Request for Addl Info Re Equipment Environ Qualification Review of Licensee Resolution of Outstanding Issues from NRC Equipment Environ Qualification Safety Evaluation Repts & TMI Action Plan Installed Equipment
ML20040G159
Person / Time
Site: Davis Besse Cleveland Electric icon.png
Issue date: 12/22/1981
From:
FRANKLIN INSTITUTE
To:
Shared Package
ML20040G155 List:
References
RTR-NUREG-0737, RTR-NUREG-737 IEB-79-01B, IEB-79-1B, NUDOCS 8202110373
Download: ML20040G159 (8)


Text

.

REQUEST FOR ADDITIONAL INFORMATION QUIPMENT E?NIRO?HE?TIAL QUALIFICATION (EM)

REVIEW OF LICENSEES' RESOLUTION OF OUTSTANDING ISSUES FROM NRC EQUIPMENT ENVIRONMENTAL QUALIFICATION SAFETY EVALUATION REPORTS (SER) AND TMI, ACTION PLAN INSTALLED Q UIPME!?f The Toledo Edison Company Davis-Besse Unit 1 NRC Docket No. 50-346 December 22, 1981 NRC TAC No. 42508 1

?

l Please send a copy of cover letter to NRC Project flanager and complete package to FRC.

FRC mailing address is as follows:

Mr. Cyril J,. Crane Franklin Research Center The Parkway at Twentieth Street l

Philadelphia, PA 19103 Telephone No. 215/448-1353 Te?.ecopy No. 215/448-1296 s Telecepy Confirmation No. 215/443-1215 l

I I

l l

i l

. Franidin Research Center l

A Division of The Franklin Institute The Sen,stran Franen Parkmey, PMe., Pa.191C3 (21S) 448 1000 8202110373 820128 PDR ADOCK 05000346 P

PDR

l

.(

BACKGROUND f

Franklin Research Center (FRC) of Philadelphia, Pa. is providing assis-l tance to the U.S. Nuclear Regulatory Commission (NRC) for the equipment

{

environmental qualification (EEQ) review of operating reactors. FRC will perform an EEQ review of the Licensee's 90-day response to outstanding issues l

from the NRC Equipment Environmental Qualification Safety Evaluation Report (SER) and the installed TMI Action Plan equipment. The review will be limited to safety-related equipment potentially exposed to a harsh environment. The results will be presented in the form of a technical evaluation report for each plant.

This request for additional inforn.ation (RFI) is the result of an evaluation of the information provided by letters dated October 12, 1981 [1]

and January 30, 1981 [2].*

FRC REVIEW OF THE LICENSEE'S 90-DAY RESPONSE TO THE NRC EEQ SER Information Requested 1.

In referance to the Licensee's 90-day response [1] to the NRC SER [3], a legible single copy of each of the following qualification documents is requested in order that the FRC evaluation may proceed:

a. Wyle Laboratories Report No. 44354-1

" Qualification Test Report for Four (4)

NEMA 4 Enclosures," March 8, 1979 (for States, Raychem).

b. Rosemount Test Report No. 87414, "Investication Radiation Requirement, Model 177 HW," 8/16/74
  • Numbers in brackets refer to citations found in the list of references.

nklin Research Center A Dnemen ed The Fransen bummme

I

c. Foxboro Company Test Report No. T2-1075,

" Radiation Test of E10 Series Differential Pressure Transmitter of the Standard Construction Type," August,1973.

d. Rosemount Test Report No. 12756B Rev. A, "Rosemount Modified Model 1152 Pressure Transmitter Environmental Class lA Equipment," 12/5/75.
e. NAMCO Qualification Report, " Estimation 1

of Qualified Life of EA740-20000 Rev. C, D, or E, Revised 2/27/80.

f. Microswitch Engineering Report No.

~

LTR-24407, " Preliminary Evaluation of

'LS,'

'HS,'

' CMC,'

'PT, ' and ' Series 2 '

Type Switches Under Electrical Aging, Environmental Aging, and Seismic Vibration Tests."

g. ITT Barton Report No. R3-288A-1, "IEEE 344-1975 Seismic and Radiation Qualification Tests for ITT Barton Differential Pressure Indicating Switches Models 288A and 289A.
h. Summary Report No. QSR 027-A-01, BWR Equipment Qualification Summary, Barton Model 288 Differential Pressure Switch, 10/2/80.
i. ITT General Controls Engineering Report No. 721.77.095 ADDENDUM #2,

" Certification of NH90 Series Actuators For 50*C (122"F) Ambient Temperature and 20,000 hour0 days <br />0 hours <br />0 weeks <br />0 months <br /> Usage at 60% Rated Load,"

5/16/81.

j. ITT General Controls Engineering Report No. 721.77.095 ADDENDUM i5, " Summary of NH90 (Model B) Series Actuator Supplemental Generic Qualification Testing for Class lE Requirements, outside Containment," 2/10/80.
k. Letter of 6/4/81 from ASCO to EDS containing materials lists for ASCO coils. & Frank!!n Research Center A Opumen of The Femman tumme
1. Letter of 6/18/81 from ASCO to'EDS containing Class A and Class F coil lead wires.
m. Letter of 6/8/81 from ASCO to Toledo Edison Co. concerning environmental qualification of ASCO valves.
n. Letter of 9/22/81 from Bailey Meter Co.

I to EDS concerning Bailey Meter Materials lists.

o. Letter of 5/21/81 from Barksdale to EDS containing Non-Metallic Material List for T2H-M155S Temperature Switch.
p. Letter of 10/30/75 from Boston Insulated Wire and Cable Co. to Bechtel concerning LOCA si:nulation tests of BIW cable.
q. Letter of 3/26/81 from Fenwal to EDS concerning non-metallic parts in Fenwal 27120-22 Thermoswitch.
r. Letter of 4/21/81 from Foxboro to EDS s

concerning environmental qualification of Foxboro transmitte'rs.

s. Letter of 4/13/81 from General Dynamics to EDS concerning Stator Coil Insulation materials for Electro Dynamic Motors.
t. Letter of 3/26/81 from Differential Pressure Instruments to EDS concerning non-metallic parts in ITT Barton Pressure Indicating Switches Models 288A and 289A.
u. Letter of 6/17/81 from D.P.I. to EDS concerning materials used in 288 and 289 ITT Barton Differential Precsure Switch.
v. Letter of 6/5/81 from Licon to EDS concerning materials in Barton parts Nos.

00068-004-T and 5891-0001-Z.

(

w. Letter of 6/19/81 from Kerite to EDS concerning submergence of Kerite Cable.

f a

~ ~ -. -.

x. Letter of 4/27/79 from B&W to TBCO concerning Limitorque test reports.
y. L'etter of 7/28/80 from B&W to Bechtel concerning Limitorque test reports.
z. Letter of 11/5/80 from Limitorque to TECO concerning Limitorque test reports.

-r aa. Letter of 6/1/81 from B&W to TECO concerning Limitorque test reports.

bb. Letter of,7/13/81 from Bechtel to EDS concerning Limitorque test reports.

cc. Letter of 7/21/81 from Limitorque to EDS concerning Limitorque test reports.

dd. Letter of 7/7/81 from Limitorque to EDS concerning Limitorque test reports.

ee. Letter of 4/28/81 from Microswitch to EDS containing parts list for Microswitch lLS3.

ff. Letter of 4/2d/81 from Microswitch to EDS containing parts list for Microswitch LSD2B-4N.

gg. Letter of 5/1/81 from Okonite to EDS containing data on EP insulation.

~

hh. Lettar of 9/18/81 from Raychem to EDS

oncerning Moisture Resistance of WCSF-N Heat Shrink Tubing.
11. Letter of 11/10/81 from Rees to Bechtel containing Rees lists of components and materials lists.

l jj. Letter of 3/11/31 from Rees to EDS ccntaining Material List for Pushbutton Switches.

kk. Letter cf 4/2/81 from Rees to EDS containing Material List for Pushbutton Switches..

d r.anklin Research Center 4:

mr- -

4 e

w

11. Letter of 7/14/80 from Stanwick to Bechtel containing component materials lists and testing documentation for Stanwick Terminal Blocks.

em. Letter of 2/18/81 from Stanwick to EDS containing component materials lists and testing data for Stanwick Type G Terminal Dlock.

nn. Letter of 1/27/78 from States to Yankee Atomic Electric concerning States NT and ZWM Terminal Blocks.

oo. Letter of 9/18/80 from Southern Company Services concerning Wyle Test Report 44354-1.

pp. Letter of 2/9/81 from States to EDS concerning States TWM and NT Terminal Block materials.

qq. Letter of 12/9/80 from SOR to TECO containing material lists for non-metallic parts in SOR pressure switches.

rr. Letter of 7/9/81 from SOR to EDS concerning qualification of SOR Pressure Switches.

ss. Letter of 7/20/81 from Westinghouse to EDS containing e.vironmental qualification docu.aentation for Westinghcuse Hydrogen Dilution System Motors.

tt. Letter of 8/15/80 from Toledo Edison Co.

to Babcock and Wilcox concerning HPI and LPI pumps.

uu. Telephone conversation of 7/30/81 besween F. Levancesti and J. Thompson en:.c,e ~ne standard test time for Equipment Qualification Tests, t

4 N0) ranMin Reseanch Center A Chenon of The Fransen besmae

,a..

s W.

EDS Calculation 1040-001-038, Arrhenius Model for Rosemount, Foxboro, and Bailey Transmitters.

ww. EDS Calculation 1040-001-040, Iow pH Analysis for Components Tested in a High pH Chemical Spray.

l xx. EDS Calculation 1040-001-042, Chemical Spray Analysis of Safety-Related Components.

yy. Boston Insulated Wire & Cable Company Prototype Test Report flo. 73C212, 6/18/73

22. Amphenol SAMS Operation Technical Report 123-1268, "Special Prototype Radiation, Environmental and Short Circuit Testing p

of a Type 2 Low Voltage Power Penetration Assembly used on Davis-Besse Nuclear Power Station Unit No.

1," 3/12/75.

l l

  • eb 1 nklin Research Center A Chuman J The Feenaan %

~ -

REFERENCES 1.

R. P. Crouse i

Letter to J. F. Stolz, NRC.

Subject:

Response to SER for the Environmental Qualification of Safety-Related Electrical Equipment at Davis-Besse Nuclear Power Station Toledo Edison Co., 12-Oct-81 Serial No. 750 i

2.

R. P. Crouse Letter to J. Keppler, NRC.

Subject:

Revision 3 of response to IE j

Bulletin 79-01B for Davis-Basse Nuclear Power Station Unit 1 Toledo Edison, 30-Jan-81 1

1-184 3.

Office of Nuclear Reactor Regulation

~

~

Safety Evaluation Report for Davis-Besse Unit 1 Environmental Qualification of Safety-Related Electrical Equipment NRC, 05-Jun-81 e

m A Dhamm of The Frerunn humanume i

- - - -..