Duke Energy - Response to Regulatory Issue Summary (RIS) 2014-13, Planned Licensing Action Submittals for All Power Reactor Licensees
ML15049A238
Person / Time
Site: Oconee, Mcguire, Catawba, Harris, Brunswick, Crystal River, Robinson, McGuire  Duke Energy icon.png
Issue date: 02/05/2015
From: Nolan M
Duke Energy Corp
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
RA-15-0005, RIS-14-013
Download: ML15049A238 (33)


Text

DU UN.ChdsWherNoAM DUKE 526 Soug Church Shr..t

£ &Ec2zF/P.O. Box iW06

  • * ; *~~Ch*IkfNC"_20X-0
  • 7043*2-7426
  • * * . i , " . , -

Serial: RA-15-0005 . .10 CFR 50.4 February 5, 2015 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325, 50-324/ RENEWED LICENSE NOS. DPR-71 AND DPR-62 CATAWBA NUCLEAR STATION, UNIT NOS. I AND 2 DOCKET NOS. 50-413,50-414 / RENEWED LICENSE NOS. NPF-35 AND NPF-52 CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT DOCKET NO. 50-302/ LICENSE NO. DPR-72' SHEARON HARRIS NUCLEAR POWER PLANT, UNIT 1 DOCKET NO. 50-400/ RENEWED UCENSE NO. NPF-63 MCGUIRE NUCLEAR STATION, UNIT NOS. I AND 2 DOCKET NOS. 50-369, 50-370/ RENEWED UCENSE NOS. NPF-9 AND NPF-17 OCONEE NUCLEAR STATION, UNIT NOS. 1,2 AND 3 DOCKET NOS. 50-269,50-270, AND 60-287 / RENEWED UCENSE NOS. DPR-38, DPR-47, AND DPR-55 H.B.ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261 1RENEWED UCENSE NO. DPR-23

Subject:

RESPONSE TO NRC REGULATORY ISSUE

SUMMARY

2014-13 PLANNED LICENSING ACTION SUINITTALS FOR ALL POWER REACTOR LICENSEES On December 17,2014, the Nuclear Regulatory Commission issued Regulatory issue Summary (RIS) 2014-13, "Planned Licensing Action Submittals for All Power Reactor Licensees." The RIS requests the voluntary submittal of licensees to provide Information regarding the licensing actions that they plan to submit to the NRC for review over the next 3 calendar yearsand power uprate applications that they plan to submit to the NRC for review over the next 5 calendar years. The Included attachments contain the estimated future licensing actions and power uprate applications for the Brunswick Steam Electric Plant, Catawba Nuclear Station, Shearon Harris Nuclear Power Plant, McGulre Nuclear Station, Oconee Nuclear Station, and H.S.

AitoI

Serial: RA-15-0005 February 5, 2015 Page 2 Robinson Steam Electric Plant. Crystal River Unit 3 is not included due to its expected transition from Nuclear Reactor Regulation (NRR) to Nuclear Material Safety and Safeguards (NMSS) in the near future.

This sbrnmittal contains no new regulatory commitments or changes to previous commitments.

Please direct any questions to Art Zaremba at (980) 373-2062.

Sincerely, M. Christopher Nolan Director Nuclear Regulatory Affairs Attachment(s)

1. Table of Estimated Licensing Actions, Brunswick Steam Electric Plant
2. Table of Estimated Licensing Actions, Catawba Nuclear Station
3. Table of Estimated Licensing Actions, Shearon Harris Nuclear Power Plant
4. Table of Estimated Licensing Actions, McGuire Nuclear Station
5. Table of Estimated Licensing Actions, Oconee Nuclear Station
6. Table of Estimated Licensing Actions, H.B. Robinson Steam Electric Plant cc: Tracy Off, Division of Operating Reactor Licensing TechniCal Assistant U.S. Nuclear Regulatory Commission Mail Stop O-8C2 Rockville, MD 20852-2738 USNRC Region II USNRC Senior Resident Inspector - SHNPP USNRC Senior Resident Inspector - HBRSEP USNRC Senior Resident inspector - MNS USNRC Senior Resident Inspector - CNS USNRC Senior Resident Inspector - ONS USNRC Senior Resident Inspecor - BSEP USNRC Senior Resident Inspector - CRNGP M.C. Barillas, NRRProject Manager - SHNPP & HBRSEP G. E. Miller, NRR Project Manager - CNS & MNS J. R. Hall, NRR Project Manager - ONS A. L. Hon, NRR Project Manager - BSEP M. D. Orenak, NRR Project Manager - CRNGP

Serial: RA-15-0005 February 5, 2015 Page 3 bcc: Chris Nolan Art Zaremba Lara Nichols David Cummings File: (Corporate)

Electronic Licensing Library (ELL)

Randy Gideon Lee Grzeck Bill Murray (For BNP Licensing/Nuclear Records Files)

Ben Waldrep Dave Corlett A!

