MONTHYEARW3F1-2023-0052, Core Operating Limits Report (COLR) - Cycle 26, Revision O2023-11-0707 November 2023 Core Operating Limits Report (COLR) - Cycle 26, Revision O ML22123A3322022-05-0303 May 2022 Core Operating Limits Report (COLR) - Cycle 25, Revision 0 W3F1-2020-0066, Core Operating Limits Report (COLR) - Cycle 24, Revision 22020-11-11011 November 2020 Core Operating Limits Report (COLR) - Cycle 24, Revision 2 W3F1-2020-0064, Core Operating Limits Report (COLR) - Cycle 24, Revision 12020-10-27027 October 2020 Core Operating Limits Report (COLR) - Cycle 24, Revision 1 W3F1-2020-0058, Core Operating Limits Report (COLR) - Cycle 24, Revision 02020-10-15015 October 2020 Core Operating Limits Report (COLR) - Cycle 24, Revision 0 W3F1-2019-0015, Core Operating Limits Report (COLR) - Cycle 23, Revision 12019-03-13013 March 2019 Core Operating Limits Report (COLR) - Cycle 23, Revision 1 W3F1-2019-0014, Core Operating Limits Report-Cycle 23 Revision 02019-02-14014 February 2019 Core Operating Limits Report-Cycle 23 Revision 0 W3F1-2017-0045, Core Operating Limits Report - Cycle 22 Revision 02017-05-0909 May 2017 Core Operating Limits Report - Cycle 22 Revision 0 W3F1-2017-0034, Submittal of Core Operating Report for Cycle 21, Rev. 12017-04-0505 April 2017 Submittal of Core Operating Report for Cycle 21, Rev. 1 W3F1-2015-0088, Submits Core Operating Limits Report - Cycle 21 Revision 02015-11-18018 November 2015 Submits Core Operating Limits Report - Cycle 21 Revision 0 W3F1-2014-0047, Core Operating Limits Report - Cycle 20, Revision 12014-07-29029 July 2014 Core Operating Limits Report - Cycle 20, Revision 1 W3F1-2014-0033, Core Operating Limits Report Cycle 20 Revision 0, Waterford Steam Electric Station, Unit 32014-05-12012 May 2014 Core Operating Limits Report Cycle 20 Revision 0, Waterford Steam Electric Station, Unit 3 W3F1-2013-0074, Core Operating Limits Report - Cycle 19 Revision 22013-12-18018 December 2013 Core Operating Limits Report - Cycle 19 Revision 2 W3F1-2013-0026, Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 18 / Refuel 182013-04-18018 April 2013 Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 18 / Refuel 18 W3F1-2012-0103, Core Operating Limits Report - Cycle 19 Revision 02012-12-14014 December 2012 Core Operating Limits Report - Cycle 19 Revision 0 W3F1-2011-0084, Core Operating Limits Report - Cycle 18 Revision 02011-11-23023 November 2011 Core Operating Limits Report - Cycle 18 Revision 0 ML11229A0262011-08-10010 August 2011 Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 17 / Refuel 17 W3F1-2009-0030, Response to Amendment Request NPF-38-276, Core Protection Calculator Power Calibration Adjustment Limit2009-06-30030 June 2009 Response to Amendment Request NPF-38-276, Core Protection Calculator Power Calibration Adjustment Limit W3F1-2008-0057, Startup Power Escalation Report for Cycle 162008-08-25025 August 2008 Startup Power Escalation Report for Cycle 16 W3F1-2008-0041, Core Operating Limits Report - Cycle 16 Revision 02008-05-20020 May 2008 Core Operating Limits Report - Cycle 16 Revision 0 W3F1-2006-0068, Core Operating Limits Report - Cycle 15 Revision 02006-12-14014 December 2006 Core Operating Limits Report - Cycle 15 Revision 0 W3F1-2006-0063, 10 CFR 50.46 Thirty-Day Report for Changes to the Plant Emergency Core Cooling System Performance Analysis2006-12-0606 December 2006 10 CFR 50.46 Thirty-Day Report for Changes to the Plant Emergency Core Cooling System Performance Analysis ML0513902172005-05-17017 May 2005 Core Operating Limits Report for Cycle 14, Revision 0 W3F1-2004-0022, Core Operating Limits Report - Cycle 13 Revision 1, Change 22004-04-19019 April 2004 Core Operating Limits Report - Cycle 13 Revision 1, Change 2 W3F1-2003-0097, Core Operating Limits Report, Cycle 13, Revision 1, Change 12003-11-20020 November 2003 Core Operating Limits Report, Cycle 13, Revision 1, Change 1 W3F1-2003-0094, Core Operating Limits Report, Cycle 13, Revision 12003-11-17017 November 2003 Core Operating Limits Report, Cycle 13, Revision 1 W3F1-2003-0086, Core Operating Limits Report - Cycle 13, Revision 02003-11-0505 November 2003 Core Operating Limits Report - Cycle 13, Revision 0 W3F1-2002-0064, Ses Startup and Power Escalation Report for Cycle 122002-07-12012 July 2002 Ses Startup and Power Escalation Report for Cycle 12 W3F1-2002-0034, Ses Core Operating Limits Report for Cycle 122002-04-0404 April 2002 Ses Core Operating Limits Report for Cycle 12 2023-11-07
