ML07255006330 August 2007Progress Energy Carolinas
Holder A
NFPA 805 Transition Pilot Plant FAQ 06-0019, Revision 2Request
ML0730605507 September 2007Duke EnergyNFPA 805 Transition Pilot Plant FAQ 07-0040Request
ML07274026220 September 2007Progress Energy Carolinas
Began K
NFPA-805 Transition Pilot Plant FAQ 07-0038Request
ML07274024820 September 2007Engineering Planning & Management
Jutras T H
NFPA-805 Transition Pilot Plant FAQ 06-0011, Revision 2Request
ML07274026820 September 2007Progress Energy Carolinas
Ratchford A
NFPA-805 Transition Pilot Plant FAQ 07-0039Request
ML07274025528 September 2007Progress Energy Carolinas
Holder A
NFPA-805 Transition Pilot Plant FAQ 06-0019, Revision 3Request
ML07355002312 November 2007Progress Energy Carolinas
Holder A
NFPA 805 Transition Pilot Plant FAQ 07-0033, Revision 1Request
ML07351008212 November 2007Progress Energy CarolinasNFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 3 (Corrected Version)Request
ML07332002826 November 2007Progress Energy Carolinas
Kleinsorg E
NFPA 805 Transition Pilot Plant FAQ 06-0012, Revision 5, Determining Manual Actions That Require a Change Evaluation During Transition.Request
ML0733700253 December 2007Progress Energy Carolinas
Ertman J
NFPA 805 Transition Pilot Plant FAQ 06-0008, Revision 8, Alternative Method for Fire Protection Engineering AnalysesRequest
ML0734001476 December 2007Progress Energy Carolinas
Holder A
NFPA 805 Transition Pilot Plant FAQ 06-0025, Revision 3Request
ML07355002520 December 2007Progress Energy Carolinas
Holder A
NFPA 805 Transition Pilot Plant FAQ 07-0036, Revision 1Request
ML07354026220 December 2007Electric Power Research Institute
Funk D
NRC/RES/DRA/FRB
Js Hyslop
Joglar F
Kazarians M
Nowlen S
Najafi B
Wyant F
Afpb Staff Response to NFPA 805 Transition Pilot Plant FAQ 07-0035, Revision 0Request
ML08070041110 March 2008Progress Energy Carolinas
Holder A
NFPA 805 Transition Pilot Plant FAQ 07-0032, Revision 1, Clarification of 10 CFR 50.48(c), 50.48(a), and GDC 3.Request
ML08091013628 March 2008- No Known Affiliation
Ratchford A
NFPA 805 Transition Pilot Plant FAQ 07-0039, Revision 1, Lessons Learned - NEI 04-02 B-2 and B-3 TablesRequest
ML08143004122 May 2008Duke Energy
Goforth D
NFPA 805 Transition Pilot Plant FAQ 07-0040, Revision 2Request
HNP-08-061, Request for License Amendment to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)29 May 2008Progress Energy Co
Duncan R
Request for License Amendment to Adopt NFPA 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)Request
ML08204101430 May 2008Duke Energy
Rosalyn Jones
Public Version of Enclosures 2 Through 6 of License Amendment Request to Adopt NFPA-805Request
ML08169012117 June 2008Vaaler M
NRC/NRR/ADRO/DORL/LPLII-1
Forthcoming Closed Meeting with Progress Energy Carolinas, Inc., to Discuss the May 29, 2008, License Amendment Request (LAR) to Transition the Shearon Harris Nuclear Plant, Unit 1 (Harris) to National Fire Protection Association (Nfpa)..Meeting
ML0818406967 July 2008Vaaler M
NRC/NRR/ADRO/DORL/LPLII-1
Meeting with Progress Energy Carolinas, Inc. and Duke Energy Carolinas, LLC, to Discuss the 05/29&30/2008, License Amendment Requests to Transition Shearon Harris, Unit 1, and Oconee, Units 1, 2, & 3 to NFPA Standard 805Meeting
ML08189052911 July 2008Vaaler M
NRC/NRR/ADRO/DORL/LPLII-2
Summary of Closed Meeting with Progress Energy Carolinas Regarding May 29, 2008, License Amendment Request to Transition the Shearon Harris Nuclear Plant Unit 1, to National Fire Protection Association Standard 805, Performance-Based....Meeting
ML08207039117 July 2008Duke Energy
Office of Nuclear Reactor Regulation
Meeting Handouts from 7/17/08 Public Meeting on the Harris and Oconee LARs to Transition to NFPA-805Meeting
ML0820605367 August 2008Vaaler M
NRC/NRR/ADRO/DORL/LPLII-2
Summary of Mtg. with Progress Energy Carolinas, and Duke Energy Carolinas to Discuss the LARs to Transition the Shearon Harris and Oconee Nuclear Plants to National Fire Protection Association Standard NFPA-805Acceptance Review
ML08287001626 September 2008Runkle J
North Carolina Waste Awareness & Reduction Network (NC WARN)
Nc Warn'S Response to Board Notification - Enclosure P-1 - Shearon Harris Nuclear Power Plant, Unit 1 - Acceptance Review NFPA-805 License Amendment Request, September 26, 2008Request
ML08270115826 September 2008Boyce T
Plant Licensing Branch II
Acceptance Review Regarding the License Amendment Request to Transition to NFPA 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants.Acceptance Review
ML08309007412 November 2008NRC/NRR/DRA/AFPB
Plant Licensing Branch II
Olshan L
Stambaugh M
Summary of Category 2 Public Meeting Held to Discuss National Fire Protection Association Standard 805 Pilot Plant Process: Current Lessons Learned from the Pilot License Amendment Request Reviews (TAC Nos. MD8807, MD8832, MD8833, & MD8834)Meeting
HNP-08-113, Supplement to Request for License Amendment, to Adopt NFPA 805 Performance-Based Standards for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)14 November 2008Progress Energy Carolinas
Progress Energy Co
Burton C
Supplement to Request for License Amendment, to Adopt NFPA 805 Performance-Based Standards for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)Supplement
ML08296015317 November 2008Ellen Brown
Plant Licensing Branch II
Summary of Meeting with Progress Energy Carolinas, Inc., to Discuss Shearon Harris Unit 1 National Fire Protection Association Standard 805 License Amendment RequestMeeting
HNP-08-121, Supplement 2 to Request for License Amendment to Adopt NFPA 805 Performance-based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)11 December 2008Progress Energy Carolinas
Progress Energy Co
Harshaw K
Supplement 2 to Request for License Amendment to Adopt NFPA 805 Performance-based Standard for Fire Protection for Light Water Reactor Generating Plants (2001 Edition)Supplement
ML09030003030 January 2009Vaaler M
Plant Licensing Branch II
Acceptance Review Regarding Amendment to Adopt National Fire Protection Association 805 Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants, 2001 EditionAcceptance Review
ML09029032710 March 2009Vaaler M
Plant Licensing Branch II
Regulatory Audit in Support of the License Amendment Request to Implement a Risk-Informed, Performance-Based Fire Protection Program as Allowed by Title 10 of the Code of Federal Regulations, Paragraph 50.48(c) Fire ProtectionOther
ML09099001810 April 2009Vaaler M
Plant Licensing Branch II
04/21-22/2009, Notice of Meeting with Progress Energy Carolinas, Inc., and Duke Energy Carolinas, LLC, to Discuss Topics Involving the License Amendment Requests to Transition the Shearon, Unit 1 and the Oconee, Units 1, 2 and 3Meeting
ML09160028111 June 2009Vaaler M
Plant Licensing Branch II
Notice of Consideration of Issuance of Amendment to Facility Operating License and Opportunity for a HearingOther
ML0921707156 August 2009Vaaler M
Plant Licensing Branch II
Request for Additional Information Regarding Amendment to Adopt National Fire Protection Association Standard 805 (NFPA 805), Performance-Based Standard for Fire Protection for Light Water Reactor ...RAI
HNP-09-084, Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Generating Plants.13 August 2009Progress Energy Carolinas
Burton C
Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Generating Plants.Response to RAI
HNP-09-086, Second Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Reactor...28 August 2009Progress Energy Carolinas
Burton C
Second Response to Request for Additional Information Regarding License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-based Standard for Fire Protection for Light Water Reactor...Response to RAI
HNP-09-094, Third Response to Request for Additional Information License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor....9 October 2009Progress Energy Carolinas
Burton C
Third Response to Request for Additional Information License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor....Response to RAI
HNP-09-096, Additional Information Re License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants16 December 2009Progress Energy Carolinas
Burton C
Additional Information Re License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating PlantsRequest
ML10013025414 January 2010Vaaler M
Plant Licensing Branch II
Second Request for Additional Information Regarding the License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating PlantRAI
HNP-10-008, Response to Second Request for Additional Information Regarding License Amendment Request to Anfp Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants.4 February 2010Progress Energy Carolinas
Burton C
Response to Second Request for Additional Information Regarding License Amendment Request to Anfp Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants.Request
ML1006009879 March 2010Vaaler M
Plant Licensing Branch II
Discussion of Clarification Questions Related to the License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance - Based Standard for Fire Protection for Light ...Other
HNP-10-040, Response to 3rd Round of RAI License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants.5 April 2010Progress Energy Carolinas
Warner J
Response to 3rd Round of RAI License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Generating Plants.Request
HNP-10-064, Additional Items Related to License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants.9 June 2010Progress Energy Carolinas
Burton C
Additional Items Related to License Amendment Request to Adopt National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for LWR Generating Plants.Request
ML10175060428 June 2010Vaaler M
Plant Licensing Branch II
Redacted - Regarding Adoption of National Fire Protection Association Standard 805Acceptance Review
ML10175060228 June 2010Vaaler M
Plant Licensing Branch II
Issuance of Amendment Regarding Adoption of National Fire Protection Association Standard 805, Performance-Based Standard for Fire Protection for Light Water Reactor Electric Generating Plants..Approval
ML10251085228 December 2010Vaaler M
Mozafari B
Plant Licensing Branch II
Corrections of Typographical and Formatting Errors Regarding Amendment No. 133 and the Associated Safety EvaluationApproval