Cindy Hereford (For HNP Licensing/Nuclear Records Files)

- ~ .. . .

Mike Glover Richard Hightower Heidi Walters (For RNP Licensing/Nuclear Records Files)

Kelvin Henderson Bentley Jones North Carolina Municipal Power Agency No. I (NCMPA)

Piedmont Municipal Power Agency (PMPA)

North Carolina Electric Membership Corporation (NCEMC)

CNS Master File 801.01 - CN04DM T. K. Pasour (For CNS Licensing/Nuclear Records)

Steven Capps Jeff Robertson MNS Master File 801.01 - MG01DIM K. L. Crane (For MNS Licensing/Nuclear Records)

Scott Batson Chris Wasik Sandy Severance ONS Master File 801.01 - ONO3DM J. E. Smith (For ONS Licensing/Nuclear Records)

RA-15-0005 Attachment I Tabl" of destimaed Licensing Actions, Brunswick Steam Electric Plant RA-15-0005 Page 1

1. For all planned licensing actions expected to be submitted in the next 3 calendar years, Brunswick Units I and 2.are providing the following information:

TABLE OF ESTIMATED UCENSING ACTIONS Brunswick Steam Electric Plant Units I and 2 Docket Nos.60-325 and 50-324 Rf Al nfns apply oWboth units UCENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION TYPE DESCRIPTION SUBMITTAL RELATED? IF SO, NEEDED)

NUMBER -DATE..' DATE NEEDED I License Revise Emergency Action 1st Quarter 2015 No Amendment Levels consistent with NEI Request 9-01, Revision 6 2 License Adopt TSTF-523, 2nd Quarter 2015 No Brunswick, Harris, Amendment "Managing Gas Catawba, McGuire, Request Accumulation" Oconee combined:

.%"- submittal 3 License Emergency Response 2nd Quarter 2015 No Amendment Organization (ERO)

Request ResponseTiunes _,

4 License Merged Quality Assurance 2nd Quarter 2015 No Brunswick, Harris, Amendment Topical Report Catawba, McGuire, Request Oconee, Robinson

_________"__combined submittal 5 License Electrical Protection 3rd Quarter 2015 No Amendment Assembly (EPA) Breaker

___Reques . Voltag Allowable Value I_____ ____ ______ ...

RA-15-0005 Page 2 6 License Adopt TSTF-427, 3rd Quarter 2015 No Brunswick, Harris, Amendment "Allowance for Non- Catawba, McGuire, Request Technical Specification Oconee, Robinson Barrier Degradation on combined submittal Supported System Operabdity 7 License Adopt TSTF-52Z "Revise 3rd Quarter 2015 No Brunswick, Harris, Amendment Ventilation System Catawba, McGuire, Request Surveillance Requirements Oconee, Robinson to Operate for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> per combined submittal Month" 8 License Common Emergency 4th Quarter 2015 No Brunswick, Harris, Amendment Operations Facility Robinson combined Request submittal 9 License Adopt TSTF-425, 1st Quarter 2016 No Amendment "Relocate Surveillance Request Frequencies to Licensee Control - RITSTF Initiative 5b" 10 License Adopt new type of 2nd Quarter 2016 No Brunswick, Harris, Amendment respirator (Respirex) Robinson combined Request submittal 11 License Adopt TSTF-505, 4th Quarter 2016 No Amendment "Provide Risk-Informed Request Extended Completion Times - RITSTF Initiative 4b" 12 License Extend Appendix J, Type A 1st Quarter 2017 Yes, Spring 2020 Amendment (ILRT) and Type C (LLRT)

Request Test Intervals 13 License 50.69 - Graded Quality 4th Quarter 2017 No Brunswick, Harris, Amendment Assurance Program Catawba, McGuire, Request Oconee, Robinson combined submittal

Attachment I RA-15-0005 Page 3

2. Brunswick Units 1 and 2 do not plan to apply for a power uprate in the next 5 calendar years,
3. The NRC staff may make the above Information public.

