ML02045070111 February 2002NRC/NRR/DLPM/LPD2
Padovan L
Unit - Request for Additional Information Re Tritium Production Program Interface Issue 7RAI
ML02058008219 February 2002Tennessee Valley Authority
Pace P
Response to Request for Additional Information Re Tritium Production - Holtec Analysis. Submits New non-proprietary Version (Revision 3) of Holtec International Report HI-2012620Response to RAI
ML02058061221 February 2002NRC/NRR/DLPM/LPD2
Padovan L
License Amendment, FSAR Change for Revised Spent Fuel Cooling Analysis Methodology - TAC Nos. MB1807 and MB1884Other
ML02058000521 February 2002Tennessee Valley Authority
Pace P
Responses to RAI Regarding Tritium Producing Burnable Absorber Rods (TPBARS)Response to RAI
ML02058043021 February 2002Tennessee Valley Authority
Pace P
Tennessee Valley Authority Response to NRC Request for Additional Information Re Tritium Producing Burnable Absorber Rods (TPBARS) at Watts Bar Nuclear PlantResponse to RAI
ML0210003615 April 2002Tennessee Valley Authority
Pace P
Response to Request for Additional Information Re Tritium Production - Interface Issue Number 2 - Procurement and Fabrication IssuesResponse to RAI
ML02119055725 April 2002NRC/NRR/DLPM
Padovan L
Second Request for Additional Information Tritium Production Program Interface Issue 7RAI
ML0212806308 May 2002NRC/NRR/DLPM/LPD2
Padovan L
Request for Additional Information Re Tritium Production Program Interface Issue 5RAI
ML02144015221 May 2002Tennessee Valley Authority
Pace P
Mays R
Request for Additional Information Regarding Tritium Production - Interface Issue Number 7 Light Load Handling SystemsRequest
ML02144014221 May 2002Tennessee Valley Authority
Pace P
Request for Additional Information Re Tritium Production - Interface Issue Number 7 - Light Load Handling SystemsRequest
ML02144013521 May 2002Tennessee Valley Authority
Pace P
Request for Additional Information Re Tritium Production - Interface Issue Number 5 - Control Room Habitability SystemsRequest
ML02149013923 May 2002Tennessee Valley Authority
Pace P
Response to Request for Additional Information Re Radiological ImpactResponse to RAI
ML02210044929 July 2002NRC/NRR/DLPM/LPD2
Padovan L
Request for Additional Information Tritium Production ProgramRAI
ML02214019730 July 2002Tennessee Valley Authority
Pace P
Tritium Production -- Post-LOCA Hot Leg Emergency Core Cooling System (ECCS) Recirculation Time -- Supplemental InformationSupplement
ML0222601529 August 2002Tennessee Valley Authority
Burzynski M
Request for Risk-Informed Information Tritium Production ProgramRequest
ML0831800949 August 2002Tennessee Valley Authority
Burzynski M
Plants - Request for Risk-Informed Information Tritium Production ProgramRequest
ML02232090520 August 2002NRC/NRR/DLPM/LPD2
Padovan L
Environmental Assessment and Finding of No Significant Impact for Incore Irradiation Services for the U. S. Department of Energy'S Tritium Production ProgramOther
ML02254092523 September 2002NRC/NRR/DLPM/LPD2
Padovan L
Amendment No. 40, Irridiate Up to 2304 Tritium-Producing Burnable Absorber Rods in the Reactor CoreAcceptance Review
ML02275029523 September 2002NRC/NRR/DLPM/LPD2
Padovan L
Technical Specification Pages for Amendment No. 40, Irradiated Up to 2304 Tritium Producing Burnable Absborber Rods in the Reactor CoreOther
ML07352054618 January 2008Moroney B
NRC/NRR/ADRO/DORL/LPLII-2
Issuance of License Amendment 67 Regarding the Maximum Number of Tritium Producing Burnable Assembly Rods in the Reactor CoreApproval
ML08022037818 January 2008NRC/NRR/ADRO/DORL/LPLII-2Tech Spec Pages for Amendment 67 Regarding the Maximum Number of Tritium Producing Burnable Assembly Rods in the Reactor CoreOther
