ML17286B125: Difference between revisions

From kanterella
Jump to navigation Jump to search
(Created page by program invented by StriderTol)
 
(Created page by program invented by StriderTol)
Line 49: Line 49:
+QQ REVISION<s'.I'JI NVMBEA~>NVMSE A PAGE 13)Washington Nuclear Plant-Unit 2 TEXT///moro 4Pooo ir n//I/ror/Iroo oddioooo/HRC
+QQ REVISION<s'.I'JI NVMBEA~>NVMSE A PAGE 13)Washington Nuclear Plant-Unit 2 TEXT///moro 4Pooo ir n//I/ror/Iroo oddioooo/HRC
%%drm 36643/(17)Plant Conditions Plant Node-1 (RUN)Power Level-12K Event Descri tion p 6 p p p OF 0 4 At approximately 1030 hours on September 30, 1991 plant personnel discovered that the primary containment airlock door seal leak rate test had not been performed within the allowable surveillance interval.WNP-2 was starting up from Cold Shutdown (Node 4)conditions after an extended outage.The actual startup began on September 26, 1991 at 1636 hours when the Node Switch was placed in the Startup/Hot Standby position and control rods were withdrawn.
%%drm 36643/(17)Plant Conditions Plant Node-1 (RUN)Power Level-12K Event Descri tion p 6 p p p OF 0 4 At approximately 1030 hours on September 30, 1991 plant personnel discovered that the primary containment airlock door seal leak rate test had not been performed within the allowable surveillance interval.WNP-2 was starting up from Cold Shutdown (Node 4)conditions after an extended outage.The actual startup began on September 26, 1991 at 1636 hours when the Node Switch was placed in the Startup/Hot Standby position and control rods were withdrawn.
Technical Specification 4.6,1.3.b requires that the a'irlock door seals be tested"within 72 hours following each closing, except when the airlock is being used for multiple entries, then at least once per 72 hours..." and is applicable in Nodes 1, 2 and 3.Since the plant was taken from Node 4 directly to Node 2 during this startup as normal for a startup from refueling, the 72 hour interval commenced when Node 2 was entered.The allowable 72 hours expi red at 1636 hours on September 29, 1991.However, Technical Specification 4.0.2 provides flexibility for surveillance scheduling by permitting Ra maximum allowable extension not to exceed 25$of the specified surveillance interval." In this case, the 255 provided an additional 18 hours for performance of the test.The additional 18 hours expired at 1036 on September 30, 1991.Although the test was begun at 0817 hours on September 30, 1991, it was not completed unti 1 1455 hours, a deviation from the Technical Specification requirements.
Technical Specification 4.6,1.3.b requires that the a'irlock door seals be tested"within 72 hours following each closing, except when the airlock is being used for multiple entries, then at least once per 72 hours..." and is applicable in Nodes 1, 2 and 3.Since the plant was taken from Node 4 directly to Node 2 during this startup as normal for a startup from refueling, the 72 hour interval commenced when Node 2 was entered.The allowable 72 hours expi red at 1636 hours on September 29, 1991.However, Technical Specification
 