[Table view] Category:Letter type:W
MONTHYEARW3F1-2024-0040, Special Report SR 2024-001-00 Radiation Monitor Inoperable Greater than 7 Days2024-09-0303 September 2024 Special Report SR 2024-001-00 Radiation Monitor Inoperable Greater than 7 Days W3F1-2024-0019, (Waterford 3) - Steam Generator Tube Inspection Report for the 25th Rf Inspection Performed During Operating Cycle 25 / Refuel 252024-07-22022 July 2024 (Waterford 3) - Steam Generator Tube Inspection Report for the 25th Rf Inspection Performed During Operating Cycle 25 / Refuel 25 W3F1-2024-0032, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation2024-07-17017 July 2024 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation W3F1-2024-0024, Special Report SR 2023-004-02 Radiation Monitor Inoperable Greater than 7 Days2024-06-17017 June 2024 Special Report SR 2023-004-02 Radiation Monitor Inoperable Greater than 7 Days W3F1-2024-0011, Licensee Amendment Request to Modify Surveillance Requirements in Support of Surveillance Frequency Control Program2024-05-0808 May 2024 Licensee Amendment Request to Modify Surveillance Requirements in Support of Surveillance Frequency Control Program W3F1-2024-0018, Submittal of Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 25 / Refuel 252024-05-0101 May 2024 Submittal of Owners Activity Report Form for Inservice Inspection Performed During Operating Cycle 25 / Refuel 25 W3F1-2024-0014, Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 20242024-04-29029 April 2024 Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 2024 W3F1-2024-0015, Annual Radioactive Effluent Release Report (ARERR) 2023 with Revised ODCM and Revised Process Control Program Procedure2024-04-24024 April 2024 Annual Radioactive Effluent Release Report (ARERR) 2023 with Revised ODCM and Revised Process Control Program Procedure W3F1-2024-0016, Annual Radiological Environmental Operating Report (AREOR) - 20232024-04-24024 April 2024 Annual Radiological Environmental Operating Report (AREOR) - 2023 W3F1-2024-0017, Annual Report of Individual Monitoring of Radiation Exposure for 2023 Per 10 CFR 20.22062024-04-23023 April 2024 Annual Report of Individual Monitoring of Radiation Exposure for 2023 Per 10 CFR 20.2206 W3F1-2024-0020, Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 20232024-04-11011 April 2024 Annual Report on Westinghouse Electric Company LLC Combustion Engineering Emergency Core Cooling System Performance Evaluation Models for Calendar Year 2023 W3F1-2024-0008, Proposed Alternative WF3-RR-24-01 for Examinations of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds2024-03-18018 March 2024 Proposed Alternative WF3-RR-24-01 for Examinations of Pressurizer Circumferential and Longitudinal Shell-to-Head Welds and Nozzle-to-Vessel Welds W3F1-2024-0009, Proposed Alternative WF3-RR-24-02 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles2024-03-18018 March 2024 Proposed Alternative WF3-RR-24-02 for Examinations of Steam Generator Pressure-Retaining Welds and Full Penetration Welded Nozzles W3F1-2024-0012, Response to NRC Integrated Inspection Report 05000382/20230042024-03-11011 March 2024 Response to NRC Integrated Inspection Report 05000382/2023004 W3F1-2024-0006, Special Report SR-2023-004-01, Radiation Monitor Inoperable Greater than 7 Days2024-02-28028 February 2024 Special Report