ML080110611: Difference between revisions
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
StriderTol (talk | contribs) (Created page by program invented by StriderTol) |
||
Line 3: | Line 3: | ||
| issue date = 01/17/2008 | | issue date = 01/17/2008 | ||
| title = G20080024/LTR-08-0011/EDATS: SECY-2008-0020 - William Shack Ltr. Susquehanna, Units 1 & 2, Extended Power Uprate Application | | title = G20080024/LTR-08-0011/EDATS: SECY-2008-0020 - William Shack Ltr. Susquehanna, Units 1 & 2, Extended Power Uprate Application | ||
| author name = Reyes L | | author name = Reyes L | ||
| author affiliation = NRC/EDO | | author affiliation = NRC/EDO | ||
| addressee name = Shack W | | addressee name = Shack W | ||
| addressee affiliation = NRC/ACRS | | addressee affiliation = NRC/ACRS | ||
| docket = 05000387, 05000388 | | docket = 05000387, 05000388 | ||
| license number = NPF-014, NPF-022 | | license number = NPF-014, NPF-022 | ||
| contact person = Guzman R | | contact person = Guzman R, NRR/DLPM 415-1030 | ||
| case reference number = G20080024, LTR-08-0011, SECY-2008-0020, TAC MD7729, TAC MD7730 | | case reference number = G20080024, LTR-08-0011, SECY-2008-0020, TAC MD7729, TAC MD7730 | ||
| package number = ML080110459 | | package number = ML080110459 | ||
Line 28: | Line 28: | ||
==Dear Dr. Shack:== | ==Dear Dr. Shack:== | ||
On October 9 and 10, and November 14, 2007, the U.S. Nuclear Regulatory Commission (NRC) staff presented its review of the Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2), extended power uprate (EPU) application to the Advisory Committee on Reactor Safeguards (ACRS) subcommittee on power uprates. During the 547 th and 548 th meetings of the ACRS, on November 1 and December 7, 2007, respectively, the staff discussed the EPU with the ACRS full committee. By letter dated December 20, 2007, the ACRS forwarded its conclusions and recommendations on the staff's review of the SSES 1 and 2 EPU application to Chairman Klein. In that letter, the ACRS provided the following conclusions and recommendations: | On October 9 and 10, and November 14, 2007, the U.S. Nuclear Regulatory Commission (NRC) staff presented its review of the Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2), extended power uprate (EPU) application to the Advisory Committee on Reactor Safeguards (ACRS) subcommittee on power uprates. During the 547 th and 548 th meetings of the ACRS, on November 1 and December 7, 2007, respectively, the staff discussed the EPU with the ACRS full committee. By letter dated December 20, 2007, the ACRS forwarded its conclusions and recommendations on the staff's review of the SSES 1 and 2 EPU application to Chairman Klein. In that letter, the ACRS provided the following conclusions and recommendations: | ||
: 1. The PPL application for the SSES EPU should be approved subject to the conditions imposed in the Safety Evaluation (SE) and the modification in recommendation 2. | : 1. The PPL application for the SSES EPU should be approved subject to the conditions imposed in the Safety Evaluation (SE) and the modification in recommendation 2. | ||
: 2. An appropriate margin should be added to the operating limit minimum critical power ratio (OLMCPR) as an interim measure to account for uncertainties in the void fraction correlation and the lack of data for its validation at void fraction above 90 percent. This interim measure should be reviewed when PPL submits more detailed analyses that account for the effect of uncertainties in the void fraction on the OLMCPR. | : 2. An appropriate margin should be added to the operating limit minimum critical power ratio (OLMCPR) as an interim measure to account for uncertainties in the void fraction correlation and the lack of data for its validation at void fraction above 90 percent. This interim measure should be reviewed when PPL submits more detailed analyses that account for the effect of uncertainties in the void fraction on the OLMCPR. | ||
: 3. We concur with the staff that the load rejection and main steam isolation valve closure transient tests should not be required. The plant transient testing program adequately addresses the performance of the modified systems. 4. We concur with the staff that the monitoring that will be performed during power ascension to the uprate conditions provides adequate assurance that if vibration modes are induced in the steam dryer, they will be identified. | : 3. We concur with the staff that the load rejection and main steam isolation valve closure transient tests should not be required. The plant transient testing program adequately addresses the performance of the modified systems. 4. We concur with the staff that the monitoring that will be performed during power ascension to the uprate conditions provides adequate assurance that if vibration modes are induced in the steam dryer, they will be identified. | ||
