will act as the Concurrent Checker for all necessary steps and will concur with all actions taken by the examinee.
NOTE: The Evaluator will act as the Concurrent Checker for all necessary steps and will concur with all actions taken by the examinee.
5.2  Placing D-09 Battery Charger in Service for D-08 Charger, (D-09 Initially Supplying D-305 Battery)
Performance Step: 1        5.2.1  CHECK the following are in OFF at D-301 and D-02 OR have Critical N                          OPEN indication on 2C20:
* D72-301-01, Alternate Power to D-01 DC Distr Pnl
* D72-301-03, Alternate Power to D-02 DC Distr Pnl
* D72-301-04, Alternate Power to 1/2D-201 DC Distr Pnl
* D72-301-06, Feed to D-302 from D-305 Swing Station Battery
* D72-301-07, Power to Mnt Test Equipment (no 2C20 ind)
* D72-02-04, Feed to D-02 from D-301 Swing Batt Distr Pnl The examinee checks that the breakers at panels D-301 and D-02 Standard:
are OFF.
The examinee may question the NOTE regarding D-109 prior to the Evaluator Note:            1st step of this section. If necessary, remind the examinee of the turnover information that D-109 is OOS for maintenance.
Evaluator Cue:              The breakers at panels D-301 and D-02 are in the OFF position.
Performance:                SATISFACTORY                  UNSATISFACTORY Comments:                  _____________________________________________________
TR-AA-230-1003-F10, Revision 2


===5.2 Placing===
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery               JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8              Page 7 of 17 Performance Step: 2 5.2.CHECK DC current is approximately zero on D-09 Charger.
D-09 Battery Charger in Service for D
Critical N The examinee checks that Battery Charger D-09 DC CURRENT is Standard:
-08 Charger, (D
approximately '0' amps.
-09 Initially Supplying D
Evaluator Cue:             Battery Charger D-09 DC CURRENT is '0' amps.
-305 Battery) Performance Step:
Performance:               SATISFACTORY               UNSATISFACTORY Comments:                   _____________________________________________________
1 Critical  N
Performance Step: 3        5.2.3  PLACE D-09-DC, D-09 Swing Stn Battery Charger Output to Critical Y                          the OFF position on D-09.
 
Standard:                  The examinee places D-09-DC breaker to the OFF position.
====5.2.1 CHECK====
Per the NOTE prior to step 5.2.3; when D-09-DC breaker is taken to Evaluator Note:            OFF a D-09 Battery Charger Trouble Alarm will occur in the Control Room.
the following are in OFF at D-301 and D-02 OR have OPEN indication on 2C20:
* D-09-DC is in the OFF position.
D72-301-01, Alternate Power to D
-01 DC Distr Pnl D72-301-03, Alternate Power to D-02 DC Distr Pnl D72-301-04, Alternate Power to 1/2D
-201 DC Distr Pnl D72-301-06, Feed to D
-302 from D
-305 Swing Station Battery  D72-301-07, Power to Mnt Test Equipment (no 2C20 ind)
D72-02-04, Feed to D
-02 from D-301 Swing Batt Distr Pnl  Standard: The examinee checks that the breakers at panels D
-301 and D-02 are OFF. Evaluator Note:
The examinee may question the NOTE regarding D
-109 prior to the 1st step of this section. If necessary, remind the examinee of the turnover information that D
-109 is OOS for maintenance.
Evaluator Cue:
The breakers at panels D
-301 and D-02 are in the OFF position. Performance:
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________
 
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
-02), Rev.
8 JPM Page 7 of 17  TR-AA-230-1003-F10, Revision 2 Performance Step:
2 Critical  N 5.2.2 CHECK DC current is approximately zero on D
-09 Charger.
Standard: The examinee checks that Battery Charger D
-09 DC CURRENT is approximately '0' amps.
Evaluator Cue:
Evaluator Cue:
Battery Charger D
* The control room announces: "D-09 BATTERY CHARGER TROUBLE ALARM" Performance:               SATISFACTORY               UNSATISFACTORY Comments:                   _____________________________________________________
-09 DC CURRENT is '0' amps.
TR-AA-230-1003-F10, Revision 2
Performance:
SATISFACTORY UNSATISFACTORY Comments:  _____________________________________________________
Performance Step:
3 Critical  Y
 
====5.2.3 PLACE====
D-09-DC, D-09 Swing Stn Battery Charger Output to the OFF position on D
-09. Standard: The examinee places D DC breaker to the OFF position. Evaluator Note:
Per the NOTE prior to step 5.2.3; when D DC breaker is taken to OFF a  D-09 Battery Charger Trouble Alarm will occur in the Control Room. Evaluator Cue:
D-09-DC is in the OFF position. The control room announces: "D
-09 BATTERY CHARGER TROUBLE ALARM"   Performance:
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________


PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                 JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8                 Page 8 of 17 Performance Step: 4        5.2.4    PLACE D72-301-05, Feed to D-301 From D-305 Swing Critical Y                          Station Battery, to the OFF position on D-301.
-02), Rev.
Standard:                  The examinee places D72-301-05 to the OFF position.
8 JPM Page 8 of 17 TR-AA-230-1003-F10, Revision 2 Performance Step:
As the Concurrent Checker the Evaluator will concur with all actions Evaluator Note:
4 Critical  Y
taken by the examinee.
Evaluator Cue:              Breaker is in the OFF position.
Performance:                SATISFACTORY                  UNSATISFACTORY Comments:                  _____________________________________________________
Performance Step: 5        5.2.5    IF D-09 is NOT being supplied from the desired AC source, Critical N                          THEN PERFORM the following: .....
D-09 is already aligned to the desired source, Step 5.2.5 has been Standard:
previously marked N/A; the examinee moves on to Step 5.2.6.
If the examinee asks, D-09 IS aligned to 1B-49, the desired AC Evaluator Cue:
source (provided in the turnover).
Performance:                SATISFACTORY                  UNSATISFACTORY Comments:                  _____________________________________________________
TR-AA-230-1003-F10, Revision 2


====5.2.4 PLACE====
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8              Page 9 of 17 Performance Step: 6        5.2.6  ENSURE the following for D-09 Battery Charger:
D72-301-05, Feed to D
Critical N                         a. D-09 voltage is approximately equal to D-08 Charger voltage - ADJUST D-09 Float potentiometer as necessary.
-301 From D
: b. D-09 Battery Charger voltage is 132 to 135 vdc.
-305 Swin g Station Battery, to the OFF position on D
The examinee checks that D-08 and D-09 Charger voltages are Standard:
-301. Standard: The examinee places D72
approximately equal and that D-09 voltage is between 132-135 VDC.
-301-05 to the OFF position. Evaluator Note:
* Battery Charger D-08 voltage is 133.5 VDC.
As the Concurrent Checker the Evaluator will concur with all actions taken by the examinee.
Evaluator Cue:
Breaker is in the OFF position. Performance:
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________
Performance Step:
5 Critical N 5.2.5 IF D-09 is NOT being supplied from the desired AC source, THEN PERFORM the following: .....
Standard: D-09 is already aligned to the desired source, Step 5.2.5 has been previously marked N/A; the examinee moves on to Step 5.2.6.
Evaluator Cue:
Evaluator Cue:
If the examinee asks, D
* Battery Charger D-09 voltage is 133.5 VDC.
-09 IS aligned to 1B
Performance:                SATISFACTORY                UNSATISFACTORY Comments:                  _____________________________________________________
-49, the desired AC source (provided in the turnover).
Performance Step: 7        5.2.7  ENSURE D72-301-02, Feed to D-301 from D-09 Swing Stn Critical N                        Battery Chgr, is in the ON position on D-301.
Performance:
Standard:                  The examinee ensures breaker D72-301-02 is in the ON position.
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________
Evaluator Cue:              Breaker is in the ON position Performance:               SATISFACTORY               UNSATISFACTORY Comments:                   _____________________________________________________
TR-AA-230-1003-F10, Revision 2


PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery               JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8             Page 10 of 17 Performance Step: 8        5.2.8 PLACE D72-301-03, Alternate Power to D-02 DC Distribution Critical Y                        Panel to the ON position on D-301.
-02), Rev.
Standard:                  The examinee places breaker D72-301-03 to the ON position.
8 JPM Page 9 of 17  TR-AA-230-1003-F10, Revision 2 Performance Step:
Evaluator Cue:              Breaker is in the ON position Performance:                SATISFACTORY                UNSATISFACTORY Comments:                  _____________________________________________________
6 Critical  N
Performance Step: 9        5.2.9  PLACE D72-02-04, Feed to D-02 from D-301 Swing Batt Critical Y                        Distr Pnl to the ON position on D-02..
Standard:                  The examinee places breaker D72-02-04 to the ON position.
Evaluator Cue:              Breaker is in the ON position Performance:                SATISFACTORY                UNSATISFACTORY Comments:                  _____________________________________________________
Performance Step: 10        5.2.10 RECORD DC current on D-08 Charger:
Critical N                        D-08 DC current __________ amps The examinee records DC current (130 amps) for Battery Charger D-Standard:
08.
Evaluator Cue:              DC current for Battery Charger D-08 is 130 amps.
Performance:                SATISFACTORY                UNSATISFACTORY Comments:                  _____________________________________________________
TR-AA-230-1003-F10, Revision 2


====5.2.6 ENSURE====
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                   JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8                 Page 11 of 17 Performance Step: 11       5.2.11 PLACE D-09-DC, D-09 Swing Stn Battery Charger Output to Critical Y                          the ON position on D-09.
the following for D
Standard:                   The examinee places breaker D-09-DC to ON.
-09 Battery Charger:
Per the NOTE prior to step 5.2.11; when D-09-DC is taken to ON the Evaluator Note:
: a. D-09 voltage is approximately equal to D
D-09 Battery Charger Trouble Alarm will clear in the Control Room.
-08 Charger voltage - ADJUST D-09 Float potentiometer as necessary.
* Breaker is in the ON position, D-09 current moves to 90 amps.
: b. D-09 Battery Charger voltage is 13 2 to 135 vdc.
Standard: The examinee checks that D
-08 and D-09 Charger voltages are approximately equal and that D
-09 voltage is between 13 2-135 VDC. Evaluator Cue:
Battery Charger D
-08 voltage is 13 3.5 VDC. Battery Charger D
-09 voltage is 13 3.5 VDC. Performance:
SATISFACTORY UNSATISFACTORY Comments:  _____________________________________________________
Performance Step:  7 Critical N 5.2.7 ENSURE D72
-301-02, Feed to D
-301 from D
-09 Swing Stn Battery Chgr, is in the ON position on D
-301. Standard: The examinee ensures breaker D72
-301-02 is in the ON position. Evaluator Cue:
Breaker is in the ON position  Performance: SATISFACTORY UNSATISFACTORY Comments:  _____________________________________________________
 
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
-02), Rev.
8 JPM Page 10 of 17  TR-AA-230-1003-F10, Revision 2 Performance Step:
8 Critical  Y
 
====5.2.8 PLACE====
D72-301-03, Alternate Power to D
-02 DC Distribution Panel to the ON position on D
-301. Standard: The examinee places breaker D72
-301-03 to the ON position. Evaluator Cue:
Breaker is in the ON position  Performance:
SATISFACTORY UNSATISFACTORY Comments:  _____________________________________________________
Performance Step:
9 Critical  Y
 
