TXX-2866, Responds to Violations Noted in Insp Repts 50-445/78-11 & 50-446/78-11 on 780620-23.Corrective Actions:Pipe Spools Inspected & Tagged & Formal QA Surveillances of Cleanliness Control Will Be Performed on Monthly Basis

From kanterella
(Redirected from TXX-2866)
Jump to navigation Jump to search
Responds to Violations Noted in Insp Repts 50-445/78-11 & 50-446/78-11 on 780620-23.Corrective Actions:Pipe Spools Inspected & Tagged & Formal QA Surveillances of Cleanliness Control Will Be Performed on Monthly Basis
ML20237J795
Person / Time
Site: Comanche Peak, 05000000
Issue date: 07/28/1978
From: Gary R
TEXAS UTILITIES ELECTRIC CO. (TU ELECTRIC)
To: Seidle W
NRC OFFICE OF INSPECTION & ENFORCEMENT (IE REGION IV)
Shared Package
ML20237J513 List:
References
FOIA-87-428 TXX-2866, NUDOCS 8708180347
Download: ML20237J795 (3)


Text

_ _ _ _ - . - - -

l c,: 3,

,, s;' .

TEXAS UTII.lTIES GENERATING CO.TIPANY  !

m.,i ii.nm ,u m . i, s u. nmor,m.,

. :+.

e July 28, 1978

, y ,y TXX-2866

. 4 L L*l " ?.:::'

Mr. W. C. Seidle

~ Reactor Construction and

/' Engineering Support Branch j

U. S. Nuclear Regulatory Commission Office of Inspection & [.nforcement

' 611'Ryan Plaza Dr., Suite 1000 Docket Nos. 50-445/Rpt. 78-11 Arlington, Texas 76011 50-446/Rpt. 78-11 COMANCHE PEAK STEAM ELECTRIC STATION 1981-83 2300 MW INSTALLATION-RESPONSE TO NRC i

INSPECTION REPORT NO. 78-11 DOCKET NOS. 50-445 & 50-446 FILE NO. 10130

Dear Mr. Seidle:

We have reviewed the report on the' inspection conducted by Mr. 'l R. G.'

Taylor (June 20-23,1978) of the activities authorized by O NRC PeakConstruction facility. WePermit Nos. CPPR-126 and 127 for the Comanche have responded to the findings listed in

- AppendixA of your " Inspection Report" dated June 30, 1978.

To aid in the. understanding of our response, we have repeated the requirement and your finding, followed on the same page by our corrective action.

We believe the attached information 'to be responsive to the Inspector's findings. If you have any questions, please advise.

Very truly yours,

,e -

R.f'J. Gary -

RJG:dla Attachment i

,\

I f

f3 B708180347 870014 PDR FDIA _a WILLI AMB7_--428 , PDR

TXX-2866 Page 2 Response to NRC Inspec tion Report 78-11 NOTICE OF VIOLATION Based on results of the NRC inspection conducted on June 20-23, 1978, it appears that certain of your activities were not conducted in full compliance with Appendix B to 10 CFR 50 as indicated below:

Fai'ure to Follow Piping Installation Procedures Criterion V of Appendix B requires that established instructions, procedures, or drawings be followed for all activities affecting quality.

Brown and Root Instruction 35-1195-PCI-001, " Pipe Department Cleanliness Control Guidelines", requires that each pipe spool, after being welded to previously comp'-ted niping runs, be examined by a pipe fitter foreman for cleariliness, capped, taped with red tape and tagged.

Contrary to the above:

The inspector observed on June 21 and June 22, 1978, that the i

unwelded ends of four pipe spools in the lower two headers of the

" containment spray system were capped but not taped or tagged as required.

This is an infraction.

Corrective Steps Which Have Been Taken and Results Achieved:

Beginning on June 26, 1978, a complete review of all pipe spools, valves and vessels in the field was initiated by Quality Control to ascertain compliance with the requirements of PCI-001. Items not protected and tagged as required were corrected by responsible craft personnel.

Results of the Quality Control efforts and a formal QA surveillance conducted on July 20, 1978 indicated the need for stronger controls on the part of construction management. This was initiated on July 21, and completed on July 25, 1978. Informal surveillance of selected areas on July 26, 1978, indicate that the management efforts have been effective and that spools, valves, and vessels are now being maintained in a manner consistent with the project requirements.

1 i

'*J 1

.TXX-2866

, Page 3 Response to NRC Inspection Report 78-11 Corrective Steps Which Have Been or Will Be Taken to Avoid Further Noncompliance All QC inspection personnel and pipe department foremen and general foremen have been administered detailed instruction as to the require-ments of pCI-001.

Additiot. ally, pipe department foremen were directed to instruct all pipe department craftspeople in their respective areas as to the requirements of PCI-001.

Effective July 25, 1978, formal QA surveillance will be performed on a minimum monthly frequency to verify that the established " Cleanliness Control" requirements are being maintained. Appropriate management ac-tion will be taken as necessary to maintain compliance with the project requirements.

Date of Full Compliance Corrective action was initiated immediately following the inspection and full compliance was achieved on July 25, 1978.

)

l 1

i l

l l l

l l

J