SR-2023-004-01, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0056, Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242023-12-19019 December 2023 Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2023-0055, Reply to a Notice of Violation2023-12-14014 December 2023 Reply to a Notice of Violation W3F1-2023-0052, Core Operating Limits Report (COLR) - Cycle 26, Revision O2023-11-0707 November 2023 Core Operating Limits Report (COLR) - Cycle 26, Revision O W3F1-2023-0049, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal2023-09-28028 September 2023 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability - Withdrawal W3F1-2023-0048, Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-09-25025 September 2023 Special Report SR 2023-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0035, Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program2023-07-26026 July 2023 Application for Technical Specification Change to Revise Surveillance Requirements Included in the Surveillance Frequency Control Program W3F1-2023-0036, Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2023-05-0404 May 2023 Special Report SR-2023-003-01 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0032, Annual Radioactive Effluent Release Report (ARERR) 20222023-04-27027 April 2023 Annual Radioactive Effluent Release Report (ARERR) 2022 W3F1-2023-0033, Submittal of Annual Radiological Environmental Operating Report - 20222023-04-27027 April 2023 Submittal of Annual Radiological Environmental Operating Report - 2022 W3F1-2023-0025, Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.22062023-04-11011 April 2023 Annual Report of Individual Monitoring of Radiation Exposure for 2022 Per 10 CFR 20.2206 W3F1-2023-0018, Updated Final Supplemental Response to NRC Generic Letter 2004-022023-03-30030 March 2023 Updated Final Supplemental Response to NRC Generic Letter 2004-02 W3F1-2023-0022, Registration of Dry Fuel Storage Cask Use2023-03-22022 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0021, Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days2023-03-17017 March 2023 Submittal of Special Report SR 2023-003-00 Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0016, Registration of Dry Fuel Storage Cask Use2023-03-0303 March 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0014, Reply to a Notice of Violation; EA-22-1192023-02-20020 February 2023 Reply to a Notice of Violation; EA-22-119 W3F1-2023-0013, Notification of Readiness for Supplemental Inspection2023-02-15015 February 2023 Notification of Readiness for Supplemental Inspection W3F1-2023-0007, Registration of Dry Fuel Storage Cask Use2023-02-0606 February 2023 Registration of Dry Fuel Storage Cask Use W3F1-2023-0010, Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days2023-01-25025 January 2023 Special Report SR 2023-002-00, Radiation Monitor Inoperable Greater than 7 Days W3F1-2023-0002, SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days2023-01-0505 January 2023 SR 2023-001-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 30 Days W3F1-2022-0067, Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-022022-12-20020 December 2022 Commitment Change Notification for Generic Safety Issue 191 and Generic Letter 2004-02 W3F1-2022-0054, Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability2022-11-0101 November 2022 Revise Technical Specification 3/4.3.2 to Remove Exemption from Testing Certain Relays at Power to Support Elimination of Potential Single Point Vulnerability W3F1-2022-0063, Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 372022-10-27027 October 2022 Submittal of Emergency Preparedness Documents. Includes EP-001-001, Revision 37 W3F1-2022-0059, Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-5052022-10-13013 October 2022 Response to Clarification Questions Concerning Supplement to License Amendment Request to Adopt TSTF-505 W3F1-2022-0058, Reply to a Notice of Violation; EA-22-0332022-10-12012 