ML20129D821 | 23 February 1996 | Technical Evaluation Rept of IPE Submittal & RAI Responses for Davis-Besse Nuclear Power Station | Mission time Internal Flooding Probabilistic Risk Assessment |
ML20071J393 | 30 June 1994 | Technical Evaluation Rept,Evaluation of Util Response to Suppl 1 to NRC Bulletin 90-001, for Plant | |
ML20057E592 | 30 September 1993 | Auxiliary Feedwater System RISK-BASED Inspection Guidance for the DAVIS-BESSE Nuclear Power Plant | |
ML20086F707 | 31 October 1991 | Ter,Pump & Valve Inservice Testing Program,Davis-Besse Nuclear Power Station,Unit 1 | Safe Shutdown Unanalyzed Condition Boric Acid Stroke time Power Operated Valves |
ML20058F869 | 31 October 1990 | PRESSURE-DEPENDENT Fragilities for Piping Components.Pilot Study on Davis-Besse Nuclear Power Station | Hydrostatic Probabilistic Risk Assessment Earthquake |
ML20069N487 | 17 August 1990 | Station Blackout Evaluation, Final Technical Evaluation Rept | Safe Shutdown |
ML20083B549 | 13 July 1990 | Monthly Rept for June 1990 for FIN B-5699, ISLOCA Research Program | Probabilistic Risk Assessment |
ML20083B473 | 16 February 1990 | Assessment of Potential for ISLOCA at Davis-Besse Nuclear Power Station, Draft Rept | |
ML20070Q643 | 31 January 1989 | Nuclear Power Plant Sys Sourcebook,Davis-Besse | Safe Shutdown Boric Acid Ultimate heat sink Emergency Lighting |
ML20245E921 | 31 August 1988 | Technical Evaluation Rept TMI Action-NUREG-0737 (II.D.1) Relief & Safety Valve Testing,Davis-Besse Unit 1 | Loop seal Anticipated operational occurrence Earthquake |
ML20238A946 | 31 August 1987 | DAVIS-BESSE Uncertainty Study | Loop seal |
ML20214R206 | 30 April 1987 | Conformance to Generic Ltr 83-28,Item 2.2.1 -- Equipment Classification for All Other Safety-Related Components: Davis-Besse, Final Informal Rept | Safe Shutdown |
ML20212Q088 | 30 November 1986 | Conformance to Reg Guide 1.97,Davis-Besse Nuclear Power Station,Unit 1, Informal Rept | Boric Acid Grab sample Fuel cladding |
ML20212M276 | 31 July 1986 | Conformance to Generic Ltr 83-28,Item 2.1 (Part 1), Equipment Classification (Reactor Trip Sys Components), Arkansas 1 & 2,Calvert Cliffs 1 & 2,Crystal River 3 & Davis-Besse 1 | |
ML20210C166 | 7 March 1986 | Masonry Wall Design,Davis-Besse Unit 1, Technical Evaluation Rept | |
ML20151L345 | 6 December 1985 | Suppl to Technical Evaluation Rept of Dcrdr for Davis-Besse Nuclear Power Station | |
ML20210K129 | 19 November 1985 | Site Survey of Davis-Besse Maint Program & Practices, Technical Ltr Rept | Temporary Modification Systematic Assessment of Licensee Performance |
ML20244D387 | 10 July 1985 | Review of Licensee & Applicant Responses to NRC Generic Ltr 83-28 (Required Actions Based on Generic Implications of Salem ATWS Events),Item 1.2, `Post-Trip Review:Data & Info Capabilities' for Bellefonte Nuclear Plant. | |
ML20244D438 | 30 June 1985 | Conformance to Generic Ltr 83-28,Items 3.1.3 & 3.2.3, Dresden Units 2 & 3,Millstone Unit 1,Monticello,Pilgrim & Quad Cities Units 1 & 2. Contains Info for Dresden & Quad Cities | |
ML20132D207 | 30 June 1985 | Conformance to Generic Ltr 83-28,Items 3.1.3 & 3.2.3, Davis-Besse Unit 1 | |
ML20127J594 | 14 June 1985 | Preimplementation Audit of Dcrdr of Davis-Besse Nuclear Power Station | |
ML20133P883 | 31 May 1985 | Conformance to Reg Guide 1.97,Davis-Besse Nuclear Power Station,Unit 1 | Boric Acid Grab sample Fuel cladding |