: 5. The proposed methodology for reducing the Oscillation Power Range Monitor scram setpoint values to account for errors caused by bypass voiding is acceptable. | : 5. The proposed methodology for reducing the Oscillation Power Range Monitor scram setpoint values to account for errors caused by bypass voiding is acceptable. | ||
: 6. The staff should develop the capability and perform a thorough review and assessment of the risk of pellet-cladding interaction (PCI) fuel failures with conventional fuel cladding, during anticipated operational occurrences (AOOs). | : 6. The staff should develop the capability and perform a thorough review and assessment of the risk of pellet-cladding interaction (PCI) fuel failures with conventional fuel cladding, during anticipated operational occurrences (AOOs). | ||
: 7. Review Standard (RS)-001, "Review Standard for Extended Power Uprates," provides a structured process for the review of EPU applications. The guidance document should be improved to include cross-referencing of related section between the power uprate safety analysis report (PUSAR) and the staff's SEs. | : 7. Review Standard (RS)-001, "Review Standard for Extended Power Uprates," provides a structured process for the review of EPU applications. The guidance document should be improved to include cross-referencing of related section between the power uprate safety analysis report (PUSAR) and the staff's SEs. | ||
Revision as of 16:10, 12 July 2019
ML080110611 | |
Person / Time | |
---|---|
Site: | Susquehanna |
Issue date: | 01/17/2008 |
From: | Reyes L NRC/EDO |
To: | Shack W Advisory Committee on Reactor Safeguards |
Guzman R, NRR/DLPM 415-1030 | |
Shared Package | |
ML080110459 | List: |
References | |
G20080024, LTR-08-0011, SECY-2008-0020, TAC MD7729, TAC MD7730 | |
Download: ML080110611 (3) | |
Text
January 17, 2008
Dr. William J. Shack, Chairman Advisory Committee on Reactor Safeguards U.S. Nuclear Regulatory Commission Washington, DC 20555-0001
SUBJECT:
SUSQUEHANNA STEAM ELECTRIC STATION, UNITS 1 AND 2, EXTENDED POWER UPRATE
Dear Dr. Shack:
On October 9 and 10, and November 14, 2007, the U.S. Nuclear Regulatory Commission (NRC) staff presented its review of the Susquehanna Steam Electric Station, Units 1 and 2 (SSES 1 and 2), extended power uprate (EPU) application to the Advisory Committee on Reactor Safeguards (ACRS) subcommittee on power uprates. During the 547 th and 548 th meetings of the ACRS, on November 1 and December 7, 2007, respectively, the staff discussed the EPU with the ACRS full committee. By letter dated December 20, 2007, the ACRS forwarded its conclusions and recommendations on the staff's review of the SSES 1 and 2 EPU application to Chairman Klein. In that letter, the ACRS provided the following conclusions and recommendations:
- 1. The PPL application for the SSES EPU should be approved subject to the conditions imposed in the Safety Evaluation (SE) and the modification in recommendation 2.
- 2. An appropriate margin should be added to the operating limit minimum critical power ratio (OLMCPR) as an interim measure to account for uncertainties in the void fraction correlation and the lack of data for its validation at void fraction above 90 percent. This interim measure should be reviewed when PPL submits more detailed analyses that account for the effect of uncertainties in the void fraction on the OLMCPR.
- 3. We concur with the staff that the load rejection and main steam isolation valve closure transient tests should not be required. The plant transient testing program adequately addresses the performance of the modified systems. 4. We concur with the staff that the monitoring that will be performed during power ascension to the uprate conditions provides adequate assurance that if vibration modes are induced in the steam dryer, they will be identified.
- 5. The proposed methodology for reducing the Oscillation Power Range Monitor scram setpoint values to account for errors caused by bypass voiding is acceptable.
- 6. The staff should develop the capability and perform a thorough review and assessment of the risk of pellet-cladding interaction (PCI) fuel failures with conventional fuel cladding, during anticipated operational occurrences (AOOs).
- 7. Review Standard (RS)-001, "Review Standard for Extended Power Uprates," provides a structured process for the review of EPU applications. The guidance document should be improved to include cross-referencing of related section between the power uprate safety analysis report (PUSAR) and the staff's SEs.
In addition to the recommendations and conclusions, several ACRS members provided additional comments expressing their concern that the licensee's plan to operate the units with conventional (non-barrier) fuel has increased the risk of pellet-cladding-interaction fuel failures during AOOs at EPU conditions.