October 2022 Reply to a Notice of Violation; EA-22-033 W3F1-2022-0049, Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-5052022-08-19019 August 2022 Response to Request for Additional Information Regarding License Amendment Requests to Adopt 10 CFR 50.69 and TSTF-505 W3F1-2022-0037, Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 242022-08-0808 August 2022 Submittal of Owner'S Activity Report Form for Inservice Inspection Performed During Operating Cycle 24 / Refuel 24 W3F1-2022-0044, SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-07-0606 July 2022 SR-2022-004-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0042, SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days2022-06-27027 June 2022 SR-22-003-00 for Waterford Steam Electric Station, Unit 3, Radiation Monitor Inoperable Greater than 7 Days W3F1-2022-0015, Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf.2022-05-16016 May 2022 Response to Request for Additional Information to License Amendment Request to Revise Technical Specifications to Adopt TSTF-505, Revision 2, Provide Risk Informed Extended Completion Times - Ritstf. W3F1-2022-0026, Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 20222022-04-28028 April 2022 Report of Facility Changes, Tests, and Experiments and Commitment Changes for Two Year Period Ending April 28, 2022 W3F1-2022-0028, Annual Radiological Environmental Operating Report - 20212022-04-26026 April 2022 Annual Radiological Environmental Operating Report - 2021 W3F1-2022-0029, Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.22062022-04-26026 April 2022 Annual Report of Individual Monitoring of Radiation Exposure for 2021 Per 10 CFR 20.2206 W3F1-2022-0031, Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-2842022-04-25025 April 2022 Proposed Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule to Reflect Location of Standby Capsules 3/W-104 and 6/W-284 W3F1-2022-0009, Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors2022-04-25025 April 2022 Supplement to Application to Adopt 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems, and Components (Sscs) for Nuclear Power Reactors W3F1-2022-0020, Review of Preliminary Accident Sequence Precursor Report2022-04-11011 April 2022 Review of Preliminary Accident Sequence Precursor Report 2024-09-03
[Table view] |
Text
'Entergy Entergy Operations, Inc.
17265 River Road Killona. LA 70066 Tel 504 739 6650 W3Fl-2004-0022 April 19, 2004 U.S. Nuclear Regulatory Commission Attn: Document Control Desk Washington, DC 20555-0001
Subject:
Core Operating Limits Report - Cycle 13 Revision 1, Change 2 Waterford Steam Electric Station, Unit 3 (Waterford 3)
Docket No. 50-382 License No. NPF-38
Dear Sir or Madam:
Waterford 3 Technical Specification 6.9.1.11.3 requires submittal of the Core Operating Limits Report (COLR) for each reload cycle. Revision 1, Change 1 of the COLR for Waterford 3 Cycle 13 was submitted on November 19, 2003 by letter W3F1 -2003-0097.
COLR Cycle 13, Revision 1 Change 1 revised Section 3.2.7, Axial Shape Index (ASI), to implement a 0.03 positive adjustment to the lower limit of the allowed ASI range (changed from -0.22 to -0.19) for 2 70% power. The change was necessary due to the upward shift of incore instrumentation due to a modification performed in Refueling Outage 12 and was based on a conservative preliminary assessment of the impact of changes in incore instrumentation (ICI) position on the operation of the Core Operating Limit Supervisory and CPCs.
Final detailed analysis on the impact of changes in ICI position have been completed and the attached COLR Cycle 13 Revision 1, Change 2 revises Section 3.2.7, Axial Shape Index (ASI), to reduce the adjustment to the lower limit of the allowed ASI range for 2 70%
power. The allowed ASI lower limit is changed from -0.19 to -0.21.
If you have any questions concerning this submittal please contact D.L. Bentzinger at (504) 739-6368.