====4.0.2 provides====
flexibility for surveillance scheduling by permitting Ra maximum allowable extension not to exceed 25$of the specified surveillance interval." In this case, the 255 provided an additional 18 hours for performance of the test.The additional 18 hours expired at 1036 on September 30, 1991.Although the test was begun at 0817 hours on September 30, 1991, it was not completed unti 1 1455 hours, a deviation from the Technical Specification requirements.
Immediate Corrective Action The airlock door seal surveillance was successfully completed at 1455 hours on September 30, 1991, restoring the airlock to fully operable status, Further Evaluation and Corrective Action A.Further Evaluation 2~The bases For the WNP-2 Technical Specifications states Afailure to perform a surveillance within the provisions of Specification 4.0.2 is a violation of a Technical'pecification requirement and is, therefore, a reportable event under the requirements of 10 CFR 50.-73(a)(2)(i)(B) because it is a condition prohibited by the plant's Te'chnical Specifications.R 1'his LER is submitted pursuant thereto.There were no structures, systems or components inoperable prior to'the event which conl:ributed to the event.NAC F orro 386A 164)9)
Immediate Corrective Action The airlock door seal surveillance was successfully completed at 1455 hours on September 30, 1991, restoring the airlock to fully operable status, Further Evaluation and Corrective Action A.Further Evaluation 2~The bases For the WNP-2 Technical Specifications states Afailure to perform a surveillance within the provisions of Specification 4.0.2 is a violation of a Technical'pecification requirement and is, therefore, a reportable event under the requirements of 10 CFR 50.-73(a)(2)(i)(B) because it is a condition prohibited by the plant's Te'chnical Specifications.R 1'his LER is submitted pursuant thereto.There were no structures, systems or components inoperable prior to'the event which conl:ributed to the event.NAC F orro 386A 164)9)
NRC FORM 368A (649)US.NUCLEAR REGULATORY COMMISSION LICENSEE E NT REPORT ILER)TEXT CONTINUATION APPROVED OMB NO.3150010S EXPIRES: S/30/92 TIMATED BURDEN PER RESPONSE TO COMPLY WTH THIS INFORMATION COLLECTION REOUEST: 60.0 HRS.FORWARD COMMENTS REGARDING BURDEN ESTIMATE TO THE RECORDS AND REPORTS MANAGEMENT BRANCH (PJ)30), U.S.NUCLEAR REGULATORY COMMISSION, WASHINGTON, DC 20555, AND TO 1HE PAPERWORK REDUCTION PROJECT (31500)04).
NRC FORM 368A (649)US.NUCLEAR REGULATORY COMMISSION LICENSEE E NT REPORT ILER)TEXT CONTINUATION APPROVED OMB NO.3150010S EXPIRES: S/30/92 TIMATED BURDEN PER RESPONSE TO COMPLY WTH THIS INFORMATION COLLECTION REOUEST: 60.0 HRS.FORWARD COMMENTS REGARDING BURDEN ESTIMATE TO THE RECORDS AND REPORTS MANAGEMENT BRANCH (PJ)30), U.S.NUCLEAR REGULATORY COMMISSION, WASHINGTON, DC 20555, AND TO 1HE PAPERWORK REDUCTION PROJECT (31500)04).

Revision as of 16:23, 18 October 2018

LER 91-028-00:on on 910930,containment Airlock Door Seal Leakage Test Not Performed within Allowable Surveillance Interval.Caused by Inadequate Personnel Work Practices. Master Startup Checklist amended.W/911030 Ltr
ML17286B125
Person / Time
Site: Columbia Energy Northwest icon.png
Issue date: 10/30/1991
From: BAKER J W, SWANK D A
WASHINGTON PUBLIC POWER SUPPLY SYSTEM
To:
NRC OFFICE OF INFORMATION RESOURCES MANAGEMENT (IRM)
References
GO2-91-199, LER-91-028, LER-91-28, NUDOCS 9111060116
Download: ML17286B125 (6)


Text

ACCELERATED DISTRIBUTION DEMONSTRATION SYSTEM~~REGULATORY INFORMATXON DXSTRIBUTXON SYSTEM (RIDS)ACCESSION NBR:9111060116 DOC.DATE: 91/10/30 NOTARIZED:

NO DOCKET I FACXL:50-397 WPPSS Nuclear Project, Unit 2, Washington Public Powe 05000397 AUTH.NAME AUTHOR AFFILIATION SWANK',D.A.

Washington Public Power Supply System'BAKER,J.W.

Washington Public Power Supply System RECIP.NAME RECIPIENT AFFILIATION

SUBJECT:

LER 91-028-00:on on 910930,containment airlock door seal leakage test not performed within allowable surveillance interval.Caused by inadequate personnel work practices.

