ML18262A322: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 5: Line 5:
| author name = Pitesa B
| author name = Pitesa B
| author affiliation = NEI Nuclear Systems Ltd
| author affiliation = NEI Nuclear Systems Ltd
| addressee name = Nieh H K
| addressee name = Nieh H
| addressee affiliation = NRC/NRR
| addressee affiliation = NRC/NRR
| docket = PROJ0689
| docket = PROJ0689

Revision as of 22:12, 12 June 2019

Reactor Oversight Process Enhancement Letter from Nuclear Energy Institute Dated 09/19/2018
ML18262A322
Person / Time
Site: Nuclear Energy Institute
Issue date: 09/19/2018
From: Pitesa B
NEI Nuclear Systems Ltd
To: Ho Nieh
Office of Nuclear Reactor Regulation
Gibbs R, 415-8578
References
Download: ML18262A322 (19)


Text

Recommendations for ROP Enhancement Enclosure 1 Page 1 of 11 Revised 201809 1 7 Introduction The recommendations provided here are organized in four broad aspects of the Reactor Oversight Process: (1) the Baseline Inspection Program; (2) the Action Matrix; (3) the Significance Determination Process; and (4) response to inspection issues.

In each of these four areas, we present a summary and overall rationale for the recommendations.

Following the introduction, we present a list of specific recommendations with notes indicating their tie to NRC's transformation report and NEI's

. Area 1 - The Baseline Inspection Program Since inception, the amount of baseline direct inspection hours has increased by approximately 30 percent.1 Although some increase might have been expected if operating experience revealed major gaps in the baseline inspection program, no major gaps have been identified.

Moreover, the industry's high level of safety performance has not been factored into the baseline inspection program hours.

Experience with the recent Engineering Inspection Procedure reform effort, which NRC estimates will reduce inspection effort in the engineering area alone by 16 percent, gives industry confidence that overall baseline inspection program hours can be pared by a nomin al 20 percent. The stakeholder engagement process followed by the NRC's Engineering Inspection Procedure Working Group was well received and produced efficient and effective recommendations.

Such an approach should be a model for future interactions on significant changes to the ROP.

This effort produced a consolidation of inspection effort and reduction of redundancy and overlap.

Additionally, a more efficient and agile inspection cycle resulted

, as well as a strong recommendation to give inspection credit for self

-assessments.

The engineering procedure effort produced a meaningful reduction in direct inspection hours over a four-year cycle while maintaining the agility to respond to operating experience and ensure comprehensive inspections of engineering performance.

Item Area 1 - Recommendations to Enhance the Baseline Inspection Program Map to NRC Transformation Report 2 Map to NEI Transformation Report 3 1A Revise RP Inspections:

Review radiation protection inspections to apply lessons learned from the Engineering Inspections Working Group to streamline them (following the stakeholder engagement process employed with engineering inspections); include credit for self

-assessments.

III (a) (2) 3,4 1B Revise EP Inspections:

Review emergency preparedness inspections to apply lessons learned from the Engineering Inspections Working Group to streamline them (following the stakeholder engagement process employed with engineering inspections); include credit for self-assessments III (a) (2) 3,4

1 NEI research beginning with baseline hours presented in SECY 007 and data provided in "Operating Reactors Business Line Fee Estimates,"

available at ADAMS ML17271A262 (NEI internal reference J. Slider email September 12, 2018).

2 SECY-18-0060, "Achieving Modern Ris k-Informed Regulation

," ML18119A186, May 23, 2018.

3 "A Framework for Regulatory Transformation

," transmitted to NRC by Pamela Cowan (NEI), March 16, 2018.

Recommendations for ROP Enhancement Enclosure 1 Page 2 of 11 Revised 201809 1 7 Item Area 1 - Recommendations to Enhance the Baseline Inspection Program Map to NRC Transformation Report 2 Map to NEI Transformation Report 3 1C Revise Security Inspections:

Review security inspections to apply lessons learned from the Engineering Inspections Working Group to streamline them (following the stakeholder engagement process employed with engineering inspections); include credit for self-assessments III (a) (2) 3,4 1D Reduce Baseline Hours for Higher Performers

Reduce the baseline inspection hour levels based on sustained plant performance.

Higher performing plants should merit at least 25 percent fewer baseline inspection hours.

This can be achieved by reducing the number of samples and subsequent direct

-inspection hours in the existing inspections.

These inspector touch points ensure levels of performance are sustained.

Higher performing plants could be defined as having no greater than green inputs to the Action Matrix in the past 12 months.

