- ML20235B265 + (07:49:37, 23 May 2025)
- ML20235B232 + (07:49:43, 23 May 2025)
- ML20235B223 + (07:49:45, 23 May 2025)
- ML20235B217 + (07:49:48, 23 May 2025)
- ML20235B138 + (07:50:02, 23 May 2025)
- ML20235B067 + (07:50:32, 23 May 2025)
- ML20235B040 + (07:50:37, 23 May 2025)
- ML20235B012 + (07:50:42, 23 May 2025)
- ML20235A991 + (07:50:47, 23 May 2025)
- ML20235A978 + (07:50:50, 23 May 2025)
- IR 05000293/1988036 + (07:50:52, 23 May 2025)
- 05000382/LER-1987-017, :on 870601,diesel Fuel Oil Analysis Results Not Received within Required Time.Caused by Personnel Transfer at Contract Lab.Individual Responsible for Analysis Not Aware of 7-day Reporting Requirement + (07:50:59, 23 May 2025)
- ML20235A939 + (07:51:02, 23 May 2025)
- ML20235A891 + (07:51:12, 23 May 2025)
- TAC:64655 + (07:51:13, 23 May 2025)
- ML20235A863 + (07:51:21, 23 May 2025)
- 05000271/LER-1987-011, :During 870818 & 20,requirements of Tech Spec 3.5.H.4 for Min Subsystems Required for Refueling Not Satisfied.Caused by Procedural Error.Required Equipment During Refueling & Operation Clarified + (07:51:24, 23 May 2025)
- ML20235A816 + (07:51:45, 23 May 2025)
- 05000483/LER-1987-011, :on 870605,ESF Switchgear Rooms Halon Sys Rendered Inoperable W/O Continuous Firewatch.Caused by Cognitive Util Personnel Errors.Work Authorizing Documents Rescheduled + (07:51:50, 23 May 2025)
- ML20235A786 + (07:51:53, 23 May 2025)
- TXX-8803, Interim Deficiency Rept CP-87-130 Re Svc Water Sys Water Hammer.Initially Reported on 871207.Vacuum Breakers Will Be Installed in Emergency Diesel Generator Jacket Water Coolers.Next Rept Will Be Submitted by 880215 + (07:51:57, 23 May 2025)
- TXX-8804, Interim Deficiency Rept CP-87-72 Re Improperly Defined Weld Lengths.Initially Reported on 870824.Evaluation of Issue Continuing.Next Rept Will Be Provided No Later than 880211 + (07:51:59, 23 May 2025)
- ML20235A746 + (07:52:04, 23 May 2025)
- TXX-8801, Interim Deficiency Rept CP-87-127 Re Overstressed Platforms & Supports.Initially Reported on 871207.Seismic Category I & II Platforms/Supports Exceeding Stress Limits Redesigned. Schedule for Corrective Actions Will Be Provided by 880331 + (07:52:12, 23 May 2025)
- 05000373/LER-1987-024-01, :on 870602,control Room HVAC a Ammonia Detector OXY-VC125YB Tripped.Caused by Tape Breakage in Chemcassette Assembly.Chemcassette Tape Adjusted by Instrument Technician & Detector Returned to Operable svc.W/870701 + (07:52:15, 23 May 2025)
- ML20235A671 + (07:52:22, 23 May 2025)
- ML20235A570 + (07:52:43, 23 May 2025)
- TXX-8805, Interim Deficiency Rept CP-86-45 Re Interaction of Seismic Category II Sys & Components W/Seismic Category I Installations.Initially Reported on 871016.Schedule for Corrective Actions Anticipated by 880401 + (07:52:43, 23 May 2025)
- ML20235A423 + (07:53:17, 23 May 2025)
- TXX-8802, Final Deficiency Rept CP-87-121 Re 6.9 kV/480 Volt Transformer Bus Bar Clearance.Initially Reported on 871112. Transformer Vendor Directed to Perform Required Analyses to Demonstrate Seismic Qualification.Next Rept by 880331 + (07:53:45, 23 May 2025)
- ML20235A210 + (07:54:13, 23 May 2025)
- ML20235A149 + (07:54:26, 23 May 2025)
- IR 05000424/1987026 + (07:54:48, 23 May 2025)
- ML20234F570 + (07:55:04, 23 May 2025)
- IR 05000029/1986020 + (07:55:29, 23 May 2025)
- ML20234F354 + (07:56:05, 23 May 2025)
- ML20234F313 + (07:56:20, 23 May 2025)
- ML20234F300 + (07:56:30, 23 May 2025)
- IR 05000160/1987003 + (07:56:33, 23 May 2025)
- ML20234F267 + (07:56:39, 23 May 2025)
- ML20234F216 + (07:56:47, 23 May 2025)
- ML20234F211 + (07:56:49, 23 May 2025)
- ML20234F025 + (07:57:32, 23 May 2025)
- ML20234E994 + (07:57:38, 23 May 2025)
- ML20234E960 + (07:57:49, 23 May 2025)
- IR 07100004/2011014 + (07:57:50, 23 May 2025)
- TXX-8800, Interim Deficiency Rept CP-87-125 Re Svc Water Sys Piping Support in Which Hilti Bolt Failed When Associated Nut Being Tightened to Specified Torque.Initially Reported on 871204. Evaluation Continuing.Next Rept Will Be Submitted by 880328 + (07:57:52, 23 May 2025)
- ML20234E868 + (07:58:12, 23 May 2025)
- ML20234E778 + (07:58:32, 23 May 2025)
- IR 05000029/1987016 + (07:58:57, 23 May 2025)
- IR 05000219/1987016 + (07:59:07, 23 May 2025)