4CoDI
W3FI-2004-0022 Page 2 There are no new commitments contained in this submittal.
incerely, G. Sen Licensing Manager GS/TMM/cbh Attachment(s)
W3Fl-2004-0022 Page 3 cc: Mr. Bruce S. Mallett Regional Administrator U. S. Nuclear Regulatory Commission Region IV 611 Ryan Plaza Drive, Suite 400 Arlington, TX 76011-8064 NRC Senior Resident Inspector Waterford NPS P.O. Box 822 Killona, LA 70066-0751 U. S. Nuclear Regulatory Commission Attn: Mr. N. Kalyanam Mail Stop 0-07D1 Washington, DC 20555-0001 Wise, Carter, Child & Caraway ATTN: J. Smith P.O. Box 651 Jackson, MS 39205 Winston & Strawn ATTN: N.S. Reynolds 1400 L Street, NW Washington, DC 20005-3502 Platts Energy ATTN: B. Lewis 1200 G. St., N.W. Suite 1000 Washington, DC 20005
W3FI-2004-0022 Waterford 3 Core Operating Limits Report Cycle 13, Revision 1, Change 2
ENTERGY OPERATIONS WATERFORD 3 CORE OPERATING LIMITS REPORT FOR CYCLE 13 REVISION 1, CHG. 2 Prepared by: D. L. Bentzinger /,~t/ /g + /t1 Nuclear Engineering Reviewed by: J.M. Manzella Ls$c t( A1 I//Y'-
Lic nsing Approved by: J. B. Holman 9J Nbclear Engineering Approved by: G. Sen "X hi4 /ng ° LicvnK i (
WATERFORD 3 Page 1 CYCLE 13 REVISION 1, CHG. 2 l
WATERFORD 3 CORE OPERATING LIMITS REPORT CYCLE 13, REVISION 1, CHG. 2 INDEX PAGE I. INTRODUCTION 5
- 11. AFFECTED TECHNICAL SPECIFICATIONS 6 3.1.1.1 Shutdown Margin - Any CEA Withdrawn COLR 3/4 1-1 3.1.1.2 Shutdown Margin -All CEAs Fully Inserted COLR 3/4 1-3 3.1.1.3 Moderator Temperature Coefficient COLR 3/4 1-4 3.1.2.9 Boron Dilution COLR 3/4 1-15 3.1.3.1 Movable Control Assemblies - CEA Position COLR 3/4 1-18 3.1.3.6 Regulating and Group P CEA Insertion Limits COLR 3/4 1-25 3.2.1 Linear Heat Rate COLR 3/4 2-1 3.2.3 Azimuthal Power Tilt - Tq COLR 3/4 2-4 3.2.4 DNBR Margin COLR 3/4 2-6 3.2.7 Axial Shape Index COLR 3/4 2-12 3.9.1 Boron Concentration COLR 3/4 9-1 1II. METHODOLOGIES 33 LIST OF EFFECTIVE PAGES Revision 0 Pages 1-6, COLR 3/4 1-1 through COLR 3/4 9-1 and Page 33 Revision 1 Pages 1-6, COLR 3/4 1-1 through COLR 3/4 9-1 and Page 33 Revision 1 Pages 1, 2, 5, and COLR 3 /4 2-12 R ng. 1 Revision 1 Pages 1, 2, 5, 5a and COLR 3 /4 2-12 Chg. 2 WATERFORD 3 Page 2 CYCLE 13 REVISION 1, CHG. 2 l
WATERFORD 3 CORE OPERATING LIMITS REPORT CYCLE 13, REVISION 1, CHG. 2 I. INTRODUCTION This CORE OPERATING LIMITS REPORT (COLR) has been prepared in accordance with the requirements of Waterford 3 Technical Specification 6.9.1.1 1 for Waterford 3 Cycle 13. The core operating limits have been developed using the NRC approved methodologies specified in Section 1II. This is Revision I of the Cycle 13 COLR.
The major changes between the Cycle 13 Revision 0 COLR and the Cycle 12 COLR are listed below:
- The Table of Contents List of Effective Pages was updated.
