ML061980478: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 3: Line 3:
| issue date = 07/14/2006
| issue date = 07/14/2006
| title = D. C. Cook Unit 1: Draft Question Re Proposed RTD Bypass Amendment
| title = D. C. Cook Unit 1: Draft Question Re Proposed RTD Bypass Amendment
| author name = Tam P S
| author name = Tam P
| author affiliation = NRC/NRR/ADRO/DORL/LPLIII-1
| author affiliation = NRC/NRR/ADRO/DORL/LPLIII-1
| addressee name = Scarpello M, Waters J
| addressee name = Scarpello M, Waters J
Line 23: Line 23:
D. C. Cook Unit 1:  Draft Question re. Propsoed RTD Bypass Amendment(TAC MD2106)Michael, Joe:
D. C. Cook Unit 1:  Draft Question re. Propsoed RTD Bypass Amendment(TAC MD2106)Michael, Joe:
This is regarding your 5/31/06 application for amendment. We have developed the followingdraft question, and would like to discuss it with you in a conference call:  The amendment request involves the removal of the resistance temperature detector (RTD)bypass manifolds. This will affect the RTD response time, which is used in the OTT tripfunction. The OTT trip initiates automatic protective actions to mitigate the consequences ofthe following events, and therefore would be affected by the change in RTD response time:1. Loss of electrical load/turbine trip2. Uncontrolled rod cluster control assembly (RCCA) bank withdrawal at power
This is regarding your 5/31/06 application for amendment. We have developed the followingdraft question, and would like to discuss it with you in a conference call:  The amendment request involves the removal of the resistance temperature detector (RTD)bypass manifolds. This will affect the RTD response time, which is used in the OTT tripfunction. The OTT trip initiates automatic protective actions to mitigate the consequences ofthe following events, and therefore would be affected by the change in RTD response time:1. Loss of electrical load/turbine trip2. Uncontrolled rod cluster control assembly (RCCA) bank withdrawal at power
: 3. Chemical Volume Control System (CVCS) malfunction that results in a decrease in the boron concentration in the reactor coolant  
: 3. Chemical Volume Control System (CVCS) malfunction that results in a decrease in the boron concentration in the reactor coolant
: 4. Inadvertent opening of a pressurizer safety or relief valveFor each event, show that OTT will continue to provide adequate protection from departurefrom nucleate boiling following the requested change in RTD response time.This e-mail aims solely to prepare you and others for the requested conference call. Thise-mail does not convey a formal NRC staff position, and does not formally request for additional information. We will discuss disposition of this question in the requestedconference call.Peter S. Tam, Senior Project ManagerPlant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulatione-mail: pst@nrc.gov  Tel.: 301-415-1451 CC:Miranda, Samuel;  Nakoski, John;  Somers, ChristopherMail Envelope Properties(44B7B4A0.E11 : 12 : 35330)
: 4. Inadvertent opening of a pressurizer safety or relief valveFor each event, show that OTT will continue to provide adequate protection from departurefrom nucleate boiling following the requested change in RTD response time.This e-mail aims solely to prepare you and others for the requested conference call. Thise-mail does not convey a formal NRC staff position, and does not formally request for additional information. We will discuss disposition of this question in the requestedconference call.Peter S. Tam, Senior Project ManagerPlant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulatione-mail: pst@nrc.gov  Tel.: 301-415-1451 CC:Miranda, Samuel;  Nakoski, John;  Somers, ChristopherMail Envelope Properties(44B7B4A0.E11 : 12 : 35330)



Revision as of 14:57, 13 July 2019

D. C. Cook Unit 1: Draft Question Re Proposed RTD Bypass Amendment
ML061980478
Person / Time
Site: Cook American Electric Power icon.png
Issue date: 07/14/2006
From: Tam P
NRC/NRR/ADRO/DORL/LPLIII-1
To: Scarpello M, Waters J
Indiana Michigan Power Co
References
TAC MD2106
Download: ML061980478 (2)


Text

From: Peter TamTo:Scarpello, Michael; Waters, JoeDate: 07/14/2006 11:13:36 AM

Subject:

D. C. Cook Unit 1: Draft Question re. Propsoed RTD Bypass Amendment(TAC MD2106)Michael, Joe:

This is regarding your 5/31/06 application for amendment. We have developed the followingdraft question, and would like to discuss it with you in a conference call: The amendment request involves the removal of the resistance temperature detector (RTD)bypass manifolds. This will affect the RTD response time, which is used in the OTT tripfunction. The OTT trip initiates automatic protective actions to mitigate the consequences ofthe following events, and therefore would be affected by the change in RTD response time:1. Loss of electrical load/turbine trip2. Uncontrolled rod cluster control assembly (RCCA) bank withdrawal at power

3. Chemical Volume Control System (CVCS) malfunction that results in a decrease in the boron concentration in the reactor coolant
4. Inadvertent opening of a pressurizer safety or relief valveFor each event, show that OTT will continue to provide adequate protection from departurefrom nucleate boiling following the requested change in RTD response time.This e-mail aims solely to prepare you and others for the requested conference call. Thise-mail does not convey a formal NRC staff position, and does not formally request for additional information. We will discuss disposition of this question in the requestedconference call.Peter S. Tam, Senior Project ManagerPlant Licensing Branch III-1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulatione-mail: pst@nrc.gov Tel.: 301-415-1451 CC:Miranda, Samuel; Nakoski, John; Somers, ChristopherMail Envelope Properties(44B7B4A0.E11 : 12 : 35330)

Subject:

D. C. Cook Unit 1: Draft Question re. Propsoed RTD BypassAmendment (TAC MD2106)

Creation Date 07/14/2006 11:13:36 AMFrom: Peter TamCreated By:PST@nrc.govRecipientsActionDate & Timeaep.comTransferred07/14/2006 11:14:30

AM jrwaters (Joe Waters) mkscarpello (Michael Scarpello) nrc.gov TWGWPO01.HQGWDO01Delivered07/14/2006 11:13:43

AM JAN1 CC (John Nakoski)Opened07/14/2006 11:15:33

AM SXM1 CC (Samuel Miranda)Opened07/14/2006 1:37:26

PMnrc.gov TWGWPO02.HQGWDO01Delivered07/14/2006 11:13:37

AM CMS3 CC (Christopher Somers)Opened07/14/2006 11:13:47

AMPost Office DeliveredRouteaep.com TWGWPO01.HQGWDO0107/14/2006 11:13:43 AMnrc.gov TWGWPO02.HQGWDO0107/14/2006 11:13:37 AMnrc.govFilesSizeDate & Time MESSAGE268207/14/2006 11:13:36 AMOptions Auto Delete:

No Expiration Date:None Notify Recipients:Yes Priority:Standard ReplyRequested:

No Return Notification:None Concealed

Subject:

No Security:Standard To Be Delivered:Immediate Status Tracking:Delivered & Opened