RA- 15-0005 Afttchmewnt 2 TWO of EstimatedLicensing Actions, Catawba Nuclear Station

-'( ,

RA-15-0005 Page 1

1. For all planned licensing actions expected to be submitted in the next 3 calendar years, Catawba Units 1 and 2 are providing the following information:

TABLE OF ESTIMATED LICENSING ACTIONS Catawba Nuclear Station U"Itsliand 2 Docket NoM 50-413 and 50-414 Noft: Achd 10is zap tps fa VAN $0413) ouly.

(IoZkxM, ad M mv we to both wnt Wb.

LICENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION TYPE DESCRIPTION SUBMITTAL RELATED? IF SO, NEEDED)

NUMBER DATE -DATE NEEDED 1 License Reduce Reactor Coolant 1st Quarter 2015 No Amendment (NC) flow on both Units to Request Increase flow margin to

>1% ,

2 License Extend the Completion 2nd Quarter 2015 No Catawba, McGuire Amendment Tone for two trains of combined submittal Request Control Area Chilled Water

____,,___ _ System (YC) inoperable _,- ....

3 License Adopt .TSTF-510, t 2nd Quarter 2015 Yes, Fall 2016 Catawba, McGuire, Amendment 'Revision, to Steam , Oconee combined Request Generator Program submittal Inspection Frequencies and Tube Sample Selection" 4 License Adopt TSTF-523, 2nd Quarter 2015 No Brunswick, Harrs,,

Amendment "Managing Gas Catawba, McGuire, Request Accumulation" Oconee combined

.. .. ___-_submittal RA-15-0005 Page 2 5 License Alternative Non-LOCA 2nd Quarter 2015 No Catawba, McGuire, Amendment Fission Product Gap Oconee combined Request Fractions submittal Pre-submittal meeting held on January 14, 2015 6 License Merged Quality Assurance 2nd Quarter 2015 No Brunswick, Harris, Amendment Topical Report Catawba, McGuire, Request Oconee, Robinson combined submittal 7 License Revise Emergency Action 2nd Quarter 2015 No Amendment Levels consistent with NEI R( ., 99-01, Revision 6 8 License Extend Appendix J, TypeA 3rd Quarter 2015 Yes, Fall2016 Amendment (ILRT) and Type C (LLRT)

Reus Test Intervals_______

9 License Adopt TSTF-522, -Revise 3rd Quarter 2015 No Brunswick, Harris, Amendment Ventilation System Catawba, McGuire, Request Surveillance Requirements Oconee, Robinson to Operate for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> per combined submittal Month" ....

10 License Adopt TSTF-427, 3rd Quarter 2015 No Brunswick, Harris, Amendment "Allowance for Non- Catawba, McGuire, Request Technical Specification Oconee, Robinson Barrier Degradation on combined submittal Supported System Operability" 11 License Administrative LAR to 4th Quarter 2015 No Catawba, McGuire Amendment delete the superseded TS combined submittal Request- and Bases requirements for the Source Range /

Intermediate Range

__replacement TS change RA-15-0005 Page 3 12 License Diesel Generator AOT 1st Quarter 2016 No Amendment extension 72 hrs, to 14 Request days using BTP-8.8.

13 License UFSAR Change - Request 1st Quarter 2016 No Catawba, McGuire Amendment review and approval of the combined submittal Request TORMIS methodology to resolve a non-conformance related to the Reactor Building Doghouse openings.

SSCs inside are susceptible to tornado missile damage. _ _

14 License Removal of the License 1st Quarter 2016 No Amendment Condition that limits Dose Request Equivalent Iodine to a value Speicflesstkons than Technical __

15 Lcense 50.69 - Graded Quality 4th Quarte 2017 No Brunswick, Harris, Amendment Assurance Program Catawba, McGuire, Request Oconee, Robinson

____combined submittal 16 License Revise Reactor Coolant 1st Quarter 2018 No Applicable to Catawba Amendment System (NC) Unit I (Docket 50-413)

Request pressure/temperature only.

limits to extend beyond 34 EFPY _..,

2. Catawba Units I and 2 do not plan to apply for a power uprate in the next 5 calendar years.
3. The NRC staff may make the above information public.

