ML19238A341 | 11 October 2019 | Documentation of the Completion of Required Actions Taken in Response to the Lessons Learned from the Fukushima Dai-Ichi Accident - Supplemental Information |
ML17346A361 | 6 March 2018 | Issuance of Amendment Nos. 224 and 211 to Adopt Changes to the Emergency Plan |
ML17303B162 | 21 December 2017 | Documentation of the Completion of Required Actions Taken in Response to Fukushima Lessons Learned |
L-PI-17-035, License Amendment Request to Revise the Emergency Action Level (EAL) Scheme - Supplement and Response to Requests for Additional Information | 27 September 2017 | License Amendment Request to Revise the Emergency Action Level (EAL) Scheme - Supplement and Response to Requests for Additional Information |
IR 05000282/2017005 | 28 August 2017 | Updated Inspection Plan (Report 05000282/2017005 and 05000306/2017005) |
IR 05000282/2017007 | 9 August 2017 | NRC Temporary Instruction 2515/191, Mitigation Strategies, Spent Fuel Pool Instrumentation and Emergency Preparedness Inspection Report 05000282/2017007; 05000306/2017007 |
ML17110A275 | 4 May 2017 | Safety Evaluation Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 |
ML17094A576 | 29 March 2017 | License Amendment Request to Revise Emergency Action Level (EAL) Scheme |
L-PI-16-096, Notification of Full Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. | 13 December 2016 | Notification of Full Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. |
IR 05000282/2016005 | 31 August 2016 | Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2016005; 05000306/2016005) |
L-PI-16-063, Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events | 17 August 2016 | Seventh Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events |
IR 05000282/2015006 | 2 March 2016 | Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Inspection Report 05000282/2015006 and 05000306/2015006) |
ML16014A754 | 14 January 2016 | Notification of Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. |
ML16014A755 | 14 January 2016 | Enclosure 1, Compliance with NRC Order EA-12-049, Order Modifying Licenses with Regard to Requirements for Mitigation Strategies for Beyond-Design-Basis External Events. |
L-PI-16-001, Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report | 14 January 2016 | Enclosure 2: Responses to Open and Pending Items from the NRC Audit Report |
L-PI-15-099, Completion of Required Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation | 8 December 2015 | Completion of Required Action by NRC Order EA-12-051, Reliable Spent Fuel Pool Instrumentation |
IR 05000282/2015005 | 1 September 2015 | Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 (Report 05000282/2015005; 05000306/2015005) |
L-PI-15-064, Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation | 25 August 2015 | Fifth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation |
ML15224B396 | 20 August 2015 | Report for the Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Order EA-12-049 and EA-12-051 |
ML15083A415 | 31 March 2015 | Plan for the Onsite Audit Regarding Implementation of Mitigating Strategies and Reliable Spent Fuel Pool Instrumentation Related to Orders EA-12-049 and EA-12-051 |
IR 05000282/2014001 | 4 March 2015 | Annual Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2, (Report 05000282/2014001 and 05000306/2014001) |
L-PI-15-022, Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 26 February 2015 | Fourth Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
ML14245A201 | 2 September 2014 | Mid-Cycle Assessment Letter for Prairie Island Nuclear Generating Plant, Units 1 and 2 |
ML14245A386 | 29 August 2014 | NRDC V. NRC Et. Al., No. 13-1311 (Scheduled Oral Argument November. 21, 2014) |
L-PI-14-079, Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 25 August 2014 | Third Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
ML14083A620 | 26 March 2014 | Nuclear Regulatory Commission Audits of Licensee Responses to Reliable Spent Fuel Pool Instrumentation Order EA-12-051 |
L-PI-14-017, Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 26 February 2014 | Second Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
ML13311A486 | 14 November 2013 | Interim Staff Evaluation and Request for Additional Information Regarding the Overall Integrated Plan for Implementation of Order EA-12-051, Reliable Spent Fuel Pool Instrumentation |
ML13205A120 | 7 November 2013 | Draft Environmental Assessment for the Proposed Renewal of the Prairie Island Independent Spent Fuel Storage Installation |
L-PI-13-081, Prairie Island'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation | 26 August 2013 | Prairie Island'S First Six-Month Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation |
L-PI-13-077, Responses to Requests for Additional Information Regarding Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool... | 6 August 2013 | Responses to Requests for Additional Information Regarding Overall Integrated Plan Submitted in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool... |
ML13205A355 | 11 July 2013 | NRR E-mail Capture - Prairie Island Units 1 and 2 - Draft RAI OIP for Reliable SFP Instrumentation |
ML13060A363 | 26 February 2013 | Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
L-PI-13-006, Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 26 February 2013 | Overall Integrated Plan in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
L-PI-12-093, Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 29 October 2012 | Initial Status Report in Response to March 12, 2012 Commission Order Modifying Licenses with Regard to Requirements for Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
L-PI-12-021, Prairie Lsland Nuclear Generating Plant, Answer to March 12, 2012 Commission Order Modifying License with Regarding to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) | 30 March 2012 | Prairie Lsland Nuclear Generating Plant, Answer to March 12, 2012 Commission Order Modifying License with Regarding to Reliable Spent Fuel Pool Instrumentation (Order Number EA-12-051) |
ML12056A044 | 12 March 2012 | Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status |
NRC-2012-0067, Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status | 12 March 2012 | Order Modifying Licenses with Regard to Reliable Spent Fuel Pool Instrumentation (Effective Immediately) - to All Power Reactor Licensees and Holders of Construction Permits in Active or Deferred Status |
ML12054A679 | 12 March 2012 | Issuance of Order to Modify Licenses with Regard to Reliable Spent Fuel Pool Instrumentation |
ML20135A945 | 28 February 1997 | Spent Fuel Pool Dilution Analysis |