|
|
(9 intermediate revisions by the same user not shown) |
Line 3: |
Line 3: |
| | issue date = 06/24/2015 | | | issue date = 06/24/2015 |
| | title = R2.1 Seismic -- PVNGS Data Request and Draft Request for Additional Information | | | title = R2.1 Seismic -- PVNGS Data Request and Draft Request for Additional Information |
| | author name = DiFrancesco N | | | author name = Difrancesco N |
| | author affiliation = NRC/NRR/JLD | | | author affiliation = NRC/NRR/JLD |
| | addressee name = Weber T N | | | addressee name = Weber T |
| | addressee affiliation = Arizona Public Service Co | | | addressee affiliation = Arizona Public Service Co |
| | docket = 05000528, 05000529, 05000530 | | | docket = 05000528, 05000529, 05000530 |
Line 12: |
Line 12: |
| | document type = E-Mail | | | document type = E-Mail |
| | page count = 2 | | | page count = 2 |
| | project = TAC:MF7566 | | | project = |
| | stage = RAI | | | stage = Draft RAI |
| }} | | }} |
|
| |
|
| =Text= | | =Text= |
| {{#Wiki_filter:From:DiFrancesco, NicholasTo:Thomas.N.Weber@aps.comCc:Shams, Mohamed; Christopher.Wandell@aps.com; Carl.Stephenson@aps.com; Watford, Margaret; Jackson, Diane; Devlin-Gill, StephanieSubject:R2.1 Seismic -- PVNGS Data Request and Draft Request for Additional InformationDate:Wednesday, June 24, 2015 5:19:02 PMMr. Weber, As a follow-on to the discussion yesterday on screening status. The staff is continuing its review of the reevaluated seismic hazard for Palo Verde Nuclear Generating Station. | | {{#Wiki_filter:From: DiFrancesco, Nicholas To: Thomas.N.Weber@aps.com Cc: Shams, Mohamed; Christopher.Wandell@aps.com; Carl.Stephenson@aps.com; Watford, Margaret; Jackson, Diane; Devlin-Gill, Stephanie |
|
| |
|
| | ==Subject:== |
| | R2.1 Seismic -- PVNGS Data Request and Draft Request for Additional Information Date: Wednesday, June 24, 2015 5:19:02 PM Mr. Weber, As a follow-on to the discussion yesterday on screening status. The staff is continuing its review of the reevaluated seismic hazard for Palo Verde Nuclear Generating Station. |
| Below is an data request for review in the ePortal. | | Below is an data request for review in the ePortal. |
| Data Request In support of a confirmatory review, please provide the PVNGS composite earthquake catalog prior to the declustering analysis, meaning the catalog with 1,941 events in it as mentioned in "Palo Verde Nuclear Generating Station Seismic Source Characterization" report on page 6-7 and 6-10. The staff requests the catalog be provided in the tabular form. | | Data Request In support of a confirmatory review, please provide the PVNGS composite earthquake catalog prior to the declustering analysis, meaning the catalog with 1,941 events in it as mentioned in Palo Verde Nuclear Generating Station Seismic Source Characterization report on page 6-7 and 6-10. The staff requests the catalog be provided in the tabular form. |
| Separately, the NRC staff is planning to issue one set of request for additional information (RAI) prior to making a final screening decision. The staff has identified one RAI thus far. | | Separately, the NRC staff is planning to issue one set of request for additional information (RAI) prior to making a final screening decision. The staff has identified one RAI thus far. |
| The RAI request should be finalized during the first full week of July. Below is a draft RAI question. Please let me know if you would like a clarification call on the below request. | | The RAI request should be finalized during the first full week of July. Below is a draft RAI question. Please let me know if you would like a clarification call on the below request. |
|
| |
|
| Request for Additional Information The southwestern United States (SWUS) Ground Motion Characterization (GMC) project used the partially non-ergodic sigma model, which implies the use of a single station sigma model. For the partially non-ergodic approach, the site term (dS2Ss) is assumed to be known and as such its standard deviation (fS2S) is excluded from the single station sigma model. Use of the single station sigma approach assumes that the epistemic uncertainty for the site term is captured by the epistemic uncertainty in the Vs-kappa correction and the uncertainty in the site amplification factor. Section 2.3.6 of the Seismic Hazard and Screening Report for Palo Verde Nuclear Generating Station Units 1, 2, and 3, states that "the variability in the amplification factors results from variability in shear wave velocity, depth to hard rock, modulus reduction curves, hysteretic damping curves, and application of the nine Fourier adjustment functions to account for uncertainty in the kappa and the deep site Vs profile." | | Request for Additional Information The southwestern United States (SWUS) Ground Motion Characterization (GMC) project used the partially non-ergodic sigma model, which implies the use of a single station sigma model. For the partially