NL-22-0365, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R30 | 31 May 2022 | Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R30 | |
NL-21-0905, Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R29 | 26 January 2022 | Inservice Inspection Program Owner'S Activity Report (OAR-1) for Outage 1R29 | |
NL-19-1491, Update to the Snubber Program Plan for the Fifth Ten-Year Inservice Testing Interval | 9 December 2019 | Update to the Snubber Program Plan for the Fifth Ten-Year Inservice Testing Interval | Safe Shutdown |
NL-19-0726, Inservice Inspection Program Owner'S Activity Report for Outage 2R25 | 17 June 2019 | Inservice Inspection Program Owner'S Activity Report for Outage 2R25 | Through Wall Leak |
NL-19-0317, Submittal of Fifth Ten-Year Interval Lnservice Testing Program Update | 2 April 2019 | Submittal of Fifth Ten-Year Interval Lnservice Testing Program Update | Safe Shutdown Stroke time Time to boil Squib Incorporated by reference Scram Discharge Volume Cold shutdown justification Power-Operated Valves Power Operated Valves Scaffolding Grace period |
NL-17-1194, Submittal of Response to Request for Information Fourth Interval Relief Requests RR-13, RR-14, RR-18, RR19, RR-23, and RR-24 | 10 July 2017 | Submittal of Response to Request for Information Fourth Interval Relief Requests RR-13, RR-14, RR-18, RR19, RR-23, and RR-24 | Weld Overlay Dissimilar Metal Weld |
NL-17-0951, Inservice Inspection Program, Owner'S Activity Report for Outage 2R24 | 30 May 2017 | Inservice Inspection Program, Owner'S Activity Report for Outage 2R24 | VT-2 Finite Element Analysis Liquid penetrant Through Wall Leak |
NL-16-2707, Units 1 and 2; Fourth 10-year Interval In-service Inspection Program ISI Program Update: Notification of Impractical ASME Code Requirements (NL-16-2707) | 27 December 2016 | Units 1 and 2; Fourth 10-year Interval In-service Inspection Program ISI Program Update: Notification of Impractical ASME Code Requirements (NL-16-2707) | Weld Overlay VT-2 Liquid penetrant Dissimilar Metal Weld |
ND-16-1437, Snubber Program Plan for the Fifth Ten-Year Inservice Testing Interval | 24 August 2016 | Snubber Program Plan for the Fifth Ten-Year Inservice Testing Interval | Safe Shutdown |
NL-16-0795, Inservice Inspection Program - Owner'S Activity Report for Outage IR27 | 1 June 2016 | Inservice Inspection Program - Owner'S Activity Report for Outage IR27 | Weld Overlay EVT-1 |
NL-16-0421, Full Structural Weld Overlays on Reactor Recirculation and Residual Heat Removal Systems, Nondestructive Examination Results - Spring 2016 Outage (1R27) | 17 March 2016 | Full Structural Weld Overlays on Reactor Recirculation and Residual Heat Removal Systems, Nondestructive Examination Results - Spring 2016 Outage (1R27) | Weld Overlay Nondestructive Examination |
NL-15-1096, Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval | 18 June 2015 | Provides Follow-up Letter Regarding Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval | |
NL-15-1032, E. I. Hatch, Unit 2 - Inservice Inspection Program Owner'S Activity Report for Outage 2R23 | 12 June 2015 | E. I. Hatch, Unit 2 - Inservice Inspection Program Owner'S Activity Report for Outage 2R23 | Weld Overlay EVT-1 |
NL-15-0784, Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval | 4 May 2015 | Submittal of the Inservice Testing Program Relief Requests and Alternatives for Pumps and Valves - Fifth Ten-Year Interval | Stroke time Scram Discharge Volume Power-Operated Valves Scaffolding Grace period |
NL-14-1821, Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 2.0 - Supplemental Information | 13 November 2014 | Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 2.0 - Supplemental Information | |
NL-14-1276, Snubber Inspection Plan Submittal in Accordance with ASME OM Code | 31 October 2014 | Snubber Inspection Plan Submittal in Accordance with ASME OM Code | Safe Shutdown Anchor Darling |
NL-14-1250, Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 2.0 | 19 September 2014 | Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 2.0 | Non-Destructive Examination Hydrostatic Operating Basis Earthquake Nondestructive Examination VT-2 Tornado Generated Missile Tornado Missile Protection Design basis earthquake Earthquake |
NL-14-0840, Lnservice Inspection Program Owner'S Activity Report for Outage 1R26 | 3 June 2014 | Lnservice Inspection Program Owner'S Activity Report for Outage 1R26 | |
NL-14-0231, Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 1.0 | 6 March 2014 | Proposed Inservice Inspection Alternative HNP-ISI-ALT-HDPE-01, Version 1.0 | Hydrostatic Nondestructive Examination VT-2 Earthquake |
NL-12-1266, Inservice Inspection Program, Owner'S Activity Report for Outage 1R25 | 14 June 2012 | Inservice Inspection Program, Owner'S Activity Report for Outage 1R25 | |
NL-10-0989, Fourth 10-Year Interval Lnservice Inspection Program Submittal of Relief Requests | 8 July 2010 | Fourth 10-Year Interval Lnservice Inspection Program Submittal of Relief Requests | Weld Overlay VT-2 Dissimilar Metal Weld |
NL-10-1023, Inservice Inspection Program, Owner'S Activity Report for Outage 1R24 | 11 June 2010 | Inservice Inspection Program, Owner'S Activity Report for Outage 1R24 | |
NL-08-1798, Fourth 10-Year Interval Lnservice Inspection Program Submittal of Relief Request RR-01 | 19 December 2008 | Fourth 10-Year Interval Lnservice Inspection Program Submittal of Relief Request RR-01 | |
NL-08-0901, Unit 1, Inservice Inspection Program Owner'S Activity Report for Outage 1R23 and Structural Integrity Design Report for the N9 CRD Nozzle-to-Cap Full Structural Weld Overlay | 13 June 2008 | Unit 1, Inservice Inspection Program Owner'S Activity Report for Outage 1R23 and Structural Integrity Design Report for the N9 CRD Nozzle-to-Cap Full Structural Weld Overlay | Weld Overlay Finite Element Analysis Dissimilar Metal Weld |
NL-07-0987, Fourth Interval Inspection (ISI) Plan Correction | 9 May 2007 | Fourth Interval Inspection (ISI) Plan Correction | |
NL-07-0802, Response to Request for Additional Information Regarding the Third 10-Year Interval Inservice Inspection (ISI) Relief Requests | 13 April 2007 | Response to Request for Additional Information Regarding the Third 10-Year Interval Inservice Inspection (ISI) Relief Requests | VT-2 |
ML070430094 | 20 November 2006 | E. I. Hatch, Unit 2, Volume 2, Revision 1, Class 1, 2 and 3 Components Fourth Ten-Year Examination Plan. | Weld Overlay Hydrostatic VT-2 Scram Discharge Volume Dissimilar Metal Weld DM weld |
ML070430100 | 20 November 2006 | E. I. Hatch, Unit 2, Volume 3, Revision 1.0, Class 1, 2 and 3 Figures Fourth Ten-Year Inservice Inspection Plan. | |
ML070430092 | 20 November 2006 | E. I. Hatch, Unit 2, Volume 1, Revision 2, Introduction Fourth Ten-Year Examination Plan. | Safe Shutdown High Radiation Area Weld Overlay Hydrostatic Coatings Nondestructive Examination VT-2 Incorporated by reference Exemption Request Dissimilar Metal Weld Scaffolding |
ML070430101 | 10 August 2006 | E. I. Hatch, Unit 2, Version 1.0, Pressure Test Section Fourth Ten-Year Examination Plan. | VT-2 |
NL-06-1358, Inservice Inspection Program, Owner'S Activity Report for Outage 1R22 | 29 June 2006 | Inservice Inspection Program, Owner'S Activity Report for Outage 1R22 | Hydrostatic Dissimilar Metal Weld |
ML070430081 | 6 February 2006 | E. I. Hatch, Unit 1, Volume 1, Revision 1, Introduction Fourth Ten-Year Inservice Inspection Plan. | High Radiation Area Weld Overlay Hydrostatic Coatings Nondestructive Examination VT-2 Incorporated by reference Exemption Request Dissimilar Metal Weld |
ML070430083 | 6 February 2006 | E. I. Hatch, Unit 1, Volume 2, Revision 1, Class 1, 2 and 3 Components Fourth Ten-Year Inservice Inspection Plan. | Safe Shutdown Weld Overlay Hydrostatic VT-2 Finite Element Analysis Scram Discharge Volume Dissimilar Metal Weld |
ML070430087 | 6 February 2006 | E. I. Hatch, Unit 1, Volume 3, Revision 1, Class 1, 2 and 3 Figures, Fourth Ten-Year Inservice Inspection Plan. | |
ML070430096 | 31 August 2005 | E. I. Hatch, Unit 1, Version 1.0, Pressure Test Section Fourth Ten-Year Examination Plan. | VT-2 |
NL-05-1190, Fourth 10-Year Interval Inservice Testing (Ist)Program Updates Submittal for Edwin I. Hatch Nuclear Plant | 11 July 2005 | Fourth 10-Year Interval Inservice Testing (Ist)Program Updates Submittal for Edwin I. Hatch Nuclear Plant | High Radiation Area Stroke time Probabilistic Risk Assessment Squib Scram Discharge Volume Excess Flow Check Valve Cold shutdown justification Power Operated Valves Scaffolding Flow Induced Vibration |
ML051640385 | 7 June 2005 | Third 10-Year Interval Inservice Inspection Program Owner'S Activity Report | |
NL-04-0813, Third 10-Year Interval Inservice Inspection Program Owner'S Activity Report | 7 June 2004 | Third 10-Year Interval Inservice Inspection Program Owner'S Activity Report | Hydrostatic |
NL-04-0478, Third 10-Year Interval Inservice Inspection Program Submittal of Relief Requests (RR) RR-38, RR-39, and RR-40 | 29 March 2004 | Third 10-Year Interval Inservice Inspection Program Submittal of Relief Requests (RR) RR-38, RR-39, and RR-40 | VT-2 |
NL-03-1380, Third 10-Year Interval Inservice Testing Program, Submittal of Relief Requests RR-V-18 | 11 July 2003 | Third 10-Year Interval Inservice Testing Program, Submittal of Relief Requests RR-V-18 | Probabilistic Risk Assessment |
ML023090356 | 1 November 2002 | Third 10-Year Interval Inservice Inspection (ISI) Program, Revision of Relief Request RR-11 | Nondestructive Examination |
ML022820026 | 4 October 2002 | Third 10-Year Interval Inservice Inspection Program, Response to Request for Additional Information (RAI) | Weld Overlay |
ML022660436 | 17 September 2002 | Third 10-Year Interval Inservice Inspection Program Owner'S Activity Report | |