In regards to recommendation 2, the NRC staff performed a detailed review of the application of AREVA methods and models to SSES at EPU conditions. In its review, the staff considered several technical points that were unique to the SSES EPU application. First, the fuel vendor (AREVA) provided full scale void fraction test data covering the range of pressure, flow rates, and void fractions up to the point of dry-out for the ATRIUM-10 fuel design. Second, the staff approval of the AREVA neutronic methods is limited to those transients which show margin to the safety limit minimum critical power ratio, and are therefore, effectively bounded by the critical heat flux test results. Third, AREVA performed a detailed sensitivity analysis demonstrating a negligible impact on the OLMCPR for a substantial void fraction bias. The staff agrees that void fraction data above 90% is lacking. However, the staff concludes that for the range of heat flux approved in the application, that any additional uncertainty for nodal void fractions at yet higher values, contributes negligibly to the analyses results such as the dual recirculation pump trip. The staff reviewed the neutronic feedback effects on potential void fraction biases for pressurization events and found that, when considered in an integral sense, the effects resulted in a power/void feedback that is substantially self compensating when determining the operating limit for SSES 1 and 2. The SSES 1 and 2 analysis is fully consistent with the staff's understanding of the power/void feedback phenomenon. Based on these points, the staff has found that an additional penalty to the OLMCPR is not necessary to ensure acceptable safety. The staff appreciates the committee's concerns and helpful insight provided during the review and will avail themselves to the committee, if requested, to discuss this matter at length.
In response to recommendation 6, the NRC staff will investigate current computational capabilities to model the complex phenomena associated with non-uniform fuel pellet expansion and stress-corrosion cracking (SCC). As necessary, the staff will develop guidance related to an application methodology and regulatory approach for implementing a PCI/SCC fuel failure criteria.
In regards to recommendation 7, the NRC staff continues to assess further means for improving the efficiency of the staff's review of EPU applications and to enhance consistency, quality, and completeness of EPU reviews. To that end, the staff continues to encourage both pressurized-water reactor and boiling-water reactor EPU applicants to use the RS-001 numbering scheme to identify the technical review areas in its applications. If an applicant desires to use a different numbering scheme, then the staff encourages EPU applicants to provide a table that cross-references the RS-001 matrix to the licensee's numbering scheme, as PPL Susquehanna did in Attachment 12 to its initial EPU application dated October 11, 2006 (the RS-001 matrix was annotated with references to the licensee's PUSAR). The staff will revise its internal guidance to ensure that future transmittals of draft SEs to ACRS include a table that provides cross-references between the staff's SE and the applicable sections of the licensee's PUSAR and supplemental responses.
The NRC staff appreciates the Committee's insights concerning the SSES 1 and 2 EPU amendment review.
Sincerely, /RA/ Luis A. Reyes Executive Director for Operations cc: Chairman Klein Commissioner Jaczko Commissioner Lyons SECY PPL Susquehanna did in Attachment 12 to its initial EPU application dated October 11, 2006 (the RS-001 matrix was annotated with references to the licensee's PUSAR). The staff will revise its internal guidance to ensure that future transmittals of draft SEs to ACRS include a table that provides cross-references between the staff's SE and the applicable sections of the licensee's PUSAR and supplemental responses.
The NRC staff appreciates the Committee's insights concerning the SSES 1 and 2 EPU amendment review.
Sincerely, /RA/
Luis A. Reyes Executive Director for Operations
cc: Chairman Klein Commissioner Jaczko Commissioner Lyons SECY
DISTRIBUTION: G20080024/LTR-08-0011/EDATS: SECY-2008-0020 PUBLIC RidsNrrWpcMail LPLI-1 RF RidsNrrDorl RidsEdoMailCenter RidsNrrDorlLpli-1 RidsNrrOd RidsNrrDss RidsNrrAdro RidsNrrDssSrxb RidsNrrAdes RidsNrrDssSnpb RidsOgcRp RidsNrrDpr RidsOpaMailCenter RidsNrrDprPgcb RidsRgn1MailCenter RidsNrrPMRGuzman RidsOgcMailCenter RidsNrrLASLittle RidsOcaMailCenter PYarsky RidsSecyMailCenter PClifford RidsAcnwMailCenter
Package: ML080110459 Incoming: ML080100452 Response: ML080110611 *Concurred via email OFFICE LPLI-I-1/PM LPLI-1/LA TECH ED* LPLI-1/BC SRXB/BC NAME RGuzman SLittle HChang MKowal GCranston DATE 1/9/08 1/7/08 1/4/08 1/7/08 1/7/08 OFFICE PGCB/BC DSS/DD DORL/OD NRR/OD EDO NAME MMurphy WRuland CHaney JDyer (JGrobe for) LReyes DATE 1/9/08 1/8/08 1/9/08 1/15/08 1/17/08 OFFICIAL RECORD COPY