Master startup checklist amended.W/911030 ltr.DISTRIBUTION CODE: IE22T COPIES RECEIVED:LTR g ENCL g SIZE: TXTLE: 50.73/50.9 Licensee Event Report (LER), Incident Rpt, etc.NOTES: RECIPXENT ID CODE/NAME PD5 LA ENG,P.L.INTERNAL: ACNW AEOD/DOA AEOD/ROAB/DSP NRR/DET/EMEB 7E NRR/DLPQ/LPEB10 NRR/DREP/PRPB11 NRR/DST/SICB8H3 NRR/DST/SRXB 8E RES/DSIR/EIB EXTERNAL: EG&G BRYCE,J.H NRC PDR NSIC POOREIW COPIES LTTR ENCL 1 1 1 1 2 2 1 1 2 2 1 1 1 1 2 2 1 1 1.1 1 1 3 3 1 1 1 1 RECIPIENT ID CODE/NAME PD5 PD ACRS AEOD/DSP/TPAB NRR/DET/ECMB 9H NRR/DLPQ/LHFB10 NRR/DOEA/OEAB NRR/DST/SELB 8D RR+D-LBSD1 EG FILE 02 RGN LE 01 L ST LOBBY WARD NSIC MURPHY,G.A NUDOCS FULL TXT COPIES LTTR ENCL 1 1 2 2 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 1 NOTE TO ALL"RIDS" RECIPIENTS PLEASE HELP US TO REDUCE 9 ASTE!CONTACT THE DOCUMENT CONTROL DESK, ROO>I Pl-37{EXT."-N79)TO 1LIMINATE YOUR NAivIE FROM DISTRIBUTION LISTS FOR DOCUiilENTS YOU DON'T NEED!FULL TEXT CONVERSION REQUIRED TOTAL NUMBER OF COPIES REQUIRED: LTTR 33 ENCL 33

~, 4a WASHINGTON PUBLIC POWER SUPPLY SYSTEM P.O.Box 988~3000 George)Vashington Way~RichIand, Washington 99352 October 30, 1991 Ci02-91-199 Docket No.50-397 Document ControlDesk U.S.Nuclear Regulatory Commission Washington, D.C.20555

Subject:

NUCLEAR PLANT NO.2 LICENSEE EVENT REPORT NO: 91-028

Dear Sir:

Transmitted herewith is Licensee Event Report No.91-028 for the WNP-2 Plant.This report is submitted in response to the report requirements of 10CFR50.73 and discusses the items of reportability, corrective action taken, and action taken to preclude recurrence.

Very truly yours,~W.Baker WNP-2 Plant Manager ,

Enclosure:

Licensee Event Report-No.91-028 cc: Mr.John B.Martin, NRC-Region V Mr.C.Sorensen, NRC Resident Inspector (M/D 901A)INPO Records Center-Atlanta, GA Ms.Dottie, Sherman, ANI Mr.D.L.Williams, BPA (M/D 399)NRC Resident Inspector-walk over copy pL NRC FORM 3$6 (64(9)US.NUCLEAR REGULATORY COMMISSION LICENSEE EVENT REPORT (LER)'PPROVED OMB NO.31604)104 EXPIRES: 4I30I92 ESTIMATED BURDEN PER RE$PONSE TO COMPLY WTH THIS INFORMATION COLLECTION REQUEST: 50.0 HRS.FORWARD COMMENTS REGARDING BURDEN ESTIMATE TO THE RECORDS AND REPORTS MANAGEMENT BRANCH (F430), U.S.NUCLEAR REGULATORY COMMISSION.

WA$HINGTON, OC 20565, AND TO THE PAPERWORK REDUCTION PROJECT (31600104), OFFICE OF MANAGEMENT AND BUDGET, WASHINGTON.

DC 20603'ACILITY NAME (1)TITLE (~)EVENT DATE (6)DOCKET NUMBER l1)0 5 0 0 0 Seal Test No't Performed in Allowable Time Period LER NUMBER (6)REPORT DATE (7)OTHER FACILI'TIES INVOLVED (Bl PA E 3 1 OF MONTH OAY YEAR YEAR~~X".SEQUENTIAL NUMBER IIEVISION NUMBER MONTH DAY YEAR FACILITY NAMES DOCKET NUMBER($)0 5 0 0 0 028 0 1 0 3 0 0 5 0 0 0 OPERATINQ MODE (9)POWER LEVEL (10)i@/(;.(TBI(~gp~gvp (Q$",.I".I'P~igp@j:

