Business Line Product Line Activity Low Estimate of Level of Effort in Staff Hours*
High Estimate of Level of Effort in Staff Hours*
Average Estimate of Level of Effort in Staff Hours* Examples Operating Reactors Licensing Amendments - simple 5
2,500 Operating Licensing NOEDs 7
40 15 Operating Reactors Licensing Exemptions 15 350 110 Operating Reactors Licensing NFPA-805 520 1,940 850 Operating Reactors Licensing License Transfers 75 370 170 Operating Reactors Licensing Orders 20 75 35 Operating Reactors Licensing Relief Requests 5
400 Operating Reactors Licensing Power Uprates -
Measurement Uncertainty Recapture 225 1,000 Operating Reactors Licensing Power Uprates - Stretch Uprate 600 2,500 Operating Reactors Licensing Power Uprates - EPU 4,000 7,500 Operating Reactors Licensing Research and Test Reactors/License Renewals NA NA 2,700 Focused review, e.g. DOW and USGS Operating Reactors Licensing Research and Test Reactors - Simple Amendments 18 200 109 Facility: Penn State (05-005);1,100kw PWR level; LA
Title:
Penn State Amendment Exigent Request; TAC: ME9067 Operating Reactors Business Line Fee Estimates Variation in the subjects of amendments, providing an average is not useful.
Operating Reactors Licensing Research and Test Reactors - Regular Amendments 201 500 350 Facility: MURR (50-186);10,000kw PWR level; LA
Title:
U. OF MO. -
MURR Request to Amend Tech.
Specs to Produce Medical I-131; TAC: MF6514 Operating Reactors Licensing Research and Test Reactors - Complex Amendments 501 1,170 743 Facility: Oregon (50-243);1,100kw PWR level; LA
Title:
OREGON ST, TRIGA MK II - fueled experiment amendment; TAC: ME8443 Operating Reactors Licensing Moly 99 Construction Permit Review NA NA 22,000 SHINE Application Operating Reactors Licensing Support Topical Reports-simple 250 700 600 Amendment to GESTAR Operating Reactors Licensing Support Topical Reports - med complex 500 2,000 1,350 Westinghouse. WCAP-17769, "Reference Fuel Design SVEA-96 Optima 3" Operating Reactors Licensing Support Topical Reports - high complex 2,000 4,000 3,000 Westinghouse. WCAP-17788, "Comprehensive Analysis and Test Program for GSI-191 Closure" Operating Reactors Oversight Baseline Inspections 1,625 2,100 1,863 This is relative to the number of plants, whether the site is a unique site, and/or is a BWR/PWR plant.
The estimate also does not include the recent new Design Basis Assurance inspection indicated separately below.
Operating Reactors Oversight Inspection Support Activities 2,022 4,954 3,488 Documentation, Preparation, Communication of Inspection, SDP, travel to site and Plant Status.
Numbers vary based on Regional and site needs.
Operating Reactors Oversight 95001 44 70 57 Operating Reactors Oversight 95002 122 220 171 Operating Reactors Oversight 95003 790 2,117 1,454 Operating Reactors Oversight Other Inspections and Assessment 40 330 185 Includes Event Response, IPE TI/SY, 95003 Follow-Up, IMC 0350, NRR Funded ISFSI Inspection, Assessment and Public Outreach Reactive Inspections do not occur at each plant annually. Hours may range based of the severity of an event.
Operating Reactors Oversight Design Basis Assurance (DBA) Inspection:
Inspection Procedures 71111.21M and 71111.21N 765 1,035 900 The DBA inspection is new and was first implemented the beginning of CY17. As such these are preliminary estimates. When additional actual data becomes available these estimates may be revised. The DBA inspection is a triennial inspection.
Operating Reactors Oversight Research and Test Reactors 4,500 5,760 5,130 Low estimate based on all docket-direct hours. High estimate includes inspector training, meetings, non-routine site visits, and enforcement and allegation actions, as well as special projects.