Semantic search
Jump to navigation
Jump to search
Issue date | Title | Topic | |
---|---|---|---|
ML20206D341 | 31 December 1999 | Suppl Technical Evaluation Rept Based on Review of Addl Responses & Site Audit of Individual Plant Exam of External Events at Susquehanna Steam Electric Station,Units 1 & 2 | Safe Shutdown Fire Barrier Probabilistic Risk Assessment Earthquake |
ML17164A690 | 31 July 1998 | Site Audit Rept for Step 2 Review of IPEEE at Susquehanna Steam Electric Station Units 1 & 2. Site Audit Plan, Jul 1998 | Safe Shutdown Fire Barrier Earthquake |
ML18026A293 | 28 February 1998 | Technical Evaluation Rept on Submittal Only Review of IPEEE at Susquehanna Steam Electric Station Units 1 & 2. Final Rept,Feb 1998 | Hot Short Safe Shutdown High winds Fire Barrier Safe Shutdown Earthquake Internal Flooding Probabilistic Risk Assessment Operating Basis Earthquake Tornado-Generated Missile Seismically rugged Earthquake Scaffolding |
ML20212F192 | 31 March 1997 | Rev 1 to, Review & Evaluation of PP&L Fire Protection Review Rept,Rev 4 Susquehanna Steam Electric Station Safe Shutdown Capability-10CFR50,App R, 'Post-Fire Safe Shutdown Methodology & Analysis of Associated Circuits.' | Hot Short Safe Shutdown Reactor Vessel Water Level Ultimate heat sink Fire Barrier Emergency Lighting Fire Protection Program Coast down |
ML18026A274 | 31 October 1995 | Technical Evaluation Rept on Second 10-Yr ISI Program Plan for Units 1 & 2. | Boric Acid Weld Overlay Hydrostatic Nondestructive Examination VT-2 Incorporated by reference Intergranular Stress Corrosion Cracking Pressure Boundary Leakage Pressure boundary leak |
ML20080L686 | 28 February 1995 | Technical Evaluation Rept:Pp&L,Susquehanna Steam Electric Station,Pump & Valve Inservice Testing Program,Rev 10,Unit 1 Second 10-Yr Interval,Rev 7,Unit 2 Second 10-Yr Interval | High Radiation Area Stroke time Local Leak Rate Testing Scram Discharge Volume Excess Flow Check Valve Cold shutdown justification Power-Operated Valves Water hammer |
ML20091J115 | 1 October 1991 | Final Technical Evaluation Rept,Susquehanna Steam Electric Station Units 1 & 2,Station Blackout Evaluation | Safe Shutdown |
ML20082Q827 | 31 August 1991 | Evaluation of 9 by 9 Fuel Impact on Stability of Susquehanna-2 at End of Cycle 4 | |
ML18040B261 | 31 October 1989 | Technical Evaluation Rept on Response from Pennsylvania Power & Light to Generic Ltr 88-01 Pertaining to Susquehanna Steam Electric Station Unit 2, Final Rept | Weld Overlay Intergranular Stress Corrosion Cracking Unidentified leakage |
ML18040A946 | 30 September 1989 | Conformance to Generic Ltr 83-28,Item 2.2.1 - Equipment Classification for All Other Safety-Related Components: Susquehanna-1/-2, Final Technical Evaluation Rept | |
ML20245F047 | 22 June 1989 | Fire Protection Review Rept Evaluation | Safe Shutdown High Radiation Area Fire Barrier Emergency Lighting Fire Protection Program |
ML18040A925 | 31 December 1988 | Conformance to Generic Ltr 83-28,Item 2.1 (Part 2),Reactor Trip Sys Vendor Interface,Susquehanna Steam Electric Station Units 1 & 2, Technical Evaluation Rept.Salp Input Also Encl | Systematic Assessment of Licensee Performance |
ML18040A922 | 31 December 1988 | Conformance to Generic Ltr 83-28,Item 4.5.2,Susquehanna Steam Electric Station Units 1 & 2, Technical Evaluation Rept | Systematic Assessment of Licensee Performance |
ML18040B189 | 31 August 1987 | Selected Operating Reactors Issues:Stability Calculations for Grand Gulf 1 & Susquehanna 2 Bwrs. | |
ML20235V152 | 31 August 1987 | Technical Evaluation Rept,Reactor Trip Sys Reliability Conformance to Item 4.5.2 of Generic Ltr 83-28,Peach Bottom 2 & 3,Perry 1 & 2,Pilgrim 1,Quad Cities 1 & 2,River Bend 1, Shoreham,Susquehanna 1 & 2,Vermont Yankee & WNP-2 | |
ML18040B167 | 30 November 1986 | First Interval Inservice Insp Program,Susquehanna Steam Electric Station Unit 2, Technical Evaluation Rept | Hydrostatic VT-2 Incorporated by reference Intergranular Stress Corrosion Cracking Dissimilar Metal Weld |
ML20211K477 | 30 November 1986 | First Interval Inservice Insp Program,Susquehanna Steam Electric Station Unit 1, Technical Evaluation Rept | Hydrostatic Nondestructive Examination VT-2 Incorporated by reference Intergranular Stress Corrosion Cracking Dissimilar Metal Weld |
ML20138B573 | 30 September 1985 | Conformance to Generic Ltr 83-28,Items 3.1.3 & 3.2.3 for Susquehanna Steam Electric Station Unit 2 | |
ML20137E693 | 30 June 1985 | Conformance to Generic Ltr 83-28,Items 3.1.3 & 3.2.3, Susquehanna Steam Electric Station Unit 1 | |
ML20093C533 | 30 March 1984 | Audit of Susquehanna Unit 2 Tech Specs, Technical Evaluation Rept | Reactor Vessel Water Level Half scram Stroke time Hydrostatic Anchor Darling Local Leak Rate Testing Excess Flow Check Valve Backfit |
ML18040B039 | 25 January 1984 | Evaluation of Detailed Control Room Design Review for Susquehanna Steam Electric Station, Technical Evaluation Rept | |
ML18040A717 | 30 September 1983 | Conformance to Reg Guide 1.97,Susquehanna Steam Electric Station,Units 1 & 2. | Post Accident Monitoring Fuel cladding |
ML18040B030 | 30 September 1983 | Control of Heavy Loads at Nuclear Power Plants,Susquehanna Steam Electric Station,Unit 2 (Phase I), Draft Technical Evaluation Rept | Safe Shutdown Control of Heavy Loads |
ML20024A604 | 30 April 1983 | Control of Heavy Loads at Nuclear Power Plants, Susquehanna Steam Electric Station,Unit 1,(Phase I). | Safe Shutdown Control of Heavy Loads |
ML20058A741 | 31 May 1982 | Audit of Environ Qualification of Safety-Related Electrical Equipment at Susquehanna Steam Electric Station, Interim Rept | |
ML20126M780 | 22 May 1981 | Contract:Environ Assessment of Low Level Waste Storage at PA Power & Light Co - Susquehanna Steam Electric Station, Awarded to Science Applications,Inc | |
ML20126M777 | 22 May 1981 | Notification of Contract Execution:Environ Assessment of Low Level Waste Storage at PA Power & Light Co - Susquehanna Steam Electric Station, Awarded to Science Applications, Inc |