NAME 20.402(s)20.406(sl(1)(il 20.40$(s'll1)(il) 20.406(s)(1)(i(i)20.405 (~)(I)(lv)20.406(~l(1)lvl 20.40S(c)50.36 (c)(I)50.36(cl(1) 50,73(s)(1HI)50.73(~)l2)lii)50.73(sl(1) liiil LICENSEE CONTACT FOR THIS LER ((2)60.73(v)(2)(ivl 60.73(s)l2)(v)50.73(sl(2) lvii)$0,73(s)(2)

(villi(A)60.73(~l(2)(villi(8) 60.73(~)(2)(s)AREA CODE THIS REPORT IS SUBMITTED PURSUANT 7 0 THE RtoUIREMENTs oF 10 cFR (II Icnrcs onr of morr of tnr forrovnnp)

(11 73.71(6)73.71(c)OTHER ISprclfy ln Apttrrct tNrow md ln Trst, ff RC Form 3664)TELEPHONE NUMBER COMPLETE ONE LINE FOR EACH COMPONENT FAILURE DESCRIBED IN THIS REPORT (13)CAUSE SYSTEM COMPONENT MANUFAC.TURER EPORTABLE TO NPRDS$CAUSE SYSTEM COMPONENT.;'.,':E~~~~~:.

MANUFAC.TUBER EPORTABLE TO NPRDS 5<Wix'='.;" SUPPLEMENTAL REPORT EXPECTED (14)EXPECTED SUBMISSION DATE (15I MONTH OAY YEAR YFS (if yrt.complrtr EXPECTED SUBMISSION DATE)NO ABSTRACT (Limit ro trp0 tprcrt.I r..rpprosimrrrty fi ltrrn tinprrrprcr ryprwritrrn linrrl l16)On September 30, 1991 at 1036 hours0.012 days <br />0.288 hours <br />0.00171 weeks <br />3.94198e-4 months <br /> the containment airlock door seal leakage test required by Technical Specification 3/4.6.1.3 was not performed within the allowable survei 1,lance interval.This is a deviation from the plant's Technical Specifications and is reportable in accordance with the requirements of 10 CFR 50..73(a)(2)(i)(B).

WNP-2 entered Node 2 from,Node 4 at 1636 hours0.0189 days <br />0.454 hours <br />0.00271 weeks <br />6.22498e-4 months <br /> on September 26, 1991.From that time the plant had 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> (plus 255 or 18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br />)to complete the required airlock seal test.The test was completed approximately four hours after expiration of the Technical Specification allowed surveillance interval, but within the 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> period provided in Action Statement 3.6.1.3.c.

The.root cause of this event is personnel work practices less than adequate in that an intended or requi red veri fication was not performed.A procedurally required verification that the airlock seal test be performed in the allotted time period was not satisfied'orrective actions include: 1)Immediate performance of the required testing within tile Action Statement time requirements; 2)Deviations to plant startup procedures to include specific guidance and requirements to ensure the test is performed prior to entry into the applicable Operational Condition; and 3)7'his LLR wi.ll be required reading for Operations personnel.

NRC Form 366 (649)

NRC FORM 388A I689)U S NUCLEAR REGULATORY COMMISSION LICENSEE EV NT REPORT{LER)TEXT CONTINUATION APPROVEO OMB NO.31504)104 EXPIRES: 4/30/92 TIMATED BURDEN PEA RESPONSE TO COMPLY WTH THIS INFORMATION COLLECTION REOUEST: 503)HAS.FORWARD COMMENTS REGARDING BUADEN ESTIMATE TO THE RECORDS AND REPORTS MANAGEMENT BRANCH IP4)30), U.S.NUCLEAR REGULATORY COMMISSION.