III (a) Apply concepts of more effective use of resources and use of OE 2 1E Remove PI&R Inspection from Baseline Program: Change Inspection Procedure 71152, Problem Identification and Resolution, 4 to an inspector follow

-up or reactive procedure (described below) and remove it from the baseline inspection program.

Resident Inspectors focus daily on the Corrective Action Program (CAP) by reviewing all new condition reports (CRs).

Moreover, in most inspections, inspectors focus first on CAP entries. Thus, each inspection and inspector assesses the ability of the plant to find and fix its problems. Focusing a separate inspection team solely on PI&R is redundant to the assessment of the PI&R function that occurs in almost every inspection.

In addition, the cross

-cutting issues element of the ROP captures trends in PI&R performance in every inspection.

III (a) Apply concepts of more effective use of resources and use of OE 2,3 1F Refrain from Expanding Baseline Inspection Effort in Future: Establish and enforce policy requiring no net increase in baseline inspection hours when considering new areas of inspection (including current consideration of inspecting III (a) Apply concepts of more focused use of resources 2,3

4 Inspection Procedure 71152, "Problem Identification and Resolution

," Issue Date 02/26/15, ADAMS ML14316A042.

Recommendations for ROP Enhancement Enclosure 1 Page 3 of 11 Revised 201809 1 7 Item Area 1 - Recommendations to Enhance the Baseline Inspection Program Map to NRC Transformation Report 2 Map to NEI Transformation Report 3 Beyond Design Basis features

). When NRC wishes to add new subjects or scope to the Baseline Inspection Program, it should identify subjects and scope that will be removed from the BIP to prevent increasing the BIP hours.

The treatment proposed for FLEX inspections is an example of weaving a new area of inspection into the existing baseline program while striving to avoid increasing direct inspection hours.

1G Revise Use of Mitigating Systems Performance Index: Reevaluate the NRC's treatment of the MSPI. Consider eliminating overlap between MSPI and inspections of safety systems monitored by MSPI or simplifying or replacing MSPI with an indicator based on similar data collected for related purposes (e.g., for Maintenance Rule monitoring

). To improve MSPI margin, plant changes have been made that significantly improve safety as well as MSPI margin.

With the increased MSPI margin, the indicator offers limited remaining value as it is difficult to exceed the White threshold.

The Maintenance Rule monitors the health of the subject systems.

Additionally, the new regime for engineering inspections provides adequate assurance of safety system performance in addition to the resident inspector s' monitoring of plant status and CAP.

III (a) Apply concepts of more effective use of OE 4 1H Eliminate Materials Inspections of ISFSI s: Inspection Procedures 60855 5 & 60855.1 6 should be eliminated as redundant to numerous other inspection activities.

The resources identified for the various inspection activities do not comport with the know n safety significance associated with dry fuel storage and ISFSI operation.

Activities associated with loading canisters are understood to fall within oversight by the resident staff.

5 Inspection Procedure 60855, "Operation of an Independent Spent Fuel Storage Installation,"

Issued Date 01/16/08, ADAMS ML073100489.

6 Inspection Procedure 60855.1, "Operation of an Independent Spent Fuel Storage Installation at Operating Plants ," Issued Date 09/05/06 , ADAMS ML062440146.

Recommendations for ROP Enhancement Enclosure 1 Page 4 of 11 Revised 201809 1 7 Area 2 - Action Matrix Enhancements The impacts of column changes in the Action Matrix 7 have increased significantly over the life of the ROP. As industry performance has improved, the external (media and financial market) response to every column change has become more pronounced. In addition, the effort required to resolve low-to-moderate safety or security issues has increased since the beginning of the ROP

. Today, the resources expended by both the NRC and licensees are no longer commensurate with the risk significance of these issues. This rise in expectations to address and resolve these issues is inconsistent with the goals of the ROP. The increase also detracts from the resources and management attention available to focus on matters of greater safety significance and promptly returning the plant to its baseline level of risk.

The Action Matrix creates a means by which low-to-moderate safety issues may be aggregated and trigger a more significant column chang

e. The original design of the ROP considered the appearance of low risk issues as expected, random variations in plant performance

. It was also assumed that occasionally, plants would realize a low but slightly elevated safety significant finding, resolve it, and return to baseline risk operation.

In practice, it is possible for issues to aggregate, even if one or more of the issues have long since been resolved and the plant returned to its baseline risk values.

This causes an intense effort to establish a n actual significance that is more precise (usually lower) through more detailed calculations, tests, and judgment by l icensees. Additionally, eighteen years of ROP experience indicate s aggregation of inputs is not necessarily a meaningful predictor of future safety performance and fails to justify escalation through the Action Matrix.

Further, the immediacy of NRC public communication s on low-risk issues gives the lay public a misleading impression of the importance of issues of low safety significance.

Consistent with the Petition for Rulemaking submitted by the industry for elimination of the immediate reports of non

-emergency events, 8 actions below consider the need for non-urgent information.

As changes are made to the regulatory treatment of White inputs, conforming changes throughout the ROP should be explored and implemented.

Item Area 2 - Recommendations to Enhance the Action Matrix Map to NRC Transformation Report 2 Map to NEI Transformation Report 2A Revise Public Communications on White Findings: NRC should discontinue the practice of issuing a press release for White findings. White findings are documented in Inspection Reports and assessment letters and should be treated as normal variations in performance as described in the original ROP construct.

NA 3 2B Revise the Structure of the Action Matrix:

Below are several actions to clarify the signifi

-cance of plant issues

, the level of plant perfor

-mance, and the plant's ability to maintain plant risk as close to baseline as reasonably achievable. Below Below

7 The ROP Action Matrix is described in NRC Inspection Manual Chapter 0305.

8 Bill Pitesa (NEI) letter to Annette Vietti

-Cook (NRC), "Petition to Amend 10 CFR 50.72, Immediate Notification Requirements for Op erating Nuclear Power Reactors,"

August 2, 2018, accepted as NRC PRM 116, available at www.regulations.gov on Docket NRC

-2018-0201.

Recommendations for ROP Enhancement Enclosure 1 Page 5 of 11 Revised 201809 1 7 Item Area 2 - Recommendations to Enhance the Action Matrix Map to NRC Transformation Report 2 Map to NEI Transformation Report 2B.1 Combine Columns 1 and 2:

Combine Action Matrix Columns 1 and 2 into one column called "Nominal Plant Operation."

There would be a change of columns only if findings with safety significance of moderate (Yellow) or high (Red) were identified.

This would eliminate the aggregation of Whites and allow the plant's CAP to work as designed in support of nominal plant operation.

Plants today nominally operate with baseline CDFs between 10-5 and 10-6/yr. Also, this would establish a column change as a more significant event the public would better understand.

Encl 6 (2) 3 2B.2 Follow-Up via Resident Inspectors

Establish the follow-up and closure for White findings through the resident inspector inspecting the causal analysis. Initially this was approximately 16 hours1.851852e-4 days <br />0.00444 hours <br />2.645503e-5 weeks <br />6.088e-6 months <br /> as originally anticipated in the 2002 version of the IP 95001 procedure

. Ensure the attributes of the 95001 procedure for prevention of recurrence, extent of cause/condition are assessed, possibly through a PI&R

-type sampling process. III (a) & Encl 6 (20) 3,4 2B.3 Redirect IP 95001:

Change the IP 95001 from a stand-alone "supplemental" procedure for Whites to become a follow

-up to Yellow or Red findings as an initial inspection, with triggers for expanded inspections using IP 95002 or IP 95003, if necessary.

This is consistent with a graded approach where performance dictates escalation, not blindly automatic escalation by process. Encl 6 (2)

Threshold of very low safety significance issues 2,3 Recommendations for ROP Enhancement Enclosure 1 Page 6 of 11 Revised 201809 1 7 Item Area 2 - Recommendations to Enhance the Action Matrix Map to NRC Transformation Report 2 Map to NEI Transformation Report 2B.4 Revise IP 71152 to be Reactive:

Change IP 71152, Problem Identification and Resolution, to an inspector follow

-up or reactive procedure and remove it from the baseline inspection program. In just about every direct inspection, the focus is first on the corrective action program.

Each inspector makes assessments of the ability of the plant to find and fix its problems; hence to focus a team on solely PI&R is redundant to almost every inspection. The cross-cutting program monitors for trends in PI&R shortfalls.

III (a) resources 3 2B.5 Promptly Close White Findings:

Close White findings upon successful completion of the resident inspector follow

-up of the causal analysis for individual White findings.

Make corresponding and consistent policy changes for Columns 3 and 4 when dealing with individual and isolated findings

. This assures that escalated inspection attention is maintained only while ongoing plant risk is above nominal.

Once the risk is returned to baseline, the inspection to ensure sustainability of corrective actions is provided by resident inspector monitorin

g. Encl 6 (2)

Encourage prompt licensee corrective actions 3 2B.6 Redefine Finding Labels

Establish labels of Green as "very low safety significance,"

White as "low safety significance,"

Yellow as "moderate safety significance,"

and Red as "high safety significance."

This clarifies the communication aspect of the color and eliminates color definition overlap that is confusing and sends a message that there is only a broad understanding of the significance rather than a true understanding of a more precise characterization of significance

. Encl 6 (2) 2,3 Recommendations for ROP Enhancement Enclosure 1 Page 7 of 11 Revised 201809 1 7 Area 3 - Significance Determination Process Over the life of the ROP, probabilistic risk assessments (PRAs) have become more widely used as an adjunct to traditional deterministic safety analyses.

PRAs have proven very valuable as systematic tools for identifying residual weaknesses in plant design and operations, and in providing perspective on the relative importance of challenges to plant safety.

As PRAs have grown more sophisticated and increased in scope to include external hazards, estimates of additional risk contributors have been included while the thresholds for ROP decision

-making have remained constant

. Since the ROP began, plant design changes and operational improvements have contributed to increasing margin. In light of our improved understanding of margin and insights from more sophisticated PRA modeling, the Electric Power Research Institute (EPRI) 9 concluded that "-only in the most extreme cases could uncertainties play a significant enough role

- at least with regard to cases in which the CDF approaches (or even exceeds) the subsidiary objective

." In other words, NRC and industry are spending vast resources to align on an estimate of risk used in the significance determination process when safety margins far exceed uncertainties in the quantitative results. It is important to recognize in the SDP that PRA is a decision

-support tool, not the decision

-making tool

. Additionally, the use of monitored plant performanc e data should be used to inform the SDP as gates to higher issue significance assements. The recommendations below would address this.

Item Area 3 - Recommendations to Enhance the Significance Determination Process Map to NRC Transformation Report Map to NEI Transformation Report 3A Revise EP SDP:

Revise the EP SDP to consider the site's performance in the Cornerstones of Initiating Events, Mitigating Systems, and Barrier Integrity.

If performance in all three Cornerstones is clear of open White inputs, then defense-in-depth (DID) is robust and the safety significance of the EP performance deficiency is less than would otherwise be the case. The EP SDP should be constructed to consider licensee performance in the ROP cornerstones associated with other elements of reactor safety Defense-in-Depth (DID). This approach would risk

-inform EP SDP outcomes with contemporaneous, site

-specific information relevant to the maintenance of other reactor safety DID barriers for protection of public health and safety.

NA 1,2,3

9 "Insights On Risk Margins At Nuclear Power Plants

A Technical Evaluation of Margins in Relation to Quantitative Health Objectives and Subsidiary Risk Goals in the United States

," May 2018 EPRI Whitepaper from Risk and Safety Management.

Recommendations for ROP Enhancement Enclosure 1 Page 8 of 11 Revised 201809 1 7 Item Area 3 - Recommendations to Enhance the Significance Determination Process Map to NRC Transformation Report Map to NEI Transformation Report 3A.1 Expand 3A Approach to All Deterministic SDPs The philosophy setting the policy for the EP SDP above should be applied to all determinist ic SDPs as much as practical.

NA 1,2,3 3B Combine BDB into One SDP:

For Beyond Design Basis (BDB) SDP, combine all IMC 0609 appendices currently used 10 into one SDP for BDB events.

III (a) 4 3C Stop Appendix M Revision:

Stop work on IMC 0609, Appendix M and leave as-is.11 , 12 III(a) 4 3D Standardize PRA Inputs to SDP:

Develop a consensus methodology for PRA inputs that will align the NRC and industry on uncertainties in key variables when beginning a PRA analysis of a performance deficiency.

These key variables include, among others, Human Reliability, Common Cause, and Exposure Time.

Presently, PRA results differ from the NRC's SPAR models largely due to the sensitivity of these inputs and incorporation of plant changes. The NRC RASP Handbook provides very conservative initial assumptions which drive the significance higher in many cases.

This causes consternation and application of intense resources, both by the NRC and industry, only to eventually come out in the end as very low safety significance.

Since 2010, less than nine percent of findings actually escalate d above very low significance.

III (a) Use of new tools and technology 1,4 3E Develop Procedure to Align on PRA Inputs Early: While the consensus methodology is being developed, the NRC should institute a procedural requirement to fill out a worksheet with the three key variables and obtain alignment with the licensee on other major inputs prior to running models either in SPAR or the licensee's PRA.

III (a), Rec 2 Use of new organizational tools 1

10 Notably IMC

-0609, Appendix L and Appendix O.

11 Christopher Earls (NEI) letter to Christopher Miller (NRC), "Significance Determination Process Revisions,"

October 12, 2017, ADAMS ML17338A031.

12 NRC released another draft of a proposed revision of IMC 0609, Appendix M, to ADAMS on September 14, 2018, just in time for a public ROP meeting scheduled for September 20, 2018.

Recommendations for ROP Enhancement Enclosure 1 Page 9 of 11 Revised 201809 1 7 Item Area 3 - Recommendations to Enhance the Significance Determination Process Map to NRC Transformation Report Map to NEI Transformation Report Experience shows that when these variables are commensurate input into either the SPAR or site-specific PRA, the outcomes are nominally equivalent. 3F Develop NRC Interface for Licensee PRAs: Industry and NRC should jointly develop a portal for NRC access to the licensee's site-specific PRA models for the purpose of supporting SDP

s. This interface would enable NRC to maintain independence of thought, assumptions, and inputs, while allowing PRA practitioners to see results from the licensee models. The portal would allow NRC to exercise the licensee's PRA application without requiring NRC to obtain the training or licenses necessary for detailed manipulation of models in the licensee's chosen PRA software.

III (a) 4 3G Eliminate Use of SPAR in SDP:

Once the portal is implemented and proven satisfactory, NRC should eliminate the use of the SPAR model in SDPs. III (a) More efficient use of resources 4 Recommendations for ROP Enhancement Enclosure 1 Page 10 of 11 Revised 201809 1 7 Area 4 - Response to Inspection Issues Since inception of the ROP, the industry has engaged the NRC through the ROP Task Force and Regional Utility Groups (RUGs)

, and in recent years, the Regulatory Issues Working Group

, on inspection issue resolution.

Many enhancements over the years have been made by both the NRC and the industry.

We appreciate the recent backfit training and are encouraged by the trajectory of this issue to hold the approved licensing basis as the foundation of decades of safe operation.

Considering the desire to focus resources on the more safety significant issues, enhancements to the openness and transparency as well as the reliability of the processes used for inspection issue response can be made.

Item Area 4 - Recommendations to Enhance Response to Inspection Issues Map to NRC Transformation Report Map to NEI Transformation Report 4A Establish Policy to Respect Licensing Basis: Establish an NRC policy where the approved licensing basis of a plant is to be respected as complete and adequate.

Inspector questions on the approved licensing basis arising from ambiguity in wording, less than desired detail, or absence of specific information should not be judged to be proof the licensing basis is inadequate unless a clear and compelling case can be made that the apparent gap must be closed to assure adequate protection.

NA 3,4 4B Establish Means of Resolving Very Low-Risk Licensing Basis Concerns: NRC should establish a process for resolving very low-risk licensing basis concerns. Ideally, the process should be developed through a collaborative effort between an NRC Working Group and corresponding NEI task force.

This effort should work with concepts introduced in SECY 0060 relative to changes in the 10CFR 50.59 process. The process would be used for adjudication of 1) licensing basis challenges and 2) adding clarity to the licensing basis to exclude challenges to the licensing basis over interpretations of the licensing basis by inspectors.

In this process, there should be an option for the licensee to perform a licensing basis change or clarification, rather than invest extensive resources in the contesting process, backfit process, or other regulatory issue resolution method.

III (b) Encl 6 (2) 3 Recommendations for ROP Enhancement Enclosure 1 Page 11 of 11 Revised 201809 1 7 Item Area 4 - Recommendations to Enhance Response to Inspection Issues Map to NRC Transformation Report Map to NEI Transformation Report 4C Open Up Communications about Inspection Results: The NRC should maintain open communications with the licensee through all stages of the inspection process, including presentations to the Significance and Enforcement Review Panel (SERP) process

. To this end, the NRC should discontinue use of the "pre-decisional" label to justify not communicating with the licensee during the vetting process for violations and findings. This "blackout" is not conducive to complete information exchange in the decision making processes and should be discontinued.

NA NA 4D Standardize Issue Escalation Practices:

Industry will develop a best practices document which formalizes the escalation of issues resulting from disagreements with inspection results and conclusions.

Many sites deal with disagreements on a case

-by-case basis. A few licensees have a formal escalation and communication process that could benefit the industry and give the NRC some consistent and reliable expectation s of licensee communications.

Industry will work with NRC in the development of this guidance document to ensure mutual understanding and shared expectations.

III (a) Reduced burden on licensee NA