RA-15-0005

.1 Atachmet 3 Table otdEstimated Ucensing Actions, Shearon Haris Nuclear Power Plant

,.C RA-15-0005 Page I

1. For all planned licensing actions expected to be submitted in the next 3 calendar years, Harris Unit 1 is providing the following information TABLE OF ESTIMATED UCENSING ACTIONS SheaRon Harris Nuclear Power Plant Unit 1 Docket No. 50400 LICENSING UCENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTIONTYPE DESCRIPTION SUBMI'TAL DATE RELATED? IF NEEDED)

NUMBER SO, DATE NEEDED 1 License DPC-NE-2005 1st Quarter 2015 No Harris, Robinson Amendment Thermal Hydraulics combined submittal Request Statistical Core Design Methodology Revision of Exsting Fuels Methodology Report Adoption Into

_____ _ ... _"__ _:_ "__'Tech Specs-2 Relief Request Generic approval of 1st Quarter 2015 No temper bead weld process for reactor vessel head repaw' _ _ _ _ _ _

3 License Adopt TSTF-425, lt Quarter 2015 No Amendment 'Relocate Surveillance..

Request Frequencies to Licensee Control - RITSTF Initiative 5b" 4 License Move Waste Gas 1st Quarter 2015 No Amendment Explosive Limits TS to Request program for consistency with ITS RA-15-0005 Page 2 5 License DPC-NE-1008 2nd Quarter 2015 No Harris, Robinson Amendment Nuclear Design combined submittal Request Methodology using CASMO-6/SIMULATE-3 New Fuels DPC-NE-3008 Methodology Reports Thermal-Hydraulic Adoption into Tech

. Transient Analysis Specs Methodology __--

6 License Revise'Emergency Action 2nd Quarter'2015 No Amendment Levels consistent with Request NEI 99-01, Revision 6 _*_.. ..

7 License Revise FSAR to take

  • 2nd Quarter 2015 No Amendment exception to RG 1.78, Request Rev. I regarding the 330 foot bulk chemical exclusion to the Control Room_

8 License Adopt TSTF-523, 2nd Quarter 2015 No Brunswick, Harris, Amendment 'Managing Gas Catawba; McGuire, Request Accumulation" Oconee combined submittal 9 License Merged Quality Assurance 2nd Quarter 2015 No Brunswick, Harris, Amendment Topical Report Catawba, McGuire, Request - Oconee, Robinson

.... ___ _____-_combined submittal 10 License Adopt TSTF-427, 3rd Quarter 2015 No Brunswick, Harris, Amendment "Allowance for Non- Catawba, McGuire, Request Technical Specification Oconee, .Robinson Barrier Degradation on combined submittal Supported System

__ _'Operability" RA-15-0005 Page 3 Brunswick, Harris, Ventilation System Catawba, McGuire, Surveillance Requirements Oconee, Robinson to Operate for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> per combined submittal Month" License DPC-NE-3009 Harris, Robinson Amendment UFSAR Chapter 15 combined submittal Request TransientAnalysis Methodology New and Revised DPC-NF-2010 Fuels Methodology Nuclear Physics Reports Adoption into Methodology for Reload Tech Specs Design DPC-NE-2011 Nuclear Design Methodology Report for Core Operating Limits of Westinahouse Reactors 13 License Common Emergency 4th Quarter 2015 No Brunswick, Harris, Amendment Operations Facility Robinson combined Request submittal 14 License Adopt TSTF-505, 1st Quarter 2016 No Amendment "Provide Risk-Informed Request Extended Completion Times - RITSTF Initiative 4b" 15 License Adopt new type of 2nd Quarter 2016 No Brunswick, Harris, Amendment respirator (Respirex) Robinson combined Request submittal 16 License DPC-NE-1003 2nd Quarter 2016 Yes, Spring Harris, Robinson Amendment Rod Swap Methodology 2018 combined submittal Request Report for Startup Physics Testing Revision of Existing Fuels Methodology Report RA-15-0005 Page 4 17 License Revise Main Steam 2nd Quarter 2016 No Amendment Safety Valve Setpoints in Request Table &7-2 for

_consistency with ITS 18 License Extend Appendix J, Type A 1st Quarter 2017 Yes, Spring Amendment (ILRT) and Type C (LLRT) 2021 Request Test Intervals 19 License 50.69 - Graded Quality 4th Quarter 2017. No Brunswick, Harris, Amendment Assurance Program Catawba, McGuire, Request Oconee, Robinson combined submittal

2. Harris Unit 1 does not plan to apply for a power uprate In the next 5 calendar years
3. The NRC staff may make the above Information public.