- The List of Figures were revised to add COLR Figure 8A and to update the List of Effective Figure Pages
- This Introduction section was revised to reflect the changes for Cycle 13.
- The surveillance requirements for Section 3.1.2.9 were changed based on results of a corrective action of Condition Report CR-WF3-2003-02844.
- Clarifying notes were added below Sections 3.1.3.1.a and 3.1.3.1.b regarding the correspondence of these sections to Technical Specifications.
.* The title for Section 3.1.3.6 was revised to match references in Section III and the Table of Contents
- Figures 6 & 7 were revised to provide vertical lines from the endpoints of the plotted line to the temperature axis. Also, the equation for the plotted line was added.
- Section 3.2.4.b was revised to allow use of Figure 8A
- Notes below the text of Section 3.2.4 for use with Figures 8, 8A & 9 were updated and new notes were added.
- Figure 8,was revised to incorporate cycle-specific limits for Cycle 13.
- Figure 8A, was added to provide better resolution for the three power ranges in the lower portion of Figure 8.
- Figure 9,was revised to incorporate cycle-specific limits for Cycle 13.
- Section 111.7 was revised to add the document date.
- Section 111.8 was added in accordance with License Amendment 191.
The changes between the Cycle 13 Revision I COLR and the Cycle 13 Revision 0 COLR are listed below:
- Figures 6 & 7 were revised to implement a 0.1 KW/FT reduction for the specified temperature range to account for greater than 500 but less than 600 plugged tubes in Steam Generator #1 (Ref. ER-WF3-2003-0117-000)
The change between the Cycle 13 Revision 1 COLR and the Cycle 13 Revision 1Chg. 1 COLR is listed below:
Section 3.2.7, Axial Shape Index, was revised to implement a 0.03 positive bias to the lower limit of the allowed ASI range (changed from -0.22 to -0.19) for 2 70% power. This change was necessary due to the upward shift of incore instrumentation due to a modification performed in Refueling Outage 12 (Ref. Westinghouse Letter CWTR-03-190, dated 11/17/03).
WATERFORD 3 Page 5 CYCLE 13 REVISION 1, CHG. 2
The change between the Cycle 13 Revision 1 Chg. 1 COLR and the Cycle 13 Revision 1 Chg. 2 COLR is listed below:
Cycle 13 Revision 1 Chg. 1 was based on a conservative preliminary assessment of the impact of changes in ICI position on the operation of the COLSS and CPCS. The necessary detailed study has since been completed and the results were transmitted via Westinghouse Letter CWTR-03-197, dated 1/8104. The maximum required margin penalty was reduced from those installed in COLSS at the beginning of Cycle 13. The suggested change to COLSS constant ASINBP(3) is still conservative to that originally suggested in the Waterford 3, Cycle 13 Startup Test and Setpoints Transmittal, (Ref.
NF-03-W-WrFD-40, dated 10/2/03) which assumed no changes in ICI position. Section 3.2.7, Axial Shape Index, was revised to implement a 0.02 negative bias to the lower limit of the allowed ASI range (changed from -0.19 to -0.21) for 2 70% power.
WATERFORD 3 Page 5A CYCLE 13 REVISION 1, CHG. 2 l
- - Z o CORE OPERATING LIMITS REPORT AXIAL SHAPE INDEX 3.2.7 The AXIAL SHAPE INDEX (ASI) shall be maintained within the following limits
COLSS Operable
-0.21 < ASI * +0.26 for THERMAL POWERS > 70% of RATED THERMAL POWER
-0.26 < ASI * +0.26 for THERMAL POWERS from 20% to 70% of RATED THERMAL POWER COLSS Out of Service
-0.17 < ASI * +0.22 for THERMAL POWERS from 20% to 100% of RATED THERMAL POWER WATERFORD3
... .. _ _ _ _ COLR3/42-12 CYCLE 13 REVISION 1. CHG 2