WASHINGTON, DC 20555, AND TO 1HE PAPERWORK REDUCTION PROJECT 13)504)104), OFFICE OF MANAGEMENT AND BUDGET, WASHINGTON, DC 20503.FACILITY NAME II)DOCKET NUMBER lll LER NUMBER)6)YEAR SPY/FSEOVENTIAL

+QQ REVISION<s'.I'JI NVMBEA~>NVMSE A PAGE 13)Washington Nuclear Plant-Unit 2 TEXT///moro 4Pooo ir n//I/ror/Iroo oddioooo/HRC

%%drm 36643/(17)Plant Conditions Plant Node-1 (RUN)Power Level-12K Event Descri tion p 6 p p p OF 0 4 At approximately 1030 hours0.0119 days <br />0.286 hours <br />0.0017 weeks <br />3.91915e-4 months <br /> on September 30, 1991 plant personnel discovered that the primary containment airlock door seal leak rate test had not been performed within the allowable surveillance interval.WNP-2 was starting up from Cold Shutdown (Node 4)conditions after an extended outage.The actual startup began on September 26, 1991 at 1636 hours0.0189 days <br />0.454 hours <br />0.00271 weeks <br />6.22498e-4 months <br /> when the Node Switch was placed in the Startup/Hot Standby position and control rods were withdrawn.

Technical Specification 4.6,1.3.b requires that the a'irlock door seals be tested"within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> following each closing, except when the airlock is being used for multiple entries, then at least once per 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br />..." and is applicable in Nodes 1, 2 and 3.Since the plant was taken from Node 4 directly to Node 2 during this startup as normal for a startup from refueling, the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> interval commenced when Node 2 was entered.The allowable 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> expi red at 1636 hours0.0189 days <br />0.454 hours <br />0.00271 weeks <br />6.22498e-4 months <br /> on September 29, 1991.However, Technical Specification

4.0.2 provides

flexibility for surveillance scheduling by permitting Ra maximum allowable extension not to exceed 25$of the specified surveillance interval." In this case, the 255 provided an additional 18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> for performance of the test.The additional 18 hours2.083333e-4 days <br />0.005 hours <br />2.97619e-5 weeks <br />6.849e-6 months <br /> expired at 1036 on September 30, 1991.Although the test was begun at 0817 hours0.00946 days <br />0.227 hours <br />0.00135 weeks <br />3.108685e-4 months <br /> on September 30, 1991, it was not completed unti 1 1455 hours0.0168 days <br />0.404 hours <br />0.00241 weeks <br />5.536275e-4 months <br />, a deviation from the Technical Specification requirements.

Immediate Corrective Action The airlock door seal surveillance was successfully completed at 1455 hours0.0168 days <br />0.404 hours <br />0.00241 weeks <br />5.536275e-4 months <br /> on September 30, 1991, restoring the airlock to fully operable status, Further Evaluation and Corrective Action A.Further Evaluation 2~The bases For the WNP-2 Technical Specifications states Afailure to perform a surveillance within the provisions of Specification 4.0.2 is a violation of a Technical'pecification requirement and is, therefore, a reportable event under the requirements of 10 CFR 50.-73(a)(2)(i)(B) because it is a condition prohibited by the plant's Te'chnical Specifications.R 1'his LER is submitted pursuant thereto.There were no structures, systems or components inoperable prior to'the event which conl:ributed to the event.NAC F orro 386A 164)9)

NRC FORM 368A (649)US.NUCLEAR REGULATORY COMMISSION LICENSEE E NT REPORT ILER)TEXT CONTINUATION APPROVED OMB NO.3150010S EXPIRES: S/30/92 TIMATED BURDEN PER RESPONSE TO COMPLY WTH THIS INFORMATION COLLECTION REOUEST: 60.0 HRS.FORWARD COMMENTS REGARDING BURDEN ESTIMATE TO THE RECORDS AND REPORTS MANAGEMENT BRANCH (PJ)30), U.S.NUCLEAR REGULATORY COMMISSION, WASHINGTON, DC 20555, AND TO 1HE PAPERWORK REDUCTION PROJECT (31500)04).

OFFICE OF MANAGEMENT AND BUDGET, WASHINGTON.

DC 20503.FACILITY NAME (1)DOCKET NUMBER (2)LER NUMBER (6)YEAR gyR SSOUSNTIAL GN REVISION NUMSSR>>>NUMBER PAGE (3)Washington Nuclear Plant-Unit 2 TEXT///moro sPooo/s rer/Ir/ror/

Iroo or/I//r/ooo/HRC Forrrr 36643/()7)p s p p p3 97 1 028 0 0 0 3oF 3.On expiration of the allowed surveillance time interval (plus 25K)the airlock was technically inoperable.

