Issue date | Title | Topic | |
---|---|---|---|
ML20209D953 | 27 June 1999 | Inservice Insp Ninety-Day Rept Bvps,Unit 2 Outage 7,Year 1999 | Boric Acid Hydrostatic Nondestructive Examination VT-2 |
ML20217E663 | 18 March 1998 | ISI Ninety-Day Summary Rept Bvps,Unit 1 Outage 12,Yr 1997 | Hydrostatic Anchor Darling Nondestructive Examination VT-2 |
ML20202B148 | 3 October 1997 | ISI Plan for Second Ten-Yr Interval at Bvps,Unit 2,Relief Request BV2-B1.11-1,Rev 1, Re Rv Lower Circumferential Weld (2RCS-REV21-C-4) | |
ML20202B175 | 3 October 1997 | Pressure Testing Program for Third Ten-Yr Interval at Bvps,Unit 1, & Second Ten-Yr Interval at Bvps,Unit 2, Relief Request BV3-IWA-1,Rev 1, Re Insulation Removal for Class 1 & 2 Bolted Connections | Boric Acid Scaffolding |
ML20202B162 | 3 October 1997 | ISI Plan for Second Ten-Yr Interval at Bvps,Unit 2,Relief Request BV2-RV-AUG-1,Rev 0, Re Rv Lower Circumferential Weld (2RCS-REV21-C-4) | |
ML20202B134 | 3 October 1997 | ISI Plan for Second Ten-Yr Interval at Bvps,Unit 1,Relief Request BV1-RV-AUG-1,Rev 0, Re Rv Circumferential Welds (RC-R-1-C-1 & RC-R-1-C-8) | |
ML20202A955 | 3 October 1997 | ISI Plan for Second Ten-Yr Interval at Bvps,Unit 1,Relief Request BV1-RV-Welds,Rev 1, Re Rv Circumferenctial Welds (RC-R-1-C-1 & RC-R-1-C-8) | |
ML20136B686 | 24 February 1997 | ISI Ninety-Day Rept BVPS Unit 2 for Outage 6 for 1996 | Hydrostatic Control of Heavy Loads |
ML20116K239 | 22 July 1996 | ISI Ninety-Day Rept for BVPS Unit 1,Outage 11, for Period 950303-960508 | Hydrostatic |
ML20096F181 | 12 January 1996 | Steam Generator Tube Inservice Insp Rept, for BVPS | |
ML20087E714 | 10 July 1995 | ISI Ninety-Day Rept Beaver Valley Power Station Unit 2 Outage 5,Yr 1995 for 931125-0507 | Boric Acid Hydrostatic |
ML20085F920 | 31 May 1995 | Interim Plugging Criteria 90 Day Rept | |
ML20084N339 | 17 May 1995 | ISI Ninety-Day Rept Beaver Valley Power Station Unit 1 | Boric Acid Hydrostatic Control of Heavy Loads |
ML20080J389 | 21 February 1995 | Results of ISI of SG Tubes,Performed During Tenth Refueling Outage | |
ML20063L608 | 15 February 1994 | ISI Ninety-Day Rept Beaver Valley Power Station Unit 2 Outage 4 1993 | Boric Acid Hydrostatic |
ML20057B556 | 3 September 1993 | ISI Ninty-Day Rept Bvps,Unit 1 Outage 9 for 1993 from 911209-930613 | Boric Acid Non-Destructive Examination Hydrostatic |
ML20099F194 | 20 July 1992 | Inservice Insp Ninety-Day Rept,Beaver Valley Power Station Unit 2 for Period of 901115-920507 | Boric Acid Hydrostatic Temporary Modification VT-2 |
ML20106D463 | 13 March 1992 | Issue 2,Rev 8 to Beaver Valley Power Station Unit 1 Inservice Testing Program for Pump & Valves | Boric Acid Stroke time Cold shutdown justification Power-Operated Valves |
ML20091D779 | 4 September 1991 | Inservice Inspection 90-Day Rept,Beaver Valley Power Station Unit 1,Outage 8 for Insp Term from 891222-910715 | Boric Acid Hydrostatic VT-2 |
ML20114B508 | 6 June 1991 | Issue 2 to Rev 7 to Beaver Valley Power Station Unit 1 Inservice Testing Program for Pump & Valves | |
ML20066J401 | 2 February 1991 | Inservice Insp 90-Day Rept for Beaver Valley Power Station Unit 2 for Period 890602-901115 | Boric Acid |
ML20012E415 | 9 March 1990 | Inservice Insp 90-Day Rept,Beaver Valley Power Station Unit 1,Outage 7, for 880227-891221 | |
ML20246P981 | 23 August 1989 | Inservice Insp Rept for Beaver Valley Power Station Unit 2, for Period 871117-890601 | |
ML20196D191 | 21 November 1988 | Sixth Refueling Steam Generator Tube Inservice Insp Special Rept | |
ML20151Q237 | 31 March 1988 | Preservice Insp Summary Rept,Beaver Valley Power Station Unit 2,1985-1988 | Nondestructive Examination |
ML20154P259 | 26 February 1988 | Inservice Insp Rept,Beaver Valley Power Station Unit 1, Outage 6, for 1987-1988 | |
ML20214U771 | 18 November 1986 | Inservice Insp Rept for Beaver Valley Power Station Unit 1, Outage 5 (First Interval,Third Period), on ASME Class 1 & 2 Components & Piping Examined Between Mar 1985 & Aug 1986 | |
ML20155J669 | 14 May 1986 | Rev 3 to Inservice Insp 10-Yr Plan for Beaver Valley Power Station | Boric Acid Hydrostatic Nondestructive Examination Liquid penetrant |
ML20080N240 | 22 September 1983 | Revised Pages to Reactor Vessel Inservice Insp Refueling Outage Core I-II Rept | |
ML20069F813 | 13 September 1982 | Inservice Insp Rept on ASME Class 1,2 & 3 Components & Piping Conducted Jan-June 1982 | Boric Acid Liquid penetrant Dissimilar Metal Weld |
ML20003B140 | 30 January 1981 | Inservice Insp Rept on 780911-801107.Summarizes Examination of Reactor Vessel for Refueling Outage.Results of Pressure Piping Attachment Weldments Survey Serve as Baseline Data for New Mods on Existing Support Components | Boric Acid Liquid penetrant |