====5.2.9 PLACE====
D72-02-04, Feed to D
-02 from D-301 Swing Batt Distr Pnl to the ON position on D
-02.. Standard: The examinee places breaker D72 04 to the ON position. Evaluator Cue:
Breaker is in the ON position  Performance:
SATISFACTORY UNSATISFACTORY Comments:  _____________________________________________________
 
Performance Step:
10 Critical  N 5.2.10 RECORD DC current on D
-08 Charger:
D-08 DC current __________ amps Standard: The examinee records DC current (130 amps) for Battery Charger D
-08. Evaluator Cue:
DC current for Battery Charger D
-08 is 130 amps.
Performance:
SATISFACTORY UNSATISFACTORY Comments:  _____________________________________________________
 
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
-02), Rev.
8 JPM Page 11 of 17 TR-AA-230-1003-F10, Revision 2 Performance Step:
11 Critical  Y 5.2.11 PLAC E D-09-DC, D-09 Swing Stn Battery Charger Output to the ON position on D
-09. Standard: The examinee places breaker D DC to ON. Evaluator Note:
Per the NOTE prior to step 5.2.11; when D DC is taken to ON the D-09 Battery Charger Trouble Alarm will clear in the Control Room.
Evaluator Cue:
Evaluator Cue:
Breaker is in the ON position, D
* Control Room announces: "D-09 Battery Charger Trouble Alarm Clear" Performance:               SATISFACTORY                 UNSATISFACTORY Comments:                   _____________________________________________________
-09 current moves to 90 amps.
Performance Step: 12       5.2.12 ADJUST D-09 Float potentiometer as necessary until the Critical N                          charger assumes at least 50 but no greater than 100 percent of the current previously carried by D-08 from Step 5.2.10.
Control Room announces: "D
The examinee verifies that D-09 current (90 amps) is between 50 Standard:                  and 100% of previously given D-08 current (130 amps). No adjustment is necessary.
-09 Battery Charger Trouble Alarm Clear"   Performance:
Evaluator Note:             130 amps was given (Cued) at step 5.2.10 for D-08 load.
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________
Evaluator Cue:             D-09 current is 90 amps.
Performance Step:
Performance:               SATISFACTORY                 UNSATISFACTORY Comments:                   _____________________________________________________
12 Critical  N 5.2.12 ADJUST D-09 Float potentiometer as necessary until the charger assumes at least 50 but no greater than 100 percent of the current previously carried by D
TR-AA-230-1003-F10, Revision 2
-08 from Step 5.2.10. Standard: The examinee verifies that D
-09 current (90 amps) is between 50 and 100% of previously given D
-08 current (130 amps). No adjustment is necessary.
Evaluator Note:
130 amps was given (Cued) at step 5.2.10 for D
-08 load. Evaluator Cue
: D-09 current is 90 amps.
Performance:
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________


PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                     JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8                   Page 12 of 17 Performance Step: 13       5.2.13 ENSURE D-09 Battery Charger is functioning normally Critical N                          (ie., no fluctuations in voltage or current and no alarms).
-02), Rev.
The examinee verifies verifies that Battery Charger D-09 is operating Standard:
8 JPM Page 12 of 17 TR-AA-230-1003-F10, Revision 2 Performance Step:
properly.
13 Critical  N 5.2.13 ENSURE D-09 Battery Charger is functioning normally (ie., no fluctuations in voltage or current and no alarms).
Standard: The examinee verifies verifies that Battery Charger D
-09 is operating properly. Evaluator Cue:
D-09 Charger Status is:
D-09 Charger Status is:
voltage is 13 3.5 VDC and stable current is 90 amps and stable No alarms in   Performance:
* voltage is 133.5 VDC and stable Evaluator Cue:
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________
* current is 90 amps and stable
Performance Step:
* No alarms in Performance:               SATISFACTORY                 UNSATISFACTORY Comments:                   _____________________________________________________
14 Critical  Y 5.2.14 PLACE D-08-DC, D-08 DC Station Battery Charger Output to the OFF position on D
Performance Step: 14       5.2.14 PLACE D-08-DC, D-08 DC Station Battery Charger Output to Critical Y                          the OFF position on D-08.
-08. Standard: The examinee places D DC breaker to OFF position. Evaluator Note:
Standard:                   The examinee places D-08-DC breaker to OFF position.
Per the NOTE prior to step 5.2.14; when D DC breaker is taken to OFF a D-08 Battery Charger Trouble Alarm will occur in the Control Room. Evaluator Cue:
Per the NOTE prior to step 5.2.14; when D-08-DC breaker is taken to Evaluator Note:            OFF a D-08 Battery Charger Trouble Alarm will occur in the Control Room.
D-08-DC is in the OFF position. The control room announces: "D
* D-08-DC is in the OFF position.
-08 BATTERY CHARGER TROUBLE ALARM"  Performance:
SATISFACTORY UNSATISFACTORY Comments:  _____________________________________________________
 
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
-02), Rev.
8 JPM Page 13 of 17  TR-AA-230-1003-F10, Revision 2 Performance Step:
15 Critical  N 5.2.15 ADJUST D-09 Float potentiometer as necessary until D
-09 Battery Charger voltage is 13 3.5 (13 2-135) vdc.
Standard: The examinee verifies D
-09 Charger voltage is 13 3.5 VDC. Evaluator Cue:
D-09 Charger voltage is 13 3.5 VDC (previously given at step 5.2.13)
Performance: SATISFACTORY UNSATISFACTORY Comments:  _____________________________________________________
Performance Step:
16 Critical  N 5.2.16 CHECK D-09 Charger current is approximately equal to the previous current on D
-08 (recorded in Step 5.2.10). Standard: The examinee verifies D
-09 Charger current is approximately equal to previous D
-08 Charger current.
Evaluator Cue:
Evaluator Cue:
D-09 Charger current is 130 amps.
* The control room announces: "D-08 BATTERY CHARGER TROUBLE ALARM" Performance:               SATISFACTORY                 UNSATISFACTORY Comments:                   _____________________________________________________
Performance:
TR-AA-230-1003-F10, Revision 2
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________


PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                 JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8               Page 13 of 17 Performance Step: 15        5.2.15 ADJUST D-09 Float potentiometer as necessary until D-09 Critical N                          Battery Charger voltage is 133.5 (132-135) vdc.
-02), Rev.
Standard:                   The examinee verifies D-09 Charger voltage is 133.5 VDC.
8 JPM Page 14 of 17 TR-AA-230-1003-F10, Revision 2 Performance Step:
Evaluator Cue:               D-09 Charger voltage is 133.5 VDC (previously given at step 5.2.13)
17 Critical N 5.2.17 PLACE D-08-AC, D-08 DC Station Battery Charger Input to the OFF position on D
Performance:               SATISFACTORY               UNSATISFACTORY Comments:                   _____________________________________________________
-08. Standard: The examinee places D AC breaker to the OFF position. Evaluator Note:
Performance Step: 16        5.2.16 CHECK D-09 Charger current is approximately equal to the Critical N                          previous current on D-08 (recorded in Step 5.2.10).
Per the NOTE prior to step 5.2.17; when D AC is taken to OFF the D-08 Battery Charger Trouble Alarm will clear in the Control Room. Evaluator Cue:
The examinee verifies D-09 Charger current is approximately equal Standard:
Breaker is in OFF position  Control Room announces, "D
to previous D-08 Charger current.
-08 Battery Charger Trouble Alarm Clear"  The red AC Power Failure light on D
Evaluator Cue:               D-09 Charger current is 130 amps.
-08 Charger is OFF.
Performance:               SATISFACTORY               UNSATISFACTORY Comments:                   _____________________________________________________
Performance:
TR-AA-230-1003-F10, Revision 2
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________
Performance Step:
18 Critical  N 5.2.18 IF D-08 contactor is operable from the Control Room, THEN TRIP    D-08 Battery Charger Supply contactor.
Standard: The examinee notifies the control room to trip the D
-08 Battery Charger Supply contactor.
Evaluator Cue:
The Control Room acknowledges the report, then reports back that 2B42-491, D-08 Battery Charger Supply contactor is OPEN.
Performance:
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________


PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                 JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8                 Page 14 of 17 Performance Step: 17        5.2.17 PLACE D-08-AC, D-08 DC Station Battery Charger Input to Critical N                          the OFF position on D-08.
-02), Rev.
Standard:                   The examinee places D-08-AC breaker to the OFF position.
8 JPM Page 15 of 17 TR-AA-230-1003-F10, Revision 2 Performance Step:
Per the NOTE prior to step 5.2.17; when D-08-AC is taken to OFF Evaluator Note:            the D-08 Battery Charger Trouble Alarm will clear in the Control Room.
19 Critical  N 5.2.19 IF D-08 contactor not operable from the Control Room, THEN TRIP locally in accordance with Section 5.7.
* Breaker is in OFF position
Standard: The examinee acknowledges that 2B42
* Control Room announces, "D-08 Battery Charger Trouble Alarm Evaluator Cue:
-491, D-08 Battery Charger Supply contactor was opened from the control room, marks Step 5.2.19 N/A, and moves on to Step 5.2.20.
Clear"
Performance:
* The red AC Power Failure light on D-08 Charger is OFF.
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________
Performance:               SATISFACTORY               UNSATISFACTORY Comments:                   _____________________________________________________
Performance Step:
Performance Step: 18        5.2.18 IF D-08 contactor is operable from the Control Room, THEN Critical N                          TRIP D-08 Battery Charger Supply contactor.
20 Critical  N 5.2.20 WHEN the AC Supply Contactor is tripped, THEN PLACE D72-02-07, Feed to D
The examinee notifies the control room to trip the D-08 Battery Standard:
-02 from D-08 Stn Battery Charger to the OFF position on D-02. Standard: The examinee places breaker D72 07 to the OFF position. Evaluator Cue:
Charger Supply contactor.
Breaker is in the OFF position. Performance:
The Control Room acknowledges the report, then reports back that Evaluator Cue:
SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________
2B42-491, D-08 Battery Charger Supply contactor is OPEN.
Performance:               SATISFACTORY               UNSATISFACTORY Comments:                   _____________________________________________________
TR-AA-230-1003-F10, Revision 2


Terminating Cues:
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery                JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8              Page 15 of 17 Performance Step: 19        5.2.19 IF D-08 contactor not operable from the Control Room, Critical N                        THEN TRIP locally in accordance with Section 5.7.
THIS COMPLETES THE JPM
The examinee acknowledges that 2B42-491, D-08 Battery Charger Standard:                  Supply contactor was opened from the control room, marks Step 5.2.19 N/A, and moves on to Step 5.2.20.
Performance:                SATISFACTORY                UNSATISFACTORY Comments:                  _____________________________________________________
Performance Step: 20        5.2.20 WHEN the AC Supply Contactor is tripped, THEN PLACE Critical N                        D72-02-07, Feed to D-02 from D-08 Stn Battery Charger to the OFF position on D-02.
Standard:                  The examinee places breaker D72-02-07 to the OFF position.
Evaluator Cue:              Breaker is in the OFF position.
Performance:                SATISFACTORY                UNSATISFACTORY Comments:                  _____________________________________________________
Terminating Cues:     THIS COMPLETES THE JPM NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
Stop Time:
TR-AA-230-1003-F10, Revision 2


NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery            JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8          Page 16 of 17 Examinee:                                            Evaluator:
Stop Time:
RO      SRO      STA      Non-Lic  SRO CERT          Date:
LOIT RO      LOIT SRO PERFORMANCE RESULTS:                    SAT:                        UNSAT:
Remediation required:            YES                    NO COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
EXAMINER NOTE:        ENSURE ALL EXAM MATERIAL IS COLLECTED AND PROCEDURES CLEANED, AS APPROPRIATE.
EVALUATORS SIGNATURE:
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
TR-AA-230-1003-F10, Revision 2


PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D
JOB PERFORMANCE MEASURE                                  JPM Page 17 of 17 TURNOVER SHEET INITIAL CONDITIONS:
-02), Rev.
* The DC Distribution system is operating under normal conditions.
8 JPM Page 16 of 17  TR-AA-230-1003-F10, Revision 2 Examinee:      Evaluator:
* Battery Charger D-09 is supplying Battery D-305.
RO    SRO    STA    Non-Lic  SRO CERT Date:        LOIT RO  LOIT SRO    PERFORMANCE RESULTS:
* Battery Charger D-09 is being supplied from 1B-49.
SAT:      UNSAT:        Remediation required:
* D-109 Battery Charger is OOS for maintenance.
YES  NO COMMENTS/FEEDBACK:  (Comments shall be made for any steps graded unsatisfactory).
INITIATING CUES (IF APPLICABLE):
EXAMINER NOTE:    ENSURE ALL EXAM MATERIAL IS COLLECTED AND PROCEDURES CLEANED, AS APPROPRIATE.
* OS1 directs you to place Battery Charger D-09 in service for Battery Charger D-08 in accordance with 0-SOP-DC-002, 125 VDC System, Bus D-02 & Components section 5.2, Placing Battery Charger D-09 in Service for Battery Charger D-08 (D-09 initially supplying battery D-305).
NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
TR-AA-230-1003-F10, Revision 2


EVALUATOR'S SIGNATURE:
JOB PERFORMANCE MEASURE                                           JPM Page 1 of 16 JPM TITLE:                Perform Lineups on the Spent Fuel Pool Cooling System JPM NUMBER:                PBN JPM P033.001a.AOT                                REV. 0 TASK NUMBER(S) /          PBN P033.001.AOT Perform Lineups of the SFP Cooling System TASK TITLE(S):
NOTE:  Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
K/A NUMBERS:              033 G 2.2.15                    K/A VALUE:     3.9/4.3 Justification (FOR K/A VALUES <3.0):
JOB PERFORMANCE MEASURE JPM Page 17 of 17  TR-AA-230-1003-F10, Revision 2 TURNOVER SHEET
TASK APPLICABILITY:
 
RO      SRO      STA      Non-Lic      SRO CERT          OTHER:
INITIAL CONDITIONS:
APPLICABLE METHOD OF TESTING:                    Simulate/Walkthrough:        X    Perform:
The DC Distribution system is operating under normal conditions.
EVALUATION LOCATION:            In-Plant:      X                      Control Room:
Battery Charger D
Simulator:                            Other:
-09 is supplying Battery D
Lab:
-305. Battery Charger D
Time for Completion:      20        Minutes      Time Critical:      NO Alternate Path [NRC]:    NO Alternate Path [INPO]:    NO Developed by:                            Andrew Zommers Instructor/Developer                                Date Reviewed by:                                Jeff Hinze Instructor (Instructional Review)                          Date Validated by:                              Jeff Baugniet SME (Technical Review)                                 Date Approved by:                            Randy Amundson Training Supervision                                Date Approved by:                               Tom Larson Training Program Owner                                Date TR-AA-230-1003-F10, Revision 2
-09 is being supplied from 1B
-49. D-109 Battery Charger is OOS for maintenance.
 
INITIATING CUES (IF APPLICABLE): OS1 directs you to place Battery Charger D
-09 in service for Battery Charger D
-08 in accordance with 0
-SOP-DC-002, 125 VDC System, Bus D
-02 & Components section 5.2, Placing Battery Charger D
-09 in Service for Battery Charger D
-08 (D-09 initially supplying battery D-305). 


NOTE:  Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,                     JPM Rev. 0                               Page 2 of 16 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED PRIOR TO USE.
 
REVIEW STATEMENTS                                                                         YES     NO     N/A
JOB PERFORMANCE MEASURE  JPM Page 1 of 16  TR-AA-230-1003-F10, Revision 2 JPM TITLE:
: 1. Are all items on the signature page filled in correctly?
Perform Lineups on the Spent Fuel Pool Cooling System JPM NUMBER:
PBN JPM P033.001 a.AOT REV. 0  TASK NUMBER(S) / TASK TITLE(S):
PBN P033.001.AOT Perform Lineups of the SFP Cooling System K/A NUMBERS:
033 G 2.2.15 K/A VALUE:
3.9/4.3  Justification (FOR K/A VALUES <3.0):
TASK APPLICABILITY:
RO  SRO    STA    Non-Lic  SRO CERT OTHER:        APPLICABLE METHOD OF TESTING:
Simulate/Walkthrough:
X  Perform:    EVALUATION LOCATION:
In-Plant: X  Control Room:
Simulator:
Other:          L ab:      Time for Completion:
20 Minutes Time Critical:
NO      Alternate Path [NRC]:
NO  Alternate Path [INPO]:
NO        Developed by:
Andrew Zommers Instructor/Developer Date    Reviewed by:
Jeff Hinze Instructor (Instructional Review)
Date Validated  by:
Jeff Baugniet SME (Technical Review)
Date Approved by:
Randy Amundson Training Supervision Date Approved by:
Tom Larson Training Program Owner Date PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0 JPM Page 2 of 16 TR-AA-230-1003-F10, Revision 2 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED PRIOR TO USE.
REVIEW STATEMENTS YES NO N/A 1. Are all items on the signature page filled in correctly?
: 2. Has the JPM been reviewed and validated by SMEs?
: 2. Has the JPM been reviewed and validated by SMEs?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 3. Can the required conditions for the JPM be appropriately established in the simulator if required?
: 4. Do the performance steps accurately reflect trainee's actions in accordance with plant procedures?
: 4. Do the performance steps accurately reflect trainees actions in accordance with plant procedures?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
: 5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
: 6. Has the completion time been established based on validation data or incumbent experience?
: 6. Has the completion time been established based on validation data or incumbent experience?
Line 607: Line 389:
: 9. Is the K/A appropriate to the task and to the licensee level if required?
: 9. Is the K/A appropriate to the task and to the licensee level if required?
: 10. Is justification provided for tasks with K/A values less than 3.0?
: 10. Is justification provided for tasks with K/A values less than 3.0?
: 11. Have the performance steps been identified and classified (Critical / Sequence / Time Critical) appropriately?   12. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 11. Have the performance steps been identified and classified (Critical /
Sequence / Time Critical) appropriately?
: 12. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
: 13. Are all references identified, current, accurate, and available to the trainee?
: 13. Are all references identified, current, accurate, and available to the trainee?
: 14. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 14. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
: 15. Are all critical steps supported by procedural guidance? (e.g., if licensing, EP or other groups were needed to determine correct actions, then the answer should be NO.)  
: 15. Are all critical steps supported by procedural guidance? (e.g., if licensing, EP or other groups were needed to determine correct actions, then the answer should be NO.)
: 16. If the JPM is to be administered to an LOIT student, has the required knowledge been taught to the individual prior to administering the JPM? TPE does not have to be completed, but the JPM evaluation may not be valid if they have not been taught the required knowledge.
: 16. If the JPM is to be administered to an LOIT student, has the required knowledge been taught to the individual prior to administering the JPM?
All questions/statements must be answered "YES" or "N/A" or the JPM is not valid for use. If all questions/statements are answered "YES" or "N/A," then the JPM is considered valid and can be performed as  
TPE does not have to be completed, but the JPM evaluation may not be valid if they have not been taught the required knowledge.
All questions/statements must be answered YES or N/A or the JPM is not valid for use. If all questions/statements are answered YES or N/A, then the JPM is considered valid and can be performed as written. The individual(s) performing the initial validation shall sign and date the cover sheet.
Protected Content: (CAPRs, corrective actions, licensing commitments, etc. associated with this material)
{C001}      None TR-AA-230-1003-F10, Revision 2


written. The individual(s) performing the initial validation shall sign and date the cover sheet.
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,                           JPM Rev. 0                                   Page 3 of 16 UPDATE LOG: Indicate in the following table any minor changes or major revisions (as defined in TR-AA-230-1003) made to the material after initial approval. Or use separate Update Log form TR-AA-230-1003-F16.
Protected Conten t:  (CAPRs, corrective actions, licensing commitments, etc. associated with this material
PREPARER    DATE
)  {C001} None PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0 JPM Page 3 of 16 TR-AA-230-1003-F10, Revision 2 UPDATE LOG: Indicate in the following table any minor changes or major revisions (as defined in TR
  #           DESCRIPTION OF CHANGE                   REASON FOR CHANGE         AR/TWR#
-AA-230-1003) made to the material after initial approval. Or use separate Update Log form TR
SUPERVISOR  DATE TR-AA-230-1003-F10, Revision 2
-AA-230-1003-F16. # DESCRIPTION OF CHANGE REASON FOR CHANGE AR/TWR# PREPARER DATE SUPERVISO R DATE PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0  JPM Page 4 of 16  TR-AA-230-1003-F10, Revision 2 SIMULATOR SET
-UP:  (Only required for simulator JPMs)
SIMULATOR SETUP INSTRUCTIONS
: 1. None 2. SIMULATOR MALFUNCTIONS:
None  SIMULATOR OVERRIDES:


PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,                      JPM Rev. 0                                    Page 4 of 16 SIMULATOR SET-UP: (Only required for simulator JPMs)
SIMULATOR SETUP INSTRUCTIONS:
: 1. None 2.
SIMULATOR MALFUNCTIONS:
None SIMULATOR OVERRIDES:
None SIMULATOR REMOTE FUNCTIONS:
None SIMULATOR REMOTE FUNCTIONS:
None  
None Required Materials:       OP 8A Spent Fuel Pool Cooling Water System Operation marked up to align P-12A SFP Cooling Pump to HX-13B SFP Heat Exchanger General  
 
Required Materials:
OP 8A Spent Fuel Pool Cooling Water System Operation marked up to align P
-12A SFP Cooling Pump to HX
-13B SFP Heat Exchanger General  


==References:==
==References:==
OP 8A Spent Fuel Pool Cooling Water System Operation Task Standards:            Per OP 8A align P-12A SFP Cooling Pump to HX-13B SFP Heat Exchanger TR-AA-230-1003-F10, Revision 2


OP 8A Spent Fuel Pool Cooling Water System Operation Task Standards:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,                       JPM Rev. 0                                     Page 5 of 16 I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
Per OP 8A align P
-12A SFP Cooling Pump to HX
-13B SFP Heat Exchanger
 
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0 JPM Page 5 of 16 TR-AA-230-1003-F10, Revision 2 I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.
INITIAL CONDITIONS:
INITIAL CONDITIONS:
Maintenance is required in the Spent Fuel Pool Cooling System which requires a cooling alignment change. Currently P
* Maintenance is required in the Spent Fuel Pool Cooling System which requires a cooling alignment change.
-12A , SFP Cooling Pump is in service to HX
* Currently P-12A, SFP Cooling Pump is in service to HX-13A SFP Heat Exchanger.
-13A SFP Heat Exchanger.
INITIATING CUES (IF APPLICABLE):
* You have been directed by OS1 to perform Section 5.5 of OP 8A, Spent Fuel Pool Cooling Water System Operation to align P-12A, SFP Cooling Pump, to HX-13B, SFP Heat Exchanger.
NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
TR-AA-230-1003-F10, Revision 2
 