RA-15-0005 Attachmnint 4 Tibleof EStiOmted Licensing Actions, McGuire Nuclear Station RA-15-0005 Page 1

1. For all planned lcensing actions expected to be submitted in the next 3 calendar years,McGuire Units 1 and 2 are providing the following information:

TABLE OF ESTIMATED MCENSING ACTIONS McGuire Nuclear Station Unbt I and2 Docket Nos. 50-369 and 50-370 o*t: Acion Ile applIOc toW-t 1 (00t 504.1Mony.

0* 0eMS WO#a olAN to both nits.

UCENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION TYPE DESCRIPTION SUBMITTAL RELATED? IF SO, NEEDED)

NUMBER DATE DATE NEEDED 1 Relief Request A Relief Request to delay 1stQuarter2015 Yes, Fall 2015 Applicable to McGuire inspection of Unit I Unit 1 (Docket 50-369)

Reactor Coolant (NC) cold only.

leg nozzle welds from 1EOC24 (March-2016) to Precedents: Safety a later outage. Code Evaluations for Indian Case N-770-1 and MRP- Point Unit 3 349, "PWR Reactor (ML14199A444); Farley Coolant System Cold- Units 1 and 2 Loop Dissimilar Metal Butt (ML-14262A317);

Weld Reexamination Arkansas Nuclear One Interval Extension, Unit 1 (ML14282A479) provlde the technical basis to support extension of the reexamination interval for large-diameter Alloy 82/182 dissimilar metal butt welds.

RA-15-0005 Page 2 2 License Administrative LAR to 1st Quarter 2015 No Amendment delete the superseded Request Rated Thermal Power definition footnote'on TS Page 1.1-5 within: 180 days after implementation of the MUR uprate on the last unit. MUR was Implemented on the last unit (Unit 1) on 9/24/14. ___.. ..

3 License Adopt TSTF-510, 2nd Quarter 2015 Yes, Fall 2016 (for Catawba, McGuire, Amendment "Revision to Steam Catawba) Oconee combined Request Generator Program submittal Inspection Frequencies and Tube Sample 4 Ucense Revise Emergency Action 2nd Quarter 2015 No Amendment Levels consistent with NEI Request 99-01, Revision 6S 5 License Alternative Non-LOCA 2nd Quarter 2015 No Catawba, McGuire, Amendment Fission Product Gap Oconee combined Request Fractions submittal Pre-submittal meeting

-. . . .held on January 14,

_ _ .- _ _ _. _ , __. _ _ _ _ _ _ _2015 .4.. ,

6 License, Extend the Completion 2nd Quarter 2015 No Catawba, McGuire Amendment Time for two trains of combined submittal Request Control Area Chilled Water System (YC)

I inoperable RA-1S-000S Page 3 7 License Adopt TSTF-493, "Clarify 2nd Quarter 2015 No Amendment Application of Setpoint Request Methodology for LSSS FunctionsW for TS Table 3.3.1-1 Function 12, Setpoint for underfrequency Reactor.

8 Licese Adopt TSTF-523, 2nd Quarter 2015 No Brunswick, Harris, Amendment "Managing Gas Catawba, McGuire, Request Accumulalton" Oconee combined subittal 9 License Merged Quality Assurance 2nd Quarter 2015 No Brunswick, Harris, Amendment Topical Report Catawba, McGuire, Request Oconee, Robinson combined submittal 10 License Diesel Generator AOT 3rd Quarter 2015 No Amendment extension 72 hrs. to 14 Requestdays using BTP-8.8.