ML08218009431 July 2008Westinghouse
Gergos B
WCAP-16932-NP, Rev. 1, Control Rod Insertion Following a Cold Leg LOCA for Watts Bar Unit 1.Request
ML0821800931 August 2008Tennessee Valley Authority
Brandon M
Watt'S Bar, Unit 1, Technical Specifications Change - Revision of Boron Requirements for Cold Leg Accumulators and Refueling Water Storage Tank.Request
ML0827502136 October 2008John Lamb
Watts Bar Special Projects Branch
Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Unit 1 (Tac No. MD9396)Withholding Request Acceptance
ML08283144714 October 2008John Lamb
Watts Bar Special Projects Branch
Request for Additional Information Regarding Analysis in Support of Control Rod Insertion Following a Cold Leg Loss-of -Coolant Accident (Tac MD9396)RAI
ML08294017028 October 2008John Lamb
Watts Bar Special Projects Branch
Request for Additional Information - Watts Bar Emergency Core Cooling System Boron RequirementsRAI
ML0830401047 November 2008John Lamb
Watts Bar Special Projects Branch
Request for Additional Information - Watts Bar Emergency Core Cooling System Boron RequirementsRAI
ML08336019125 November 2008Tennessee Valley Authority
Riedl C
Response to Request for Additional Information Analysis in Support of Control Rod Insertion Following a Cold Leg Loss-of-Coolant AccidentResponse to RAI
ML0834303049 December 2008John Lamb
Watts Bar Special Projects Branch
Potential Schedule Impact Regarding Revision of Technical Specifications, Revision of Boron Requirements for Cold Leg Accumulators and Refueling Water Storage Tank.Other
ML08351010219 December 2008John Lamb
Watts Bar Special Projects Branch
Withdrawal of Questions Number 6 from Letter Dated October 28, 2008, Regarding Proposed Amendment to Revise Technical Specifications for Boron Requirements for the Cold Leg Accumulations and Refueling Water Storage TankWithdrawal
ML09022025531 December 2008Tennessee Valley Authority
Brandon M
Response to Request for Additional Information Emergency Core Cooling System Boron RequirementsResponse to RAI
ML09009004431 December 2008Tennessee Valley Authority
Riedl C
Revised Technical Specifications Change WBN-TS-08-04 - Revision to the Maximum Number of TPBARS That Can Be Irradiated in the Reactor Core Per CycleOther
ML0933507405 January 2009Raghavan L
Watts Bar Special Projects Branch
Request for Information Regarding the Tritium Producing Burnable Absorber Rods (Tac No. ME2775)RAI
ML09006004026 January 2009John Lamb
Watts Bar Special Projects Branch
Request for Withholding Information from Public Disclosure for Watts Bar Nuclear Plant, Unit 1Withholding Request Acceptance
ML0909205064 May 2009John Lamb
Watts Bar Special Projects Branch
Issuance of Amendment Regarding the Maximum Number of Tritium Producing Burnable Assembly Rods in the Reactor CoreApproval
ML1004703209 February 2010Tennessee Valley Authority
Rod Krich
Clarification Regarding the Number of Tritium Producing Burnable Absorber Rods in Operating Cycle 10 and Program UpdateOther
CNL-14-053, Notification of the Number of Tritium Producing Burnable Absorber Rods for the Operating Cycle 13 Reactor Core8 April 2014Tennessee Valley Authority
James Shea
Notification of the Number of Tritium Producing Burnable Absorber Rods for the Operating Cycle 13 Reactor CoreOther
ML15030A50830 January 2015Tennessee Valley Authority
James Shea
Tritium Production Program, Updated Plans for Cycle 13 Operation and Updated Evaluation of the Radiological Impacts of Tritium Permeation Into the Reactor Coolant SystemOther