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,                  JPM Rev. 0                                Page 6 of 16 JPM PERFORMANCE INFORMATION Start Time:
NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e., the examinee looks or asks for the indication).
NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Performance Step: 1          5.5.1 P-12A, SFP Cooling Pump, is in service to HX-13A, SFP Critical N                            Heat Exchanger.
Standard:                    Initial step as complete, information given in turnover.
Evaluator Cue:                If asked, P-12A SFP Cooling Pump is operating.
Performance:                  SATISFACTORY                  UNSATISFACTORY Comments:
Performance Step: 2          5.5.2 CHECK SF-22, HX-13B SFP Heat Exchanger Outlet, is Critical N                            SHUT.
Standard:                    Check SF-22 SHUT Evaluator Cue:                Valve stem is inserted for SF-22.
Performance:                  SATISFACTORY                  UNSATISFACTORY Comments:
TR-AA-230-1003-F10, Revision 2
 
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,          JPM Rev. 0                            Page 7 of 16 Performance Step: 3          5.5.3 CHECK the following valves are OPEN:
Critical N                    a. SF-23, P-12A and P-12B SFP Cooling Pump Discharge Header Cross-connect.
: b. SW-2927B, HX-13B SFP HX SW Inlet.
Standard:                    Check valves are OPEN.
Evaluator Note:              If examinee asks Control Room for status of SW-2927B report back valve indicates OPEN.
Evaluator Cue:                Valve stems are extended for SF-23 and SW-2927B.
Performance:                  SATISFACTORY            UNSATISFACTORY Comments:
Performance Step: 4          5.5.4 OPEN SW-2930B, HX 13B SFP HX SW Outlet.
Critical Y Standard:                    Have Control Room OPEN SW-2930B.
Evaluator Note:              If examinee checks SW-2930B locally cue valve position consistent with reports given from Control Room (stroking open, etc).
Evaluator Cue:                When examinee asks Control Room to OPEN SW-2930B report back valve SW-2930B was operated and indicates OPEN.
Performance:                  SATISFACTORY            UNSATISFACTORY Comments:
TR-AA-230-1003-F10, Revision 2
 
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,              JPM Rev. 0                              Page 8 of 16 Performance Step: 5          5.5.5 THROTTLE OPEN SW-746, HX-13B SFP HX Return Critical Y                    Throttle, for expected heat load.
Standard:                    Throttle OPEN SW-746 for expected heat load (can check SW-661 position as reference).
Evaluator Cue:                Handwheel for SW-746 OPEN per examinees request.
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
Performance Step: 6          5.5.6 SHUT SF-21, HX-13A SFP Heat Exchanger Outlet.
Critical Y Standard:                    SHUT SF-21.
Evaluator Note:              NOTE: The following step will momentarily dead head P-12A.
Do not delay the performance of step 5.5.7 once step 5.5.6 is complete.
Evaluator Cue:                Handwheel rotated clockwise until SF-21 valve stem is inserted.
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
TR-AA-230-1003-F10, Revision 2


INITIATING CUES (IF APPLICABLE):
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,              JPM Rev. 0                              Page 9 of 16 Performance Step: 7          5.5.7 OPEN SF-22, HX-13B SFP Heat Exchanger Outlet.
You have been directed by OS1 to perform Section 5.5 of OP 8A
Critical Y Standard:                    OPEN SF-22 Evaluator Cue:                Handwheel for SF-22 rotated counterclockwise until valve stem is extended.
, Spent Fuel Pool Cooling Water System Operation to align P
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
-12A , SFP Cooling Pump
Performance Step: 8          5.5.8 THROTTLE SF-12, HX-13B SFP Heat Exchanger Inlet, to Critical Y                          PROVIDE 1200 to 1300 gpm flow rate.
, to HX-13B , SFP Heat Exchanger.
Standard:                    Turn handwheel counterclockwise until indicated SFP Cooling Water Flow is 1200 to 1300 gpm.
NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.  
Evaluator Note:              NOTE: Following step requires two (2) operators.
Flow will be lower than required initially and SF-12 should be throttled open until the report of 1250 gpm is received.
Evaluator Cue:                Cue examinee another operator will standby SFP Cooling flow indicator with flow at 1150 gpm.
As SF-12 is throttled OPEN, cue SFP cooling flow rises and is reported as 1250 gpm, then examinee stops opening SF-12.
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
TR-AA-230-1003-F10, Revision 2
 
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,              JPM Rev. 0                              Page 10 of 16 Performance Step: 9          5.5.9 SHUT SW-2930A, HX 13A SFP HX SW Outlet.
Critical N Standard:                    Have Control Room SHUT SW-2930A.
Evaluator Note:              If examinee checks SW-2930A locally cue valve position consistent with reports given from Control Room (stroking shut, etc).
Evaluator Cue:                When examinee asks Control Room to SHUT SW-2930A report back valve SW-2930A was operated and indicates SHUT.
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
Performance Step: 10          5.5.10 THROTTLE valve SW-746, HX-13B SFP HX Return Critical N                          Throttle, as necessary to MAINTAIN spent fuel pool temperature between 70 and 90&deg;F.
Standard:                    Examinee checks SFP Temperature.
Evaluator Cue:               Temperature of SFP is 81&deg;F and stable.
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
TR-AA-230-1003-F10, Revision 2


PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0  JPM Page 6 of 16  TR-AA-230-1003-F10, Revision 2 JPM PERFORMANCE INFORMATION Start Time:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,         JPM Rev. 0                           Page 11 of 16 Performance Step: 11 5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical Y HX-13B SFP HX:
NOTE:  When providing "Evaluator Cues" to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinee's actions warrant receiving the information (i.e., the examinee looks or asks for the indication).
: a. SHUT SW-665, HX-13A SFP HX Return RE-220 Inlet Isolation.
NOTE: Critical steps are marked with a "Y" below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.
Standard:                     SHUT SW-665 Evaluator Cue:               Handwheel turned clockwise and valve stem inserted for SW-665.
Performance Step:
Performance:                 SATISFACTORY               UNSATISFACTORY Comments:
1 Critical  N  5.5.1  P-12A, SFP Cooling Pump, is in service to HX
Performance Step: 12          5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical Y                          HX-13B SFP HX:
-13A, SFP Heat Exchanger.
: b. OPEN SW-747, HX-13B SFP HX Return RE-220 Inlet Isolation.
Standard: Initial step as complete, information given in turnover.
Standard:                     OPEN SW-747 Evaluator Cue:               Handwheel turned counter clockwise and valve stem extended for SW-747.
Evaluator Cue:
Performance:                 SATISFACTORY               UNSATISFACTORY Comments:
If asked, P
TR-AA-230-1003-F10, Revision 2
-12A SFP Cooling Pump is operating.
Performance:
SATISFACTORY UNSATISFACTORY Comments:      Performance Step:
2 Critical  N  5.5.2  CHECK SF-22, HX-13B SFP Heat Exchanger Outlet, is SHUT. Standard: Check SF-22 SHUT  Evaluator Cue:
Valve stem is inserted for SF
-22. Performance:
SATISFACTORY UNSATISFACTORY Comments:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0  JPM Page 7 of 16  TR-AA-230-1003-F10, Revision 2 Performance Step:
3  Critical  N  5.5.3  CHECK the following valves are OPEN:
: a. SF-23, P-12A and P-12B SFP Cooling Pump Discharge Header Cross-connect. b. SW-2927B, HX-13B SFP HX SW Inlet.
Standard: Check valves are OPEN.
Evaluator Note:
If examinee asks Control Room for status of SW
-2927B report back valve indicates OPEN.
Evaluator Cue:
Valve stems are extended for SF
-23 and SW-2927B. Performance:
SATISFACTORY UNSATISFACTORY Comments:      Performance Step:
4  Critical  Y  5.5.4  OPEN SW-2930B, HX 13B SFP HX SW Outlet.
Standard: Have Control Room OPEN SW
-2930B. Evaluator Note:
If examinee checks SW
-2930B locally cue valve position consistent with reports given from Control Room (stroking open, etc).
Evaluator Cue:
When examinee asks Control Room to OPEN SW
-2930B report back valve SW
-2930B was operated and indicates OPEN.
Performance:
SATISFACTORY UNSATISFACTORY Comments:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0 JPM Page 8 of 16  TR-AA-230-1003-F10, Revision 2 Performance Step:
5  Critical  Y  5.5.5  THROTTLE OPEN SW-746, HX-13B SFP HX Return Throttle, for expected heat load.
Standard: Throttle OPEN SW
-746 for expected heat load (can check SW
-661 position as reference).
Evaluator Cue:
Handwheel for SW-746 OPEN per examinees request.
Performance:
SATISFACTORY UNSATISFACTORY Comments:      Performance Step:
6  Critical  Y  5.5.6  SHUT SF-21, HX-13A SFP Heat Exchanger Outlet.
Standard: SHUT SF-21. Evaluator Note:
NOTE:  The following step will momentarily dead head P
-12A. Do not delay the performance of step 5.5.7 once step 5.5.6 is complete. Evaluator Cue:
Handwheel rotated clockwise until SF
-21 valve stem is inserted.
Performance:
SATISFACTORY UNSATISFACTORY Comments:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0  JPM Page 9 of 16  TR-AA-230-1003-F10, Revision 2 Performance Step:
7  Critical  Y  5.5.7  OPEN SF-22, HX-13B SFP Heat Exchanger Outlet.
Standard: OPEN SF-22  Evaluator Cue:
Handwheel for SF
-22 rotated counterclockwise until valve stem is extended.
Performance:
SATISFACTORY UNSATISFACTORY Comments:      Performance Step:
8  Critical  Y  5.5.8  THROTTLE SF-12, HX-13B SFP Heat Exchanger Inlet, to PROVIDE 1200 to 1300 gpm flow rate.
Standard: Turn handwheel counterclockwise until indicated SFP Cooling Water Flow is 1200 to 1300 gpm.
Evaluator Note:
NOTE:  Following step requires two (2) operators.
Flow will be lower than required initially and SF
-12 should be throttle d open until the report of 1250 gpm is received.
Evaluator Cue:
Cue examinee another operator will standby SFP Cooling flow indicator with flow at 1150 gpm.
As SF-12 is throttled OPEN, cue SFP cooling flow rises and is reported as 1250 gpm, then examinee stops opening SF
-12. Performance:
SATISFACTORY UNSATISFACTORY Comments:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0  JPM Page 10 of 16  TR-AA-230-1003-F10, Revision 2 Performance Step:
9  Critical  N  5.5.9  SHUT SW-2930A, HX 13A SFP HX SW Outlet.
Standard: Have Control Room SHUT SW
-2930A. Evaluator Note:
If examinee checks SW
-2930A locally cue valve position consistent with reports given from Control Room (stroking shut, etc).
Evaluator Cue:
When examinee asks Control Room to SHUT SW
-2930A report back valve SW
-2930A was operated and indicates SHUT.
Performa nce:  SATISFACTORY UNSATISFACTORY Comments:      Performance Step:
10  Critical  N  5.5.10  THROTTLE valve SW-746, HX-13B SFP HX Return Throttle, as necessary to MAINTAIN spent fuel pool temperature between 70 and 90&deg;F.
Standard: Examin ee check s SFP Temperature.
Evaluator Cue:
Temperature of SFP is 81&deg;F and stable.
Performance:
SATISFACTORY UNSATISFACTORY Comments:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0  JPM Page 11 of 16 TR-AA-230-1003-F10, Revision 2 Performance Step:
11 Critical  Y  5.5.11 ALIGN radiation monitor RE
-220 to TAKE samples fro m HX-13B SFP HX:
: a. SHUT SW-665, HX-13A SFP HX Return RE
-220 Inlet Isolation.
Standard: SHUT SW-665   Evaluator Cue:
Handwheel turned clockwise and valve stem inserted for SW-665. Performance:
SATISFACTORY UNSATISFACTORY Comments:     Performance Step:
1 2  Critical  Y  5.5.11 ALIGN radiation monitor RE
-220 to TAKE samples from HX-13B SFP HX:
: b. OPEN SW-747, HX-13B SFP HX Return RE
-220 Inlet Isolation.
Standard: OPEN SW-747   Evaluator Cue:
Handwheel turned counter clockwise and valve stem extended for SW-747. Performance:
SATISFACTORY UNSATISFACTORY Comments:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0  JPM Page 12 of 16  TR-AA-230-1003-F10, Revision 2 Performance Step:
1 3  Critical  Y  5.5.11  ALIGN radiation monitor RE
-220 to TAKE samples from HX-13B SFP HX:
: c. SHUT SW-668, HX-13A SFP HX Return RE
-220 Outlet Isolation.
Standard: SHUT SW-668  Evaluator Cue:
Handwheel turned clockwise and valve stem inserted for SW-669. Performance:
SATISFACTORY UNSATISFACTORY Comments:      Performance Step:
1 4  Critical  Y  5.5.11  ALIGN radiation monitor RE
-220 to TAKE samples from HX-13B SFP HX:
: d. OPEN SW-748, HX-13B SFP HX Return RE
-220 Outlet Isolation.
Standard: OPEN SW-748  Evaluator Cue:
Handwheel turned counter clockwise and valve stem extended for SW-748. Performance:
SATISFACTORY UNSATISFACTORY Comments:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0  JPM Page 13 of 16  TR-AA-230-1003-F10, Revision 2 Performance Step:
1 5  Critical  N  5.5.11  ALIGN radiation monitor RE
-220 to TAKE samples from HX-13B SFP HX:
: e. THROTTLE OPEN valve SW-667, RE-220 SW Throttle, to OBTAIN a flow rate greater than or equal to 8 gpm as indicated by flow through SG
-4456 AND RE-220 is NOT in "FAIL EXTERNAL" on PPCS.
Standard: Throttle OPEN SW
-667 and obtain flow of 8 gpm.
Evaluator Note:
SW-667 is a ball valve.
There is no flow meter locally, only a flapper valve indicating flow. Adequate flow is the flapper valve open with the RMS Server indicating not failed (low flow)
. Evaluator Cue:
SG-4456 flapper opens as examinee throttles open SW
-667. If Control is called, when flapper valve shows full flow, the RMS Server shows Green for RE
-220. Performance:
SATISFACTORY UNSATISFACTORY Comments:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0  JPM Page 14 of 16  TR-AA-230-1003-F10, Revision 2 Performance Step:
16  Critical  N  When complete examinee informs OS1 section 5.5 of OP 8A is completed. P-12A SFP Cooling Pump is aligned to HX
-13B SFP Heat Exchanger    Standard: Examinee informs OS1 step 5.5 of OP 8A is completed.
Evaluator Cue:
Acknowledge examinees report.
Performance:
SATISFACTORY UNSATISFACTORY Comment s:
Terminating Cues:
The JPM is complete


NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,          JPM Rev. 0                          Page 12 of 16 Performance Step: 13          5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical Y                          HX-13B SFP HX:
: c. SHUT SW-668, HX-13A SFP HX Return RE-220 Outlet Isolation.
Standard:                    SHUT SW-668 Evaluator Cue:                Handwheel turned clockwise and valve stem inserted for SW-669.
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
Performance Step: 14          5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical Y                          HX-13B SFP HX:
: d. OPEN SW-748, HX-13B SFP HX Return RE-220 Outlet Isolation.
Standard:                    OPEN SW-748 Evaluator Cue:                Handwheel turned counter clockwise and valve stem extended for SW-748.
Performance:                  SATISFACTORY              UNSATISFACTORY Comments:
TR-AA-230-1003-F10, Revision 2


Stop Time:  
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,                JPM Rev. 0                                Page 13 of 16 Performance Step: 15          5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical N                              HX-13B SFP HX:
: e. THROTTLE OPEN valve SW-667, RE-220 SW Throttle, to OBTAIN a flow rate greater than or equal to 8 gpm as indicated by flow through SG-4456 AND RE-220 is NOT in "FAIL EXTERNAL" on PPCS.
Standard:                    Throttle OPEN SW-667 and obtain flow of 8 gpm.
Evaluator Note:              SW-667 is a ball valve.
There is no flow meter locally, only a flapper valve indicating flow. Adequate flow is the flapper valve open with the RMS Server indicating not failed (low flow).
Evaluator Cue:                SG-4456 flapper opens as examinee throttles open SW-667.
If Control is called, when flapper valve shows full flow, the RMS Server shows Green for RE-220.
Performance:                  SATISFACTORY                UNSATISFACTORY Comments:
TR-AA-230-1003-F10, Revision 2


PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System , Rev. 0 JPM Page 15 of 16 TR-AA-230-1003-F10 , Revision 2  Examinee:      Evaluator:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,               JPM Rev. 0                                 Page 14 of 16 Performance Step: 16          When complete examinee informs OS1 section 5.5 of OP 8A is Critical N                    completed. P-12A SFP Cooling Pump is aligned to HX-13B SFP Heat Exchanger Standard:                    Examinee informs OS1 step 5.5 of OP 8A is completed.
RO    SRO    STA    Non-Lic  SRO CERT Date:        LOIT RO  LOIT SRO    PERFORMANCE RESULTS:
Evaluator Cue:               Acknowledge examinees report.
SAT:      UNSAT:        Remediation required:
Performance:                 SATISFACTORY            UNSATISFACTORY Comments:
YES        NO        COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
Terminating Cues:
EXAMINER NOTE:
The JPM is complete NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
ENSURE ALL EXAM MATERIAL IS COLLECTED AND PROCEDURES CLEANED, AS APPROPRIATE.
Stop Time:
EVALUATOR'S SIGNATURE:
TR-AA-230-1003-F10, Revision 2
NOTE: Only this page needs to be retained in examinee's record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
JPM Page 16 of 16  TR-AA-230-1003-F10 , Revision 2 TURNOVER SHEET


INITIAL CONDITIONS:
PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System,                  JPM Rev. 0                                    Page 15 of 16 Examinee:                                                  Evaluator:
Maintenance is required in the Spent Fuel Pool Cooling System which requires a cooling alignment change. Currently P
RO      SRO      STA      Non-Lic    SRO CERT              Date:
-12A , SFP Cooling Pump is in service to H X-13A SFP Heat Exchanger.
LOIT RO        LOIT SRO PERFORMANCE RESULTS:                    SAT:                          UNSAT:
Remediation required:            YES                        NO COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).
EXAMINER NOTE:      ENSURE ALL EXAM MATERIAL IS COLLECTED AND PROCEDURES CLEANED, AS APPROPRIATE.
EVALUATORS SIGNATURE:
NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.
TR-AA-230-1003-F10, Revision 2


JPM Page 16 of 16 TURNOVER SHEET INITIAL CONDITIONS:
* Maintenance is required in the Spent Fuel Pool Cooling System which requires a cooling alignment change.
* Currently P-12A, SFP Cooling Pump is in service to HX-13A SFP Heat Exchanger.
INITIATING CUES (IF APPLICABLE):
INITIATING CUES (IF APPLICABLE):
You have been directed by OS1 to perform Section 5.5 of OP 8A, Spent Fuel Pool Cooling Water System Operation to align P
* You have been directed by OS1 to perform Section 5.5 of OP 8A, Spent Fuel Pool Cooling Water System Operation to align P-12A, SFP Cooling Pump to HX-13B SFP Heat Exchanger.
-12A , SFP Cooling Pump to HX
NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.
-13B SFP Heat Exchanger.
TR-AA-230-1003-F10, Revision 2}}
 
NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.}}

Latest revision as of 11:56, 31 October 2019

2015 Point Beach Nuclear Plant Initial License Examination Administered In-Plant JPMs
ML15125A503
Person / Time
Site: Point Beach  NextEra Energy icon.png
Issue date: 03/06/2015
From: Mcneil D
NRC/RGN-III/DRS/OLB
To:
Point Beach
References
Download: ML15125A503 (43)


Text

JPM JOB PERFORMANCE MEASURE Page 1 of 10 JPM TITLE: Locally Operate the Atmospheric Steam Dump Control Valves JPM NUMBER: PBN JPM P000.044a.AOT REV. 3 TASK NUMBER(S) / PBN P000.044.AOT / Locally Operate the Atmospheric Steam Dump TASK TITLE(S): Control Valves 035 K6.02 3.1/3.5 K/A NUMBERS: K/A VALUE:

035 A3.02 3.7/3.5 Justification (FOR K/A VALUES <3.0):

TASK APPLICABILITY:

RO SRO STA Non-Lic SRO CERT OTHER:

APPLICABLE METHOD OF TESTING: Simulate/Walkthrough: X Perform:

EVALUATION LOCATION: In-Plant: X Control Room:

Simulator: Other:

Lab:

Time for Completion: 10 Minutes Time Critical: No Alternate Path [NRC]: No Alternate Path [INPO]: No TR-AA-230-1003-F10, Revision 2

PBN JPM P000.044a.AOT, Locally Operate the Atmospheric JPM Steam Dump Valves, Rev. 3 Page 2 of 10 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Do the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the job level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Is justification provided for tasks with K/A values less than 3.0?
11. Have the performance steps been identified and classified (Critical /

Sequence / Time Critical) appropriately?

12. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
13. Are all references identified, current, accurate, and available to the trainee?
14. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
15. Are all critical steps supported by procedural guidance? (e.g., if licensing, EP or other groups were needed to determine correct actions, then the answer should be NO.)
16. If the JPM is to be administered to an LOIT student, has the required knowledge been taught to the individual prior to administering the JPM? TPE does not have to be completed, but the JPM evaluation may not be valid if they have not been taught the required knowledge.

All questions/statements must be answered YES or N/A or the JPM is not valid for use. If all questions/statements are answered YES or N/A, then the JPM is considered valid and can be performed as written. The individual(s) performing the initial validation shall sign and date the cover sheet.

Protected Content: (CAPRs, corrective actions, licensing commitments, etc. associated with this material)

{C001}

TR-AA-230-1003-F10, Revision 2

PBN JPM P000.044a.AOT, Locally Operate the Atmospheric JPM Steam Dump Valves, Rev. 3 Page 3 of 10 UPDATE LOG: Indicate in the following table any minor changes or major revisions (as defined in TR-AA-230-1003) made to the material after initial approval. Or use separate Update Log form TR-AA-230-1003-F16.

REASON FOR AR/TWR PREPARER DATE

  1. DESCRIPTION OF CHANGE CHANGE # SUPERVISOR DATE Rev. 0 See microfilm.

Rev. 1 Revised cue for the 2012 NRC ILT Exam.

Rev. 2 Unknown Rev. 3 Updated for the 2014 operational exam.

Cue added if examinee J Hinze Rev 3 questions the Added a evaluator cue to step 1 N/A Pen/Ink applicability of AOP-10C T Larson TR-AA-230-1003-F10, Revision 2

PBN JPM P000.044a.AOT, Locally Operate the Atmospheric JPM Steam Dump Valves, Rev. 3 Page 4 of 10 SIMULATOR SET-UP: (Only required for simulator JPMs)

Simulator Setup Instructions:

  • None SIMULATOR MALFUNCTIONS:
  • None SIMULATOR OVERRIDES:
  • None SIMULATOR REMOTE FUNCTIONS:
  • None Required Materials: FOP 1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H - Unit 2 Facade) page 108 Unit 2 Secondary System Isolation General

References:

FOP 1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H - Unit 2 Facade)

Task Standards: Locally operate 2MS-2015 per FOP 1.2 using the gagging device.

TR-AA-230-1003-F10, Revision 2

PBN JPM P000.044a.AOT, Locally Operate the Atmospheric JPM Steam Dump Valves, Rev. 3 Page 5 of 10 I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

  • Unit 2 tripped from full power due to a fire in the Unit 2 Facade.
  • 2MS-2015 'B' SG Atmospheric Steam Dump Valve is operating sporadically and currently is partially open.
  • The fire is OUT and the Fire Brigade Leader has determined it is safe for personnel to access the facade area to perform any needed actions.

INITIATING CUES (IF APPLICABLE):

  • OS2 directs you to fail shut 2MS-2015, 'B' SG Atmospheric Steam Dump Valve per FOP-1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H-Unit 2 Facade) and notify the Control Room when the valve it is shut.

NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.

TR-AA-230-1003-F10, Revision 2

PBN JPM P000.044a.AOT, Locally Operate the Atmospheric JPM Steam Dump Valves, Rev. 3 Page 6 of 10 JPM PERFORMANCE INFORMATION Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e., the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.

Performance Step: 1 1. Fail 2MS-2015, 'B' SG Atmospheric Dump Valve SHUT by:

Critical Y

  • Shut IA-872, SG B Atmospheric Steam Dump Operating Air Inlet The examinee shuts IA-872, SG B Atmospheric Steam Dump Standard:

Operating Air Inlet.

If asked, control air is reading approximately half scale.

Evaluator Cue:

IA-872 valve handwheel is fully inserted.

IF ASKED, AOP-10C (AS REFERENCED IN FOP 1.2) IS NOT Evaluator Cue: APPLICABLE DUE TO THE LOCATION OF THE FIRE. THIS CUE IS APPLICABLE FOR THE DURATION OF THE JPM.

Performance: SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P000.044a.AOT, Locally Operate the Atmospheric JPM Steam Dump Valves, Rev. 3 Page 7 of 10 Performance Step: 2 2. Fail 2MS-2015, 'B' SG Atmospheric Dump Valve SHUT by:

Critical Y

  • Open moisture trap filter plug for 2MS-2015 to vent air Standard: The examinee vents air for 2MS-2015 Evaluator Cue: The moisture trap filter plug is open. Initially there was a sound of air venting, after several seconds it has stopped.

If asked, control air pressure is reading zero.

If asked, 2MS-2015 indicates shut locally.

Performance: SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________

Performance Step: 3 3. Report the status of 2MS-2015 to the Control Room.

Critical N Standard: The examinee notifies the Control Room that 2MS-2015 is shut locally.

Evaluator Cue: The Control Room acknowledges your report and OS2 directs you to locally throttle 2MS-2015 five turns open using the gagging handwheel.

If asked, there are no further actions required by AOP-10C Attachment C.

Performance: SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P000.044a.AOT, Locally Operate the Atmospheric JPM Steam Dump Valves, Rev. 3 Page 8 of 10 Performance Step: 4 4. Using the gagging handwheel, open 2MS-2015, 'B' SG Critical Y Atmospheric Dump Valve 5 turns.

Standard: The examinee opens 2MS-2015 five turns using the manual gagging device.

Evaluator Note: The handwheel must be turned clockwise to gag the valve open.

If the examinee indicates the handwheel is being turned counter-clockwise, provide a cue that the handwheel did not move.

Evaluator Cue: 2MS-2015 gagging handwheel is turned five turns open and the sound of steam flow is heard.

Performance: SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________

Performance Step: 5 5. Inform the Control Room the status of 2MS-2015.

Critical N Standard: The examinee notifies the Control Room that 2MS-2015 is gagged open five turns.

Evaluator Cue: The Control Room acknowledges your report.

Performance: SATISFACTORY UNSATISFACTORY Comments: ______________________________________________________

Terminating Cues: THIS COMPLETES THE JPM NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.

Stop Time:

TR-AA-230-1003-F10, Revision 2

PBN JPM P000.044a.AOT, Locally Operate the Atmospheric JPM Steam Dump Valves, Rev. 3 Page 9 of 10 Examinee: Evaluator:

RO SRO STA Non-Lic SRO CERT Date:

LOIT RO LOIT SRO PERFORMANCE RESULTS: SAT: UNSAT:

Remediation required: YES NO COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).

EXAMINER NOTE: ENSURE ALL EXAM MATERIAL IS COLLECTED AND PROCEDURES CLEANED, AS APPROPRIATE.

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

TR-AA-230-1003-F10, Revision 2

JPM JOB PERFORMANCE MEASURE Page 10 of 10 TURNOVER SHEET INITIAL CONDITIONS:

  • Unit 2 tripped from full power due to a fire in the Unit 2 Facade.
  • 2MS-2015 'B' SG Atmospheric Steam Dump Valve is operating sporadically and currently is partially open.
  • The fire is OUT and the Fire Brigade Leader has determined it is safe for personnel to access the facade area to perform any needed actions.

INITIATING CUES (IF APPLICABLE):

  • OS2 directs you to fail shut 2MS-2015, 'B' SG Atmospheric Steam Dump Valve per FOP-1.2, Potential Fire Affected Safe Shutdown Components (Fire Area A01H-Unit 2 Facade) and notify the Control Room when the valve it is shut.

NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.

TR-AA-230-1003-F10, Revision 2

JPM JOB PERFORMANCE MEASURE Page 1 of 17 JPM TITLE: Shift Battery Chargers (Battery Charger D-09 Supplying Power to Bus D-02)

JPM NUMBER: PBN JPM P063.003a.AOT REV. 8 TASK NUMBER(S) / PBN P063.003.AOT / Shift Battery Chargers TASK TITLE(S):

2.1.30 4.4 / 4.0 K/A NUMBERS: K/A VALUE:

063 K1.03 2.9 / 3.5 Justification (FOR K/A VALUES <3.0):

TASK APPLICABILITY:

RO SRO STA Non-Lic SRO CERT OTHER:

APPLICABLE METHOD OF TESTING: Simulate/Walkthrough: X Perform:

EVALUATION LOCATION: In-Plant: X Control Room:

Simulator: Other:

Lab:

Time for Completion: 30 Minutes Time Critical: No Alternate Path [NRC]: No Alternate Path [INPO]: No Developed by: Jeffrey Hinze Instructor/Developer Date Reviewed by: Andrew Zommers Instructor (Instructional Review) Date Validated by: Jeff Baugniet SME (Technical Review) Date Approved by: Randy Amundson Training Supervision Date Approved by: Tom Larson Training Program Owner Date TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 2 of 17 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Do the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the job level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Is justification provided for tasks with K/A values less than 3.0?
11. Have the performance steps been identified and classified (Critical /

Sequence / Time Critical) appropriately?

12. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
13. Are all references identified, current, accurate, and available to the trainee?
14. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
15. Are all critical steps supported by procedural guidance? (e.g., if licensing, EP or other groups were needed to determine correct actions, then the answer should be NO.)
16. If the JPM is to be administered to an LOIT student, has the required knowledge been taught to the individual prior to administering the JPM? TPE does not have to be completed, but the JPM evaluation may not be valid if they have not been taught the required knowledge.

All questions/statements must be answered YES or N/A or the JPM is not valid for use. If all questions/statements are answered YES or N/A, then the JPM is considered valid and can be performed as written. The individual(s) performing the initial validation shall sign and date the cover sheet.

Protected Content: (CAPRs, corrective actions, licensing commitments, etc. associated with this material)

{C001}

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 3 of 17 UPDATE LOG: Indicate in the following table any minor changes or major revisions (as defined in TR-AA-230-1003) made to the material after initial approval. Or use separate Update Log form TR-AA-230-1003-F16.

REASON FOR AR/TWR PREPARER DATE

  1. DESCRIPTION OF CHANGE CHANGE # SUPERVISOR DATE Rev. 0-2 See historical records.

Reformatted to the current revision of QF-1075-01. Revised to Rev. 10 of 0-SOP-DC-002, 125 VDC Rev. 3 System, Bus D-02 & Components.

Rev. 4 JPM updated to new format. Editorial changes made to JPM.

Rev. 5 Corrected typographical error. Verified correct for Rev 16 of 0-SOP-DC-002.

Rev. 6 Updated due to procedure revision. Verified correct for revision 18 of 0-SOP-DC-002.

Rev. 7 Updated for the 2014 operational exam.

Rev 8 Updated for 2015 NRC ILT Exam due to procedure change TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 4 of 17 SIMULATOR SET-UP: (Only required for simulator JPMs)

SIMULATOR SETUP INSTRUCTIONS:

  • None SIMULATOR MALFUNCTIONS:
  • None SIMULATOR OVERRIDES:
  • None SIMULATOR REMOTE FUNCTIONS:
  • None Required Materials: 0-SOP-DC-002, 125 VDC System Bus D-02 & Components General

References:

0-SOP-DC-002, 125 VDC System Bus D-02 & Components Task Standards: The examinee places Battery Charger D-09 in service for Battery Charger D-08 (D-09 initially supplying Battery D-305) in accordance with the applicable steps of 0-SOP-DC-002.

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 5 of 17 I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues.

When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

  • The DC Distribution system is operating under normal conditions.
  • Battery Charger D-09 is supplying Battery D-305.
  • Battery Charger D-09 is being supplied from 1B-49.
  • D-109 Battery Charger is OOS for maintenance.

INITIATING CUES (IF APPLICABLE):

  • OS1 directs you to place Battery Charger D-09 in service for Battery Charger D-08 in accordance with 0-SOP-DC-002, 125 VDC System, Bus D-02 & Components section 5.2, Placing Battery Charger D-09 in Service for Battery Charger D-08 (D-09 initially supplying battery D-305).

NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 6 of 17 JPM PERFORMANCE INFORMATION Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e., the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.

NOTE: The Evaluator will act as the Concurrent Checker for all necessary steps and will concur with all actions taken by the examinee.

5.2 Placing D-09 Battery Charger in Service for D-08 Charger, (D-09 Initially Supplying D-305 Battery)

Performance Step: 1 5.2.1 CHECK the following are in OFF at D-301 and D-02 OR have Critical N OPEN indication on 2C20:

  • D72-301-01, Alternate Power to D-01 DC Distr Pnl
  • D72-301-03, Alternate Power to D-02 DC Distr Pnl
  • D72-301-04, Alternate Power to 1/2D-201 DC Distr Pnl
  • D72-301-06, Feed to D-302 from D-305 Swing Station Battery
  • D72-301-07, Power to Mnt Test Equipment (no 2C20 ind)
  • D72-02-04, Feed to D-02 from D-301 Swing Batt Distr Pnl The examinee checks that the breakers at panels D-301 and D-02 Standard:

are OFF.

The examinee may question the NOTE regarding D-109 prior to the Evaluator Note: 1st step of this section. If necessary, remind the examinee of the turnover information that D-109 is OOS for maintenance.

Evaluator Cue: The breakers at panels D-301 and D-02 are in the OFF position.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 7 of 17 Performance Step: 2 5.2.2 CHECK DC current is approximately zero on D-09 Charger.

Critical N The examinee checks that Battery Charger D-09 DC CURRENT is Standard:

approximately '0' amps.

Evaluator Cue: Battery Charger D-09 DC CURRENT is '0' amps.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 3 5.2.3 PLACE D-09-DC, D-09 Swing Stn Battery Charger Output to Critical Y the OFF position on D-09.

Standard: The examinee places D-09-DC breaker to the OFF position.

Per the NOTE prior to step 5.2.3; when D-09-DC breaker is taken to Evaluator Note: OFF a D-09 Battery Charger Trouble Alarm will occur in the Control Room.

  • D-09-DC is in the OFF position.

Evaluator Cue:

  • The control room announces: "D-09 BATTERY CHARGER TROUBLE ALARM" Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 8 of 17 Performance Step: 4 5.2.4 PLACE D72-301-05, Feed to D-301 From D-305 Swing Critical Y Station Battery, to the OFF position on D-301.

Standard: The examinee places D72-301-05 to the OFF position.

As the Concurrent Checker the Evaluator will concur with all actions Evaluator Note:

taken by the examinee.

Evaluator Cue: Breaker is in the OFF position.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 5 5.2.5 IF D-09 is NOT being supplied from the desired AC source, Critical N THEN PERFORM the following: .....

D-09 is already aligned to the desired source, Step 5.2.5 has been Standard:

previously marked N/A; the examinee moves on to Step 5.2.6.

If the examinee asks, D-09 IS aligned to 1B-49, the desired AC Evaluator Cue:

source (provided in the turnover).

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 9 of 17 Performance Step: 6 5.2.6 ENSURE the following for D-09 Battery Charger:

Critical N a. D-09 voltage is approximately equal to D-08 Charger voltage - ADJUST D-09 Float potentiometer as necessary.

b. D-09 Battery Charger voltage is 132 to 135 vdc.

The examinee checks that D-08 and D-09 Charger voltages are Standard:

approximately equal and that D-09 voltage is between 132-135 VDC.

  • Battery Charger D-08 voltage is 133.5 VDC.

Evaluator Cue:

  • Battery Charger D-09 voltage is 133.5 VDC.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 7 5.2.7 ENSURE D72-301-02, Feed to D-301 from D-09 Swing Stn Critical N Battery Chgr, is in the ON position on D-301.

Standard: The examinee ensures breaker D72-301-02 is in the ON position.

Evaluator Cue: Breaker is in the ON position Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 10 of 17 Performance Step: 8 5.2.8 PLACE D72-301-03, Alternate Power to D-02 DC Distribution Critical Y Panel to the ON position on D-301.

Standard: The examinee places breaker D72-301-03 to the ON position.

Evaluator Cue: Breaker is in the ON position Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 9 5.2.9 PLACE D72-02-04, Feed to D-02 from D-301 Swing Batt Critical Y Distr Pnl to the ON position on D-02..

Standard: The examinee places breaker D72-02-04 to the ON position.

Evaluator Cue: Breaker is in the ON position Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 10 5.2.10 RECORD DC current on D-08 Charger:

Critical N D-08 DC current __________ amps The examinee records DC current (130 amps) for Battery Charger D-Standard:

08.

Evaluator Cue: DC current for Battery Charger D-08 is 130 amps.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 11 of 17 Performance Step: 11 5.2.11 PLACE D-09-DC, D-09 Swing Stn Battery Charger Output to Critical Y the ON position on D-09.

Standard: The examinee places breaker D-09-DC to ON.

Per the NOTE prior to step 5.2.11; when D-09-DC is taken to ON the Evaluator Note:

D-09 Battery Charger Trouble Alarm will clear in the Control Room.

  • Breaker is in the ON position, D-09 current moves to 90 amps.

Evaluator Cue:

  • Control Room announces: "D-09 Battery Charger Trouble Alarm Clear" Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 12 5.2.12 ADJUST D-09 Float potentiometer as necessary until the Critical N charger assumes at least 50 but no greater than 100 percent of the current previously carried by D-08 from Step 5.2.10.

The examinee verifies that D-09 current (90 amps) is between 50 Standard: and 100% of previously given D-08 current (130 amps). No adjustment is necessary.

Evaluator Note: 130 amps was given (Cued) at step 5.2.10 for D-08 load.

Evaluator Cue: D-09 current is 90 amps.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 12 of 17 Performance Step: 13 5.2.13 ENSURE D-09 Battery Charger is functioning normally Critical N (ie., no fluctuations in voltage or current and no alarms).

The examinee verifies verifies that Battery Charger D-09 is operating Standard:

properly.

D-09 Charger Status is:

  • voltage is 133.5 VDC and stable Evaluator Cue:
  • current is 90 amps and stable
  • No alarms in Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 14 5.2.14 PLACE D-08-DC, D-08 DC Station Battery Charger Output to Critical Y the OFF position on D-08.

Standard: The examinee places D-08-DC breaker to OFF position.

Per the NOTE prior to step 5.2.14; when D-08-DC breaker is taken to Evaluator Note: OFF a D-08 Battery Charger Trouble Alarm will occur in the Control Room.

  • D-08-DC is in the OFF position.

Evaluator Cue:

  • The control room announces: "D-08 BATTERY CHARGER TROUBLE ALARM" Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 13 of 17 Performance Step: 15 5.2.15 ADJUST D-09 Float potentiometer as necessary until D-09 Critical N Battery Charger voltage is 133.5 (132-135) vdc.

Standard: The examinee verifies D-09 Charger voltage is 133.5 VDC.

Evaluator Cue: D-09 Charger voltage is 133.5 VDC (previously given at step 5.2.13)

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 16 5.2.16 CHECK D-09 Charger current is approximately equal to the Critical N previous current on D-08 (recorded in Step 5.2.10).

The examinee verifies D-09 Charger current is approximately equal Standard:

to previous D-08 Charger current.

Evaluator Cue: D-09 Charger current is 130 amps.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 14 of 17 Performance Step: 17 5.2.17 PLACE D-08-AC, D-08 DC Station Battery Charger Input to Critical N the OFF position on D-08.

Standard: The examinee places D-08-AC breaker to the OFF position.

Per the NOTE prior to step 5.2.17; when D-08-AC is taken to OFF Evaluator Note: the D-08 Battery Charger Trouble Alarm will clear in the Control Room.

  • Breaker is in OFF position
  • Control Room announces, "D-08 Battery Charger Trouble Alarm Evaluator Cue:

Clear"

  • The red AC Power Failure light on D-08 Charger is OFF.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 18 5.2.18 IF D-08 contactor is operable from the Control Room, THEN Critical N TRIP D-08 Battery Charger Supply contactor.

The examinee notifies the control room to trip the D-08 Battery Standard:

Charger Supply contactor.

The Control Room acknowledges the report, then reports back that Evaluator Cue:

2B42-491, D-08 Battery Charger Supply contactor is OPEN.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 15 of 17 Performance Step: 19 5.2.19 IF D-08 contactor not operable from the Control Room, Critical N THEN TRIP locally in accordance with Section 5.7.

The examinee acknowledges that 2B42-491, D-08 Battery Charger Standard: Supply contactor was opened from the control room, marks Step 5.2.19 N/A, and moves on to Step 5.2.20.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Performance Step: 20 5.2.20 WHEN the AC Supply Contactor is tripped, THEN PLACE Critical N D72-02-07, Feed to D-02 from D-08 Stn Battery Charger to the OFF position on D-02.

Standard: The examinee places breaker D72-02-07 to the OFF position.

Evaluator Cue: Breaker is in the OFF position.

Performance: SATISFACTORY UNSATISFACTORY Comments: _____________________________________________________

Terminating Cues: THIS COMPLETES THE JPM NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.

Stop Time:

TR-AA-230-1003-F10, Revision 2

PBN JPM P063.003a.AOT, Shift Battery Chargers (Battery JPM Charger D-09 Supplying Power to Bus D-02), Rev. 8 Page 16 of 17 Examinee: Evaluator:

RO SRO STA Non-Lic SRO CERT Date:

LOIT RO LOIT SRO PERFORMANCE RESULTS: SAT: UNSAT:

Remediation required: YES NO COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).

EXAMINER NOTE: ENSURE ALL EXAM MATERIAL IS COLLECTED AND PROCEDURES CLEANED, AS APPROPRIATE.

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

TR-AA-230-1003-F10, Revision 2

JOB PERFORMANCE MEASURE JPM Page 17 of 17 TURNOVER SHEET INITIAL CONDITIONS:

  • The DC Distribution system is operating under normal conditions.
  • Battery Charger D-09 is supplying Battery D-305.
  • Battery Charger D-09 is being supplied from 1B-49.
  • D-109 Battery Charger is OOS for maintenance.

INITIATING CUES (IF APPLICABLE):

  • OS1 directs you to place Battery Charger D-09 in service for Battery Charger D-08 in accordance with 0-SOP-DC-002, 125 VDC System, Bus D-02 & Components section 5.2, Placing Battery Charger D-09 in Service for Battery Charger D-08 (D-09 initially supplying battery D-305).

NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.

TR-AA-230-1003-F10, Revision 2

JOB PERFORMANCE MEASURE JPM Page 1 of 16 JPM TITLE: Perform Lineups on the Spent Fuel Pool Cooling System JPM NUMBER: PBN JPM P033.001a.AOT REV. 0 TASK NUMBER(S) / PBN P033.001.AOT Perform Lineups of the SFP Cooling System TASK TITLE(S):

K/A NUMBERS: 033 G 2.2.15 K/A VALUE: 3.9/4.3 Justification (FOR K/A VALUES <3.0):

TASK APPLICABILITY:

RO SRO STA Non-Lic SRO CERT OTHER:

APPLICABLE METHOD OF TESTING: Simulate/Walkthrough: X Perform:

EVALUATION LOCATION: In-Plant: X Control Room:

Simulator: Other:

Lab:

Time for Completion: 20 Minutes Time Critical: NO Alternate Path [NRC]: NO Alternate Path [INPO]: NO Developed by: Andrew Zommers Instructor/Developer Date Reviewed by: Jeff Hinze Instructor (Instructional Review) Date Validated by: Jeff Baugniet SME (Technical Review) Date Approved by: Randy Amundson Training Supervision Date Approved by: Tom Larson Training Program Owner Date TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 2 of 16 JOB PERFORMANCE MEASURE VALIDATION CHECKLIST ALL STEPS IN THIS CHECKLIST ARE TO BE PERFORMED PRIOR TO USE.

REVIEW STATEMENTS YES NO N/A

1. Are all items on the signature page filled in correctly?
2. Has the JPM been reviewed and validated by SMEs?
3. Can the required conditions for the JPM be appropriately established in the simulator if required?
4. Do the performance steps accurately reflect trainees actions in accordance with plant procedures?
5. Is the standard for each performance item specific as to what controls, indications and ranges are required to evaluate if the trainee properly performed the step?
6. Has the completion time been established based on validation data or incumbent experience?
7. If the task is time critical, is the time critical portion based upon actual task performance requirements?
8. Is the job level appropriate for the task being evaluated if required?
9. Is the K/A appropriate to the task and to the licensee level if required?
10. Is justification provided for tasks with K/A values less than 3.0?
11. Have the performance steps been identified and classified (Critical /

Sequence / Time Critical) appropriately?

12. Have all special tools and equipment needed to perform the task been identified and made available to the trainee?
13. Are all references identified, current, accurate, and available to the trainee?
14. Have all required cues (as anticipated) been identified for the evaluator to assist task completion?
15. Are all critical steps supported by procedural guidance? (e.g., if licensing, EP or other groups were needed to determine correct actions, then the answer should be NO.)
16. If the JPM is to be administered to an LOIT student, has the required knowledge been taught to the individual prior to administering the JPM?

TPE does not have to be completed, but the JPM evaluation may not be valid if they have not been taught the required knowledge.

All questions/statements must be answered YES or N/A or the JPM is not valid for use. If all questions/statements are answered YES or N/A, then the JPM is considered valid and can be performed as written. The individual(s) performing the initial validation shall sign and date the cover sheet.

Protected Content: (CAPRs, corrective actions, licensing commitments, etc. associated with this material)

{C001} None TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 3 of 16 UPDATE LOG: Indicate in the following table any minor changes or major revisions (as defined in TR-AA-230-1003) made to the material after initial approval. Or use separate Update Log form TR-AA-230-1003-F16.

PREPARER DATE

  1. DESCRIPTION OF CHANGE REASON FOR CHANGE AR/TWR#

SUPERVISOR DATE TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 4 of 16 SIMULATOR SET-UP: (Only required for simulator JPMs)

SIMULATOR SETUP INSTRUCTIONS:

1. None 2.

SIMULATOR MALFUNCTIONS:

None SIMULATOR OVERRIDES:

None SIMULATOR REMOTE FUNCTIONS:

None Required Materials: OP 8A Spent Fuel Pool Cooling Water System Operation marked up to align P-12A SFP Cooling Pump to HX-13B SFP Heat Exchanger General

References:

OP 8A Spent Fuel Pool Cooling Water System Operation Task Standards: Per OP 8A align P-12A SFP Cooling Pump to HX-13B SFP Heat Exchanger TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 5 of 16 I will explain the initial conditions, which step(s) to simulate or discuss, and provide initiating cues. When you complete the task successfully, the objective for this job performance measure will be satisfied.

DURING THE JPM, ENSURE PROPER SAFETY PRECAUTIONS, FME, AND/OR RADIOLOGICAL CONCERNS AS APPLICABLE ARE FOLLOWED.

INITIAL CONDITIONS:

  • Maintenance is required in the Spent Fuel Pool Cooling System which requires a cooling alignment change.
  • Currently P-12A, SFP Cooling Pump is in service to HX-13A SFP Heat Exchanger.

INITIATING CUES (IF APPLICABLE):

  • You have been directed by OS1 to perform Section 5.5 of OP 8A, Spent Fuel Pool Cooling Water System Operation to align P-12A, SFP Cooling Pump, to HX-13B, SFP Heat Exchanger.

NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 6 of 16 JPM PERFORMANCE INFORMATION Start Time:

NOTE: When providing Evaluator Cues to the examinee, care must be exercised to avoid prompting the examinee. Typically cues are only provided when the examinees actions warrant receiving the information (i.e., the examinee looks or asks for the indication).

NOTE: Critical steps are marked with a Y below the performance step number. Failure to meet the standard for any critical step shall result in failure of this JPM.

Performance Step: 1 5.5.1 P-12A, SFP Cooling Pump, is in service to HX-13A, SFP Critical N Heat Exchanger.

Standard: Initial step as complete, information given in turnover.

Evaluator Cue: If asked, P-12A SFP Cooling Pump is operating.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 2 5.5.2 CHECK SF-22, HX-13B SFP Heat Exchanger Outlet, is Critical N SHUT.

Standard: Check SF-22 SHUT Evaluator Cue: Valve stem is inserted for SF-22.

Performance: SATISFACTORY UNSATISFACTORY Comments:

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 7 of 16 Performance Step: 3 5.5.3 CHECK the following valves are OPEN:

Critical N a. SF-23, P-12A and P-12B SFP Cooling Pump Discharge Header Cross-connect.

b. SW-2927B, HX-13B SFP HX SW Inlet.

Standard: Check valves are OPEN.

Evaluator Note: If examinee asks Control Room for status of SW-2927B report back valve indicates OPEN.

Evaluator Cue: Valve stems are extended for SF-23 and SW-2927B.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 4 5.5.4 OPEN SW-2930B, HX 13B SFP HX SW Outlet.

Critical Y Standard: Have Control Room OPEN SW-2930B.

Evaluator Note: If examinee checks SW-2930B locally cue valve position consistent with reports given from Control Room (stroking open, etc).

Evaluator Cue: When examinee asks Control Room to OPEN SW-2930B report back valve SW-2930B was operated and indicates OPEN.

Performance: SATISFACTORY UNSATISFACTORY Comments:

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 8 of 16 Performance Step: 5 5.5.5 THROTTLE OPEN SW-746, HX-13B SFP HX Return Critical Y Throttle, for expected heat load.

Standard: Throttle OPEN SW-746 for expected heat load (can check SW-661 position as reference).

Evaluator Cue: Handwheel for SW-746 OPEN per examinees request.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 6 5.5.6 SHUT SF-21, HX-13A SFP Heat Exchanger Outlet.

Critical Y Standard: SHUT SF-21.

Evaluator Note: NOTE: The following step will momentarily dead head P-12A.

Do not delay the performance of step 5.5.7 once step 5.5.6 is complete.

Evaluator Cue: Handwheel rotated clockwise until SF-21 valve stem is inserted.

Performance: SATISFACTORY UNSATISFACTORY Comments:

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 9 of 16 Performance Step: 7 5.5.7 OPEN SF-22, HX-13B SFP Heat Exchanger Outlet.

Critical Y Standard: OPEN SF-22 Evaluator Cue: Handwheel for SF-22 rotated counterclockwise until valve stem is extended.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 8 5.5.8 THROTTLE SF-12, HX-13B SFP Heat Exchanger Inlet, to Critical Y PROVIDE 1200 to 1300 gpm flow rate.

Standard: Turn handwheel counterclockwise until indicated SFP Cooling Water Flow is 1200 to 1300 gpm.

Evaluator Note: NOTE: Following step requires two (2) operators.

Flow will be lower than required initially and SF-12 should be throttled open until the report of 1250 gpm is received.

Evaluator Cue: Cue examinee another operator will standby SFP Cooling flow indicator with flow at 1150 gpm.

As SF-12 is throttled OPEN, cue SFP cooling flow rises and is reported as 1250 gpm, then examinee stops opening SF-12.

Performance: SATISFACTORY UNSATISFACTORY Comments:

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 10 of 16 Performance Step: 9 5.5.9 SHUT SW-2930A, HX 13A SFP HX SW Outlet.

Critical N Standard: Have Control Room SHUT SW-2930A.

Evaluator Note: If examinee checks SW-2930A locally cue valve position consistent with reports given from Control Room (stroking shut, etc).

Evaluator Cue: When examinee asks Control Room to SHUT SW-2930A report back valve SW-2930A was operated and indicates SHUT.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 10 5.5.10 THROTTLE valve SW-746, HX-13B SFP HX Return Critical N Throttle, as necessary to MAINTAIN spent fuel pool temperature between 70 and 90°F.

Standard: Examinee checks SFP Temperature.

Evaluator Cue: Temperature of SFP is 81°F and stable.

Performance: SATISFACTORY UNSATISFACTORY Comments:

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 11 of 16 Performance Step: 11 5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical Y HX-13B SFP HX:

a. SHUT SW-665, HX-13A SFP HX Return RE-220 Inlet Isolation.

Standard: SHUT SW-665 Evaluator Cue: Handwheel turned clockwise and valve stem inserted for SW-665.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 12 5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical Y HX-13B SFP HX:

b. OPEN SW-747, HX-13B SFP HX Return RE-220 Inlet Isolation.

Standard: OPEN SW-747 Evaluator Cue: Handwheel turned counter clockwise and valve stem extended for SW-747.

Performance: SATISFACTORY UNSATISFACTORY Comments:

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 12 of 16 Performance Step: 13 5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical Y HX-13B SFP HX:

c. SHUT SW-668, HX-13A SFP HX Return RE-220 Outlet Isolation.

Standard: SHUT SW-668 Evaluator Cue: Handwheel turned clockwise and valve stem inserted for SW-669.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Performance Step: 14 5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical Y HX-13B SFP HX:

d. OPEN SW-748, HX-13B SFP HX Return RE-220 Outlet Isolation.

Standard: OPEN SW-748 Evaluator Cue: Handwheel turned counter clockwise and valve stem extended for SW-748.

Performance: SATISFACTORY UNSATISFACTORY Comments:

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 13 of 16 Performance Step: 15 5.5.11 ALIGN radiation monitor RE-220 to TAKE samples from Critical N HX-13B SFP HX:

e. THROTTLE OPEN valve SW-667, RE-220 SW Throttle, to OBTAIN a flow rate greater than or equal to 8 gpm as indicated by flow through SG-4456 AND RE-220 is NOT in "FAIL EXTERNAL" on PPCS.

Standard: Throttle OPEN SW-667 and obtain flow of 8 gpm.

Evaluator Note: SW-667 is a ball valve.

There is no flow meter locally, only a flapper valve indicating flow. Adequate flow is the flapper valve open with the RMS Server indicating not failed (low flow).

Evaluator Cue: SG-4456 flapper opens as examinee throttles open SW-667.

If Control is called, when flapper valve shows full flow, the RMS Server shows Green for RE-220.

Performance: SATISFACTORY UNSATISFACTORY Comments:

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 14 of 16 Performance Step: 16 When complete examinee informs OS1 section 5.5 of OP 8A is Critical N completed. P-12A SFP Cooling Pump is aligned to HX-13B SFP Heat Exchanger Standard: Examinee informs OS1 step 5.5 of OP 8A is completed.

Evaluator Cue: Acknowledge examinees report.

Performance: SATISFACTORY UNSATISFACTORY Comments:

Terminating Cues:

The JPM is complete NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.

Stop Time:

TR-AA-230-1003-F10, Revision 2

PBN JPM P033.001a.AOT Perform Lineups SFP Cooling System, JPM Rev. 0 Page 15 of 16 Examinee: Evaluator:

RO SRO STA Non-Lic SRO CERT Date:

LOIT RO LOIT SRO PERFORMANCE RESULTS: SAT: UNSAT:

Remediation required: YES NO COMMENTS/FEEDBACK: (Comments shall be made for any steps graded unsatisfactory).

EXAMINER NOTE: ENSURE ALL EXAM MATERIAL IS COLLECTED AND PROCEDURES CLEANED, AS APPROPRIATE.

EVALUATORS SIGNATURE:

NOTE: Only this page needs to be retained in examinees record if completed satisfactorily. If unsatisfactory performance is demonstrated, the entire JPM should be retained.

TR-AA-230-1003-F10, Revision 2

JPM Page 16 of 16 TURNOVER SHEET INITIAL CONDITIONS:

  • Maintenance is required in the Spent Fuel Pool Cooling System which requires a cooling alignment change.
  • Currently P-12A, SFP Cooling Pump is in service to HX-13A SFP Heat Exchanger.

INITIATING CUES (IF APPLICABLE):

  • You have been directed by OS1 to perform Section 5.5 of OP 8A, Spent Fuel Pool Cooling Water System Operation to align P-12A, SFP Cooling Pump to HX-13B SFP Heat Exchanger.

NOTE: Ensure the turnover sheet that was given to the examinee is returned to the evaluator.

TR-AA-230-1003-F10, Revision 2