11 License Adopt TSTF-522, "Revise. 3rd Quarter 2015 No Brunswick, Harris, Amendment Ventilation System Catawba, McGuire, Request Sur"eillanrce . Oconee, Robinson Requirements to. Operate combined submittal for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> per Month" 12 License Adopt TSTF-427, 3rd Quarter 2015 No Brunswick, Harris, Amendment "Allowance for Non- .. - Catawba, McGuire, Request , Technical Specification Oconee, Robinson Barrier Degradation on combined submittal Supported System

_OperabIiy 13 License Extend Appendix J, Type 4th Quarter 2015 Yes, Spring 2017 Amendment A (ILRT) and Type C Request (LLRT) Test Intervals RA-15-0005 Page 4 14 License Administrative LAR to 4th Quarter 2015 No Catawba, McGuire Amendment delete the superseded TS combined submittal Request and Bases requirements for the Source Rang, I Irdnermediate Range replacement TS change, 15 License UFSAR Change- Request 1stOuarter2016 No Catawba, McGuire Amendment review and approval of the combined submittal Request TORMIS methodology to resolve a non-conformance related to the Reactor Building Doghouse openings SSCs inside are susceptible to tornado missile damage._

16 License TS 3.6.13- Ice condenser st Quarter 2016 No Amendment door alternate position Request monitoring. . ;

17 License RevIseTS3.6.14,iIvider 1st Quarter 2016 No Amendment Barri Integrity,- to allow Request an indMdual Steam Generator manway.hatch to be open for up to six hours.,

18 License Revise TS.3.&9, 1st Quarter'2016 No Amendment "Hydrogen Mitigation Request System," to allow more than one inoperable hydrogen igniter while still considering the train operable _.

RA-15-0005 Page 5 19 License Refueling canal drain 1st Quarter 2016 No Amendment surveillance change from Request a drain valve to a drain flange.

20 License Revise TS 3.8.9 to allow. 1st Quarter 2016 No Amendment 1) adequate time to Request respond to a single unit fire event without initiating a shutdown of the unaffected unit, 2) test manual transfer of an essential MCC to a SSF MCC, and 3) perform effective PM on plant equiment.

21 License Re-submitting a revised 4th Quarter 2016 -No Amendment version of the one-time TS Request 3.7.7, Nuclear Service Water System (RN),

change to extend the completion time to recover anything that might be in the 'A'RN Standby Nuclear Service Water Pond (SNSWP) suction header.

22 License 50.69 - Graded Quality 4th Quarter 2017 No Brunswick, Harris, Amendment Assurance Program Catawba, McGuire, Request Oconee, Robinson combined submittal

2. McGuire Units 1 and 2do not plan for apower uprate in the next 5calendar years.
3. The NRC staff may make the above Information public.

RA-15-0005

)

Attachment 5 TaWi. of Easniated Licensing Actions, Oconee Nuclear Station

.4 o ;-

.h RA-15-0005 Page 1'

1. For all planned licensing actions, eWpcted to be submitted in the next 3 calendar years, Oconee Units, 1,2, and 3 are,-

providing the following informatlon.:.

TABLE OF ESTIMATED UCENSING ACTIONS

  • Ocone. Nuciow Station Unit tZand3 Docket Nos 50469v 504270, and W0287 us.. -Alwt mo me app.I. to aD ftw, imib UCENSING LICENSING UCENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION TYPE DESCRIPTION SUBMITTAL RELATED? IF SO, NEEDED)

NUMBER DATE DATE NEEDED 4 License Add High Flm Thp for 3 lot Quarter 2015 No Amendmient Reactor Coolant Pump 2 MM- Opertin 2 License Adopt TSTF-523- 2nd Quarter 2015 No Brunswick, Harris, Amendment -Managing Gas Catawba, McGuire, Request Accumulation. - ,.. . - Oconee combined

. .submittal 3 Lwn Atemative Non-LOCA 2nd Quarter 2015 No Catawba, McGuire, Amendment Fission:Product Gap Oconee combined Request Fractos submittal rPr&-ubmfttaltmeeting

.: .-- . ..... . . held on January 14,

_-__ _ _, _ _._ _ _ _ __..,_ _ _ _ __._ 2015 4 License Merged Quality 2nd Quarter 2015 No Brunswick, Harris, Amendment Assunme Topical Report Catawba, McGuire, Request Oconee, Robinson combined submittal RA1 5-0005 Page 5 License Adt" TSTF-510, 2nd-Quarter 2015 Yes, Fad12016 (for Catawba, McGuire, Amendment "Pevision to Steam Catawba) Oconee combined equest Generator Program' . submittal Inspection Frequencies andTube Sample Sele-tlor" 6 icense Revise Emergency Action 2fid-Quarter 2015 No Amenditient Lvels consistent with NEI

______ 99-01, Revision 6 _"____

7 License Adopt TSTF-448, Rl"', " 2ndQua~ter 2015 No Amendment ",WoI Room

" Ucense Standby Shutdown 3rd uatb 2015 No Amendment Facity (SSF) Thermal Rest Margn LAR 9 License Correct Technical 3rdQuarter ,015 Nb Amndme m h Reently ....

