ML071000062: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
 
Line 3: Line 3:
| issue date = 04/27/2007
| issue date = 04/27/2007
| title = Revision of Schedule for the Conduct of the Review of the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application
| title = Revision of Schedule for the Conduct of the Review of the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application
| author name = Diaz-Sanabria Y K
| author name = Diaz-Sanabria Y
| author affiliation = NRC/NRR/ADRO/DLR/RLRA
| author affiliation = NRC/NRR/ADRO/DLR/RLRA
| addressee name = McKinney B T
| addressee name = Mckinney B
| addressee affiliation = PPL Susquehanna, LLC
| addressee affiliation = PPL Susquehanna, LLC
| docket = 05000387, 05000388
| docket = 05000387, 05000388

Latest revision as of 02:21, 13 July 2019

Revision of Schedule for the Conduct of the Review of the Susquehanna Steam Electric Station, Units 1 and 2, License Renewal Application
ML071000062
Person / Time
Site: Susquehanna  Talen Energy icon.png
Issue date: 04/27/2007
From: Yoira Diaz-Sanabria
NRC/NRR/ADRO/DLR/RLRA
To: Mckinney B
Susquehanna
Diaz -Sanabria, Y, NRR/DLR/RLRA,415-1594
References
Download: ML071000062 (6)


Text

April 27, 2007Mr. Britt T. McKinneySr. Vice President and Chief Nuclear Officer PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THESUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATION

Dear Mr. McKinney:

Enclosed is a revised schedule for review of the Susquehanna Steam Electric Station,Units 1 and 2, license renewal application. This schedule has been revised to reflect the potential impacts that would need to be considered in the license renewal (LR) review as a result of an ongoing review of an extended power uprate application submitted by PPL Susquehanna, LLC, in October 11, 2006, as supplemented on October 25, November 21, and December 4, 2006. The U.S. Nuclear Regulatory Commission staff will update and establish the remaining milestones in the LR review schedule as we previously informed you in a letter dated August 2, 2006. This letter can be accessed in the Agency Documents Access and Management System, under (Accession No. ML062140549). If you have any questions on the revised schedule, please contact me by telephone at 301-415-1594 or via e-mail at YKS@nrc.gov

.Sincerely,/RA/Yoira K. Diaz Sanabria, Project ManagerLicense Renewal Branch A Division of License Renewal Office of Nuclear Reactor RegulationDocket Nos. 50-387 and 50-388

Enclosure:

Revised Schedulecc w/encl: See next page

ML071000062OFFICEPM:RLRA:DLRLA:DLRPM:REBB:DLRPM:REBB:DLRBC:REBB:DLRBC:RLRA:DLRNAMEYDiazSanabriaI. KingDStuyvenbergJDavisRFranovichLLundDATE04/27/0704/10/0704/16/0704/16/0704/16/0704/27/07 EnclosureSUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2LICENSE RENEWAL APPLICATIONREVISION OF SCHEDULEMilestoneScheduleActualReceive license renewal application (LRA)09/15/0609/13/06 Publish Federal Register Notice (FRN) - LRA receipt and availability09/25/0609/26/06Publish FRN - LRA acceptability, environmental scoping period, andopportunity for hearing10/30/0610/30/06Public Meeting - license renewal process and environmental scoping11/15/0611/15/06Audit - scoping and screening methodology12/11-15/0612/11-15/06 Environmental scoping periods ends01/02/0701/02/07 Audit - aging management programs (AMPs)07/30-08/03/07 Audit - environmental05/14-18/07 Audit - aging management reviews (AMRs)09/10-14/07 Audit (optional)TBD Issue environmental requests for additional information (RAIs)06/18/07 Issue safety RAIsTBD Receive responses for environmental RAIs07/31/07 Receive responses for safety RAIsTBDInspection - scoping, screening, and AMPs11/7-9/0711/26-30/07Inspection (optional)TBDIssue draft supplemental environmental impact statement (SEIS)TBD Publish FRN - availability and comment on draft SEISTBD Public Meeting - draft SEISTBD Issue safety evaluation report (SER) with open item(s)TBD End of comment period for the draft SEISTBDAdvisory Committee on Reactor Safeguards (ACRS) subcommitteemeeting on SER with open item(s)TBDReceive responses related to the SER with open item(s)TBDIssue Regional Administrator's letter TBD Issue final SEISTBD Issue SERTBD Publish FRN - availability of final SEISTBD ACRS full committee meeting on SERTBD Issue ACRS letterTBD Issue staff recommendation to NRR's DirectorTBD

NRR decision (license issued, if approved and no hearing is granted - 22 months)TBDCommission decision (if hearing is granted - 30 months)TBD Letter to B.McKinney from Y.Diaz-Sanabria, dated April 27, 2007

SUBJECT:

REVISION OF SCHEDULE FOR THE CONDUCT OF REVIEW OF THESUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, LICENSE RENEWAL APPLICATIONDISTRIBUTION:HARD COPY:DLR R/FE-MAIL:PUBLICRWeisman GGalletti SSmith (srs3)

SDuraiswamy RidsNrrDlr RidsNrrDlrRlra RidsNrrDlrRlrb RidsNrrDlrRlrc RidsNrrDlrReba RidsNrrDlrRebb

RidsNrrDci RidsNrrDra RidsNrrDe RidsNrrDeEemb RidsNrrDeEeeb RidsNrrDeEqvb

RidsNrrDss RidsOgcMailCenter RidsNrrAdes


YDiaz RGuzman BRogers Susquehanna Steam Electric Station, Units 1 and 2 cc:Robert A. SacconeVice President - Nuclear Operations PPL Susquehanna, LLC 769 Salem Blvd., NUCSB3 Berwick, PA 18603-0467Terry L. HarpsterGeneral Manager - Plant Support PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Rocco R. SgarroManager - Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Walter E. MorrisseySupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC 769 Salem Blvd., NUCSA4 Berwick, PA 18603-0467Michael H. CrowthersSupervising Engineer Nuclear Regulatory Affairs PPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Steven M. CookManager - Quality Assurance PPL Susquehanna, LLC 769 Salem Blvd., NUCSB2 Berwick, PA 18603-0467Luis A. RamosCommunity Relations Manager, Susquehanna PPL Susquehanna, LLC 634 Salem Blvd., SSO Berwick, PA 18603-0467Bryan A. Snapp, Esq.Associate General Counsel PPL Services Corporation Two North Ninth Street, GENTW3 Allentown, PA 18101-1179Supervisor - Document Control ServicesPPL Susquehanna, LLC Two North Ninth Street, GENPL4 Allentown, PA 18101-1179Richard W. OsborneAllegheny Electric Cooperative, Inc.

212 Locust Street P.O. Box 1266 Harrisburg, PA 17108-1266Director, Bureau of Radiation ProtectionPennsylvania Department of Environmental Protection Rachel Carson State Office Building P.O. Box 8469 Harrisburg, PA 17105-8469Senior Resident InspectorU.S. Nuclear Regulatory Commission P.O. Box 35, NUCSA4Berwick, PA 18603-0035Regional Administrator, Region 1U.S. Nuclear Regulatory Commission

475 Allendale Road King of Prussia, PA 19406Board of SupervisorsSalem Township P.O. Box 405 Berwick, PA 18603-0035 Susquehanna Steam Electric Station, Units 1 and 2 cc:-2-Dr. Judith JohnsrudNational Energy Committee Sierra Club 443 Orlando Avenue State College, PA 16803Mr. James RossNuclear Energy Institute 1776 I Street, NW, Suite 400 Washington, DC 20006-3708