Upon determining that the airlock door seal leak test had not been performed, the Shift Manager logged entry into the Action Statement for the airlock Technical Specification (3/4.6.1.3) at 1045 hours0.0121 days <br />0.29 hours <br />0.00173 weeks <br />3.976225e-4 months <br /> on September 30, 1991.Airlock operability was restored within the action statement 24 hour2.777778e-4 days <br />0.00667 hours <br />3.968254e-5 weeks <br />9.132e-6 months <br /> time limit and no further immediate action was necessary.

4, The apparent cause, of this event is personnel work practices were less than adequate in that an intended or required verification was not'erformed.

The Master Startup Checklist procedure (PPN 3.1.1)specifies that the procedure performer verify that the airlock door seals be tested"within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> following closing[of the airlock door]for establishing primary containment." This procedure step was signed off with the understanding that the seals would be tested following the completion of required containment entries for inspections, and prior to the expi ration of the 72 hour8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> allowable time period.Normal administrative methods of tracking required actions for Technical Specification Limiting Condition For Operation or inoperable equipment were not utilized.This resulted in the seal test not being completed within the allowable time period.B.Further Corrective Action The Master Startup Checklist, PPM 3.1.1, has been amended to require performance of the airlock door seal tests prior to entry into Node 2.Previously, the procedure required only a verification that the"Door seals tested within 72 hours8.333333e-4 days <br />0.02 hours <br />1.190476e-4 weeks <br />2.7396e-5 months <br /> following closing...R This change forces performance of the surveillance prior"to entry into Node 2, or logging the equipment as inoperable.

2.Precautions and signoff steps have been added to PPNs 3.1.1, 3.1.2 (Reactor Plant Cold Startup), and 3.1.4 (Minimum Startup Checklist) to reflect the surveillance requirements following closure of the airlock.3.This LER will be required reading for Operations personnel.

Safet Si nificance This event had no safety significance.

Performance of the required airlock door seal leakage test verified that the seals were intact and met the required leakage acceptance criteria.In addition, the test of the entire airlock for leakage, as required by Technical Specification 4.6.1.3.c, was up-to-date.

This test provides additional assurance that the airlock was capable of performing it's intended safety function.NRC Form 366A (6$9)

NRC FORM 366A (649)U.S NUCLEAR REGULATORY COMMISSION LICENSEE E ENT REPORT (LER)TEXT CONTINUATION APPROVED OMB NO.31500104 EXPIRES: 6/30/92 TIMATED BUADEN PER RESPONSE TO COMPLY WTH THIS INFORMATION COLLECTION REOUESTI 60.0 HAS.FORWARD COMMENTS REGARDING BURDEN ESTIMATE TO THE RECORDS AND REPORTS MANAGEMENT BRANCH IP430).U.S.NUCLEAR REGULATORY COMMISSION, WASHINGTON, DC 20555, AND TO 1HE PAPERWORK REDUCTION PROJECT (3150010m), OFF/CE OF MANAGEMENT AND BUDGET, WASHINGTON.

DC 20503.FACILITY NAME (11 DOCKET NUMBER (2)LEA NUMBER (6)PAGE (3)Washington Nuclear Plant-Unit 2 TEXT///moro S>>oe/n nor/rr/rmd, Iree odd/dor>>/HRC Form 366AB/(17)YEAR o s o o.o 3 979 l SEGUE NTIAL NUMSSII 028 REVISION NUMSSII 0 0 0 4 OF 0 4 Similar Events LER 87-031 documented one instance of a Technical Specification deviation due to personnel failure to follow established procedural requi rements.In that instance, plant personnel failed to recognize that a surveillance requirement was not met during the performance of a surveillance test and failed to notify the Operations Shift IIIanager'f this condition as required by the procedure.

EIIS Information Text Reference EIIS Reference System~tom onent Containment Airlock AL NRC Form 366A (649)