Reque"t Issued Amendment to TS 3.8.1 Oper~t"AC Sources- .. d ....,, ,N 10 Lcense TS3.8.1 "ACSources- 3rd uarter 2015 No.':

Amendment Operating" Completion Request Time Extension to Suppoit Keowes " ....

Hydroelectric Statice.

-Stator

... W ork .:-,*',

11 License Adopt TSTF-522, "Revise 3rd Quarter 2015 No Buriswick, Harris, Amendment Ventilation System Catawba, McGuire, Request Surveillance Oconee, Robinson Requirements to Operate , combined submittal for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> per Month"

Attachmeht 5 RA-15-0005 Page 3 12 License Adopt TSTF-427, 3rdlQuter 2015 No Brunswick, Harris, Amendment *Allowance for WlW Catawba, McGuire, Request Technical Specification Oconee, Robinson Barrier Degradation on combined submittal

- -". ",O Supported e bi System "  : .- ":,'

13 ... ense..- DeletOTS3.7.18-Dryý Ist Quarter 2016 No Amendment Spent Fuel StoragCaesk Request Lobdi and Unloading 14 License Main FDW Contrd Valve -ý 4th Quarter 2016 No Amendment Inadequate Air Supply Request 15 License SSF Sump Upgrade/ Kirk- 4th Quarter 2016 No 16 License Tormado Mfidigation lst Quarter 2017 No LAR was submitted Amendment Recostitution LAR previously but NRC Request review has been 17 LIcense HELB MitigaionhtAR 1st Quarter 2017 No LAR was submitted Amendment ,,  ;" previously but NRC Request ... "-vi- has bedn suspended t8 License MUR ReviewRestartafter 1st Quarter 2017 Yes, SeeNo. 2 To be subh*W -after Amendment RAI response submittal below the HELB LAR - MUR Request LAR depends on the safety analysis of the MFDW break in the HELB LAR.

19 License Extend Appendix J, Type 1st Quarter 2017 Yes, Spring 2024 Amendment A (ILRT) and Type C Request (LLRT) Test Intervals 20 License Atmospheric Dump Valve 4th Quarter 2017 No Amendment Allowed Outage Time Request Extension (12 hour1.388889e-4 days <br />0.00333 hours <br />1.984127e-5 weeks <br />4.566e-6 months <br />)

Attachment RA-M15-0005 5 Page4 21 License Adopt TSTF-498 "Risk- 4thQuarte 2017 No Amendment Wormed Contairnmei' Request Isolation Valve Compmok,

__________" Tim es (BAW -2461)" ........ _____..... _' _" _

22 - uces... Revise TS Table 3.3.5-1:" 4th Caiiter 2017' 'No

,.* Amendment to change the a "A *... H. h Reactor 13i ,....

kressure for Eniginered Safeguards actuation to 5 23 Li.ense Revise TS 3.9.1 to adopt 4t Ouarter 2017 No

- Amendment aTSTF -272 querttinge-Request Boron Concetration Clariiation to allow boron samng of FTC .in

________ _________Mods6 a.. ... K.~

24 Lbcense Aflow Ocounee to seff- 4th Quarter 2017 No Amendmnent approve quantitative risk-Request in? orr66d fire pobtechon Proararn chanqe 25 License 50.89 - Graded Qualty 4th Quarter 2017 NO Brunswick, Harris, Amendment... Assurance Prograr .. . Catawta, McGuire, Request Oconee, Robinson

_combined submttal RA-15-0005 Page 5

2. Oconee Units 1, 2, and 3 plan to apply for a 1.84% power uprate measurement uncertainty recapture (MUR) in the next 5 calendar years.

NOTE: Oconee previously submitted a MUR LAR in 9/2011 that was Indefinitely suspended due to NRC resource availability.

A set of RAI items was received by Oconee in the Interim. The MUR LAR will. likely be supplemented In the 3rd quarter 2016.

o What percent Increase In power from the current licensed thermal power (CLTP) limit does the licensee plan to apply for?

(Please write N/A in any unit that does not apply or that is not planned for a power uprate.)

Unit 1 .4% Unit 2 1.1% Unit 3 1.6% Unit 4 IVA%

o What is the planned Increase from the CLTP limit in megawatts thermal?