ML20108F444 | 27 November 1984 | Masonry Wall Design,Davis-Besse Nuclear Power Station Unit 1, Technical Evaluation Rept | |
ML20106A654 | 24 September 1984 | Control of Heavy Loads (C-10),Davis-Besse Nuclear Power Station Unit 1, Technical Evaluation Rept | Safe Shutdown Coatings Nondestructive Examination Control of Heavy Loads |
ML20095H063 | 10 July 1984 | Draft Control of Heavy Loads - Phase II,Davis-Besse Nuclear Power Station Unit 1, Technical Evaluation Rept | Safe Shutdown Control of Heavy Loads Fuel cladding |
ML20086N245 | 29 February 1984 | Review of the DAVIS-BESSE Unit No. 1 Auxiliary Feedwater System Reliability Analysis | Time to boil |
ML20077L789 | 9 August 1983 | Control of Heavy Loads (C-10),Toledo Edison Co,Davis-Besse Nuclear Power Station Unit 1, Draft Technical Evaluation Rept | Safe Shutdown Coatings Nondestructive Examination Control of Heavy Loads |
ML20077K845 | 14 March 1983 | Selected Operating Reactor Issues Program Ii,Rcs Vents, (NUREG-0737,Item II.B.1), Final Technical Evaluation Rept | Hot Short |
ML20077K150 | 24 November 1982 | ECCS Repts (F-47),TMI Action Plan Requirements, Davis-Besse Nuclear Power Station,Unit 1, Technical Evaluation Rept | |
ML20071L384 | 31 August 1982 | Improvements in Training & Requalification Programs as Required by TMI Action Items I.A.2.1 & II.B.4 for Davis-Besse Nuclear Power Station, Technical Evaluation Rept | |
ML20027C500 | 27 August 1982 | Control of Heavy Loads (C-10),Toledo Edison Co,Davis-Besse Nuclear Power Station,Unit 1, Draft Technical Evaluation Rept | Safe Shutdown Coatings Nondestructive Examination Control of Heavy Loads |
ML20065S605 | 23 July 1982 | Seismic Qualification of Auxiliary Feedwater Sys, Technical Evaluation Rept | Backfit |
ML20069C592 | 23 June 1982 | PWR Main Steam Line Break W/Continued Feedwater Addition (B-69),Toledo Edison Co,Davis-Besse Nuclear Power Station Unit 1, Technical Evaluation Rept | Boric Acid Shutdown Margin |
ML20064L282 | 10 May 1982 | Auxiliary Feedwater Sys Automatic Initiation & Flow Indication (F-16,F-17) | |
ML20027A775 | 30 April 1982 | Override & Reset of Control Circuitry in Ventilation/Purge Isolation & Other ESF Sys, Technical Evaluation Rept | |
ML20207N438 | 6 April 1982 | Rev 1 to Equipment Environ Qualification Review of Licensee Resolution of Outstanding Issues from NRC Environ Qualification SERs & TMI Action Plan Installed Equipment, Request for Addl Info | |
ML20040G159 | 22 December 1981 | Request for Addl Info Re Equipment Environ Qualification Review of Licensee Resolution of Outstanding Issues from NRC Equipment Environ Qualification Safety Evaluation Repts & TMI Action Plan Installed Equipment. | |
ML20052A068 | 31 May 1981 | Technical Evaluation of Response to Position 5 of Item II.E.4.2 of NUREG-0737,Containment Isolation Setpoint. | |
ML19240C002 | 31 March 1981 | Inservice Testing Program for Pumps & Valves at Davis-Besse Nuclear Power Station - Unit 1 (Docket 50-346) for Period Nov 1977 Through Nov 1987, Safety Evaluation | Stroke time Power Operated Valves |
ML19208B871 | 30 July 1979 | Technical Evaluation Rept Re Alternative to Keylock Control to Bypass Valves.Supports Alternative Procedures | |
ML19329C467 | 17 July 1970 | Review of Seismic Design Criteria for Davis-Besse. | Tornado Generated Missile Earthquake |
ML19329C480 | 31 October 1969 | Seismological & Geological Review. | Design basis earthquake Earthquake |
ML19329C470 | 28 October 1969 | Seismic Review. | Earthquake |