non-ergodic approach, the site term (dS2Ss) is assumed to be known and as such its standard deviation (fS2S) is excluded from the single station sigma model. Use of the single station sigma approach assumes that the epistemic uncertainty for the site term is captured by the epistemic uncertainty in the Vs-kappa correction and the uncertainty in the site amplification factor. Section 2.3.6 of the Seismic Hazard and Screening Report for Palo Verde Nuclear Generating Station Units 1, 2, and 3, states that the variability in the amplification factors results from variability in shear wave velocity, depth to hard rock, modulus reduction curves, hysteretic damping curves, and application of the nine Fourier adjustment functions to account for uncertainty in the kappa and the deep site Vs profile. |
| | In order for the staff to better understand how the uncertainty in the site term is captured for the Palo Verde site; please provide a more detailed description, including all equations used for the total standard deviation of the site amplification factor. As part of the response, describe how the various epistemic and aleatory portions are combined to determine the total amplification factor uncertainty. In addition, provide a justification for including the epistemic uncertainty associated with the Vs-kappa correction as part of the uncertainty in the site amplification factor rather than as part of the logic tree for the median ground motion models and |
|
| |
|
| In order for the staff to better understand how the uncertainty in the site term is captured for the Palo Verde site; please provide a more detailed description, including all equations used for the total standard deviation of the site amplification factor. As part of the response, describe how the various epistemic and aleatory portions are combined to determine the total amplification factor uncertainty. In addition, provide a justification for including the epistemic uncertainty associated with the Vs-kappa correction as part of the uncertainty in the site amplification factor rather than as part of the logic tree for the median ground motion models and whether this decision impacts the final control point hazard curves and GMRS. Please let me know if you have any questions or concerns.
| | whether this decision impacts the final control point hazard curves and GMRS. |
| | | Please let me know if you have any questions or concerns. |
| Thanks, | | : Thanks, Nick Senior Project Manager - Seismic Reevaluation Activities U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Japan Lesson Learned Project Division nicholas.difrancesco@nrc.gov l Tel: (301) 415-1115}} |
| | |
| Nick | |
| | |
| Senior Project Manager - Seismic Reevaluation Activities U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Japan Lesson Learned Project Division nicholas.difrancesco@nrc.gov l Tel: (301) 415-1115 | |
| }} | |
|
---|
Category:E-Mail
MONTHYEARML24297A6212024-10-22022 October 2024 Request for Additional Information Relief Request (RR) No. 72: Re-Submittal of RR-39/ASME Code X1 IWC-3420, IWA-3300 ML24267A2172024-09-23023 September 2024 (E-Mail) Palo Verde Nuclear Generating Station Units 1, 2, and 3 License Amendment Request to Revise the Technical Specifications 3.5.1 and 3.5.2 Safety Injection Tank Pressure Bands, and to Use GOTHIC Code ML24257A1012024-09-11011 September 2024 Request for Additional Information License Renewal Commitment for AMP of Alloy 600 Components ML24248A2632024-09-0404 September 2024 Acceptance Review of Palo Verde Nuclear Generating Station, Units 1, 2, and 3, Relief Request (RR) No. 71: Re?Submittal of RR?30 ML24242A2812024-08-26026 August 2024 RR72 Acceptance 08/27/24 - La Jr ML24221A2382024-08-0606 August 2024 Change in Estimated Review Schedule and Level of Effort for Palo Verde Units 1, 2, and 3 ML24143A1112024-05-20020 May 2024 Draft 2nd Round Request for RAIs Concerning LAR to Modify LCO for TS 3.5.2, LCO for TS 3.6.5, and Surveillance Requirements 3.5.1.2 and 3.5.2.2 for TS 3.5.1 and TS 3.5.2 ML24138A1112024-05-16016 May 2024 Draft 2nd Round Request for Additional Information (Rais) Concerning License Amendment Request (LAR) to Modify Limiting Condition for Operation (LCO) for Technical Specification (TS) 3.5.2 ML24123A2002024-05-0101 May 2024 (E-Mail) Draft 2nd Round Request for Additional Information Concerning License Amendment Request to Modify Limiting Condition for Operation (LCO) for Technical Specification (TS) 3.5.2, LCO for TS 3.6.5, 3.5.1.2 and 3.5.2.2 for TS 3.5.1, a ML24120A2612024-05-0101 May 2024 Email Acceptance Review of Requested Licensing Action License Renewal Commitment 23A, Alloy 600 Management Program Plan ML24114A2812024-04-19019 April 2024 Request for Additional Information (RAI-10150-R1) ML24103A1222024-04-11011 April 2024 – Acceptance of Requested Licensing Action Re_ License Amendment Request to Revise Technical Specifications 3 ML24011A1002024-01-10010 January 2024 March 2024 Emergency Preparedness Program Inspection - Request for Information ML23334A1612023-11-30030 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - RAIs Associated with License Renewal Commitment for Pressurizer Surge Line Welds Inspection Program to Manage Environmentally Assisted Fatigue ML23334A0072023-11-29029 November 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAIs for LAR That Revises TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating ML23298A1232023-10-25025 October 2023 NRR E-mail Capture - Palo Verde, Unit 1 - RAIs for Relief Request 70, Proposed Alternatives for Pressurizer Lower Shell Temperature Nozzle ML23243B0082023-08-31031 August 2023 NRR E-mail Capture - Action: Opportunity to Review and Comment on a New NRC Information Collection, 10 CFR Part 50.55a, Codes and Standards (3150-XXXX) ML23233A0132023-08-18018 August 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of License Renewal Commitment for Pressurizer Surge Line Welds Inspection Program to Manage Environmentally Assisted Fatigue ML23220A0512023-08-0303 August 2023 NRR E-mail Capture - Re Palo Verde 1, 2, and 3 - SUNSI Review of UFSAR, Rev. 22 ML23202A0162023-07-20020 July 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Revise TSs 3.5.1, SITs - Operating; 3.5.2, SIT Shutdown; 3.6.5, Containment Air Temperature; and SRs for TS 3.5.1, SITs Operating ML23143A1332023-05-23023 May 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of LAR Revising TS 3.3.11 to Adopt TSTF-266-A, Rev. 3, Eliminate the Remote Shutdown System Table of Instrumentation and Controls ML23130A0132023-05-10010 May 2023 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review for Authorized Use of Mururoa Supplied Air Suits (Models V4F1 and MTH2) Pursuant to 10 CFR 20.1703 and 10 CFR 20.1705 ML23017A0932023-01-17017 January 2023 NRR E-mail Capture - Palo Verde - Acceptance of License Amendment Request Regarding Adoption of TSTF-107, Separate Control Rods That Are Untrippable Versus Inoperable (L-2022-LLA-0181) ML23013A0632023-01-13013 January 2023 NRR E-mail Capture - Palo Verde Unit 1 -Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22348A1672022-12-14014 December 2022 March 2023 Emergency Preparedness Exercise Inspection - Request for Information ML22339A2372022-12-0505 December 2022 NRR E-mail Capture - Palo Verde Unit 1 – Request for Additional Information - U1R23 Inspection Summary Report for Steam Generator Tubing ML22173A0682022-06-17017 June 2022 Email Concurrence on SE Input for Columbia Pltr LAR ML22167A1872022-06-16016 June 2022 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Revised Acceptance Review of LAR to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues ML22136A0922022-05-16016 May 2022 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Adopt TSTF-487-A, Revision 1, Relocate DNB Parameters to the COLR ML22075A1902022-03-16016 March 2022 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of LAR to Adopt TSTF-567, Add Containment Sump TS to Address GSI-191 Issues ML22055A5842022-02-24024 February 2022 NRR E-mail Capture - Palo Verde, Unit 3 - Final RAIs for 22nd Refueling Outage (Spring 2021) Steam Generator Tube Inservice Inspection Report ML22034A0132022-02-0202 February 2022 NRR E-mail Capture - Palo Verde, Unit 2 - Verbal Approval of RR-69 to Extend Containment Tendon Inspection from 2/8/22 to 6/8/22 ML22032A0312022-01-31031 January 2022 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review for an Exemption Regarding Elimination of Dafas Using RIPE Process ML22025A4012022-01-0303 January 2022 March 2022 Emergency Preparedness Program Inspection - Request for Information ML21333A1982021-11-19019 November 2021 NRC Review of PVNGS Training Needs Analysis and Training Required by Condition I of the Confirmatory Order EA-20-054 ML21306A1882021-10-18018 October 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Second Pre-submittal Meeting for the Proposed Exemption to Eliminate Dafas Using RIPE Process ML21272A0592021-09-28028 September 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - SUNSI Review of UFSAR, Rev. 21 ML21264A1352021-09-17017 September 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Acceptance Review of LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21237A0762021-08-25025 August 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of RR-67, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection ML21228A0082021-08-16016 August 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review of an LAR for Administrative Changes to Technical Specifications ML21228A1042021-08-12012 August 2021 RR-67, Request for Alternative Frequency to Containment Unbonded Post-Tensioning System Inservice Inspection (EPID L-2021-LLR-0050) (Email) ML21237A5172021-08-10010 August 2021 Email to PV Licensee and Palo Verde Nuclear Generating Station, Units 1, 2 and 3 - Notification of Inspection of the Licensees Implementation Industry Initiative Associated with the Open Phase Condition (NRC Bulletin 2012-01) and Request Fo ML21160A1442021-06-0909 June 2021 NRR E-mail Capture - Palo Verde 1 and, 2 - Acceptance Review for Order Approving Transfers of Control of Licenses for Minority Interests Subject to Expiring Leases ML21154A0082021-05-26026 May 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Official RAIs for LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21146A3342021-05-14014 May 2021 ISFSI - Final Package for an Order Associated with Indirect Transfers of Control of Licenses from Pnm to Avangrid ML21132A2372021-05-12012 May 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3, and ISFSI - Final Package for an Order Associated with Indirect Transfers of Control of Licenses from Pnm to Avangrid ML21103A3632021-04-13013 April 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Acceptance Review for Indirect Transfer of Control of Licenses Pursuant to 10 CFR 50.80 and 10 CFR 72.50 ML21064A2372021-03-0303 March 2021 ISI Request for Information Rls ML21053A0262021-02-22022 February 2021 NRR E-mail Capture - Palo Verde 1, 2 and 3 - Acceptance Review of LAR Associated with Permanent Extension of Containment ILRT Frequency to 15 Years (Type a) and CIV Leak Rate Test Frequency to 75 Months (Type C) ML21043A1462021-02-11011 February 2021 NRR E-mail Capture - Palo Verde 1, 2, and 3 - Official RAI for an Order Associated with Indirect License Transfer from Public Service Company of New Mexico to Avangrid, Inc 2024-09-04
[Table view] |
Text
From: DiFrancesco, Nicholas To: Thomas.N.Weber@aps.com Cc: Shams, Mohamed; Christopher.Wandell@aps.com; Carl.Stephenson@aps.com; Watford, Margaret; Jackson, Diane; Devlin-Gill, Stephanie
Subject:
R2.1 Seismic -- PVNGS Data Request and Draft Request for Additional Information Date: Wednesday, June 24, 2015 5:19:02 PM Mr. Weber, As a follow-on to the discussion yesterday on screening status. The staff is continuing its review of the reevaluated seismic hazard for Palo Verde Nuclear Generating Station.
Below is an data request for review in the ePortal.
Data Request In support of a confirmatory review, please provide the PVNGS composite earthquake catalog prior to the declustering analysis, meaning the catalog with 1,941 events in it as mentioned in Palo Verde Nuclear Generating Station Seismic Source Characterization report on page 6-7 and 6-10. The staff requests the catalog be provided in the tabular form.
Separately, the NRC staff is planning to issue one set of request for additional information (RAI) prior to making a final screening decision. The staff has identified one RAI thus far.
The RAI request should be finalized during the first full week of July. Below is a draft RAI question. Please let me know if you would like a clarification call on the below request.
Request for Additional Information The southwestern United States (SWUS) Ground Motion Characterization (GMC) project used the partially non-ergodic sigma model, which implies the use of a single station sigma model. For the partially non-ergodic approach, the site term (dS2Ss) is assumed to be known and as such its standard deviation (fS2S) is excluded from the single station sigma model. Use of the single station sigma approach assumes that the epistemic uncertainty for the site term is captured by the epistemic uncertainty in the Vs-kappa correction and the uncertainty in the site amplification factor. Section 2.3.6 of the Seismic Hazard and Screening Report for Palo Verde Nuclear Generating Station Units 1, 2, and 3, states that the variability in the amplification factors results from variability in shear wave velocity, depth to hard rock, modulus reduction curves, hysteretic damping curves, and application of the nine Fourier adjustment functions to account for uncertainty in the kappa and the deep site Vs profile.
In order for the staff to better understand how the uncertainty in the site term is captured for the Palo Verde site; please provide a more detailed description, including all equations used for the total standard deviation of the site amplification factor. As part of the response, describe how the various epistemic and aleatory portions are combined to determine the total amplification factor uncertainty. In addition, provide a justification for including the epistemic uncertainty associated with the Vs-kappa correction as part of the uncertainty in the site amplification factor rather than as part of the logic tree for the median ground motion models and
whether this decision impacts the final control point hazard curves and GMRS.
Please let me know if you have any questions or concerns.
- Thanks, Nick Senior Project Manager - Seismic Reevaluation Activities U.S. Nuclear Regulatory Commission Office of Nuclear Reactor Regulation Japan Lesson Learned Project Division nicholas.difrancesco@nrc.gov l Tel: (301) 415-1115