Unit 1 42MWt Unit 2 42MWt Unit 3 4MWt Unit 4 NAMWt o What Isthe expected schedule for fMig the application (onth/year)? (Ifthe mnth is not known, please provide the quarter and/or year.)

Unit10*ML Unit2 MM. Unitt32017 Unit 4 NA o What is the expected date for power ascension with uprated conditions (month/year)?

Unit 1 1!,18 Unit 2 11/2017 Unit 3 512-OI Unit 4 V

3. The NRC staff may make the above information public, RA-15-0005 Atti" ment 6 Tabe Or E*maed Licesi Actions, H.S. Rbnsn Steam Eletc PNt
  • 1.

RA-15-0005 Page 1

1. For all planned licensing actions expected to be submitted in the next 3 calendar years, Robinson Unit 2 is providing the following information:

TABLE OF ESTIMATED UCENSING ACTIONS H. B, Robinson Stem Electric Plant Unit 2 Docket No. 50-261 uLCENSING LICENSING LICENSING ACTION PROJECTED OUTAGE COMMENTS (AS ACTION ACTION TYPE DESCRIPTION SUBMITTAL RELATED? IF SO, NEEDED)

NUMBER ___. DATE DATE NEEDED 1 License DPC-NE-2005 1st Quarter 2015 No Harris, Robinson Amendment Thermal Hydraulics combined submittal Request Statistical Core Design Methodology Revision of Existing Fuels Methodology Report Adoption into

.... ___ Tech Specs 2 License Adpt TSTF-339, Rev. 2, 2nd Quarter 2015 No Amendment "Relocate TS parametemr Request to COLFr_

3 License DPC-NE-1008 2nd Quarter 2015 No Harris, Robinson Amendment Nuclear Design combined submittal Request Methodology using CASMO-5/SIMULATE-3 New Fuels DPC-NE-3008 Methodology Reports Thermal-Hydraulic Adoption into Tech Transient Analysis Specs

_____ ______ ~~Methodology _ _ _ _ _ _ _ _ _ _

RA-15-0005 Page 2 4 License Merged Quality Assurance 2nd Quarter 2015 No Brunswick. Harris, Amendment Topical Report.- Catawba, McGuire, Request Oconee, Robinson combined submittal 5 License Revise Emergency Action 2nd Quarter 2015 No Amendment Levels consistent with Request NEI 99-01, Revision 6. _ _,

6 license Revise TS 3.1.4 and 3.1.7 2nd Quarter 2015 No Amendment to credit ERFIS as a Request means to monitor Rod Position Indication - _

7 License Plant Transmission 3rd Quarter 2015 Yes, Spring 2017 Amendment Interface Upgrades Request ,....

8 License Adopt TSTF-427, - 3rd Quarter 2015 No Brunswick, Harris, Amendment "Alowance for Non- Catawba, McGuire, Request Technical Specification Oconee, Robinson Barrier Degradation on combined submittal Supported System Op.erabilit? _......._..

9 License Adopt TSTF,522,*"Revise 3rd Quarter 2015 No Brunswick, Harris, Amendment Ventilation System Catawba, McGuire, Request Surveillance Requirements Oconee, Robinson to.Operate for 10 hours1.157407e-4 days <br />0.00278 hours <br />1.653439e-5 weeks <br />3.805e-6 months <br /> per combined submittal

__ Month"w _ _ _ _ _ _ _ _ _

RA-15-0005 Page 3 10 License DPC-NE-3009 4th Quarter 2015 No Harris, Robinson Amendment UFSAR Chapter 15S combined submittal Request Transient Analysis Methodology New and Revised DPC-NF-2010 Fuels Methodology NUclear*Physics . Reports Adoption into Methodology for Reload Tech Specs Design DPC-NE-201 1 Nuclear Design Methodology Report for Core Operating Limits of Westinghouse Reactors 11 License Extend Appendix J, Type A 4th Quarter 2015 Yes, Spring 2017 Amendment (ILRT) and Type C (LLRT)

Request Test Intervals 12 License Common Emergency 4th Quarter 2015 No Brunswick, Harris, Amendment Operations Facility Robinson combined Request, submittal 13 License Adopt new type of 2nd Quarter 2016 No Brunswick, Harris, Amendment respirator (Respirex) Robinson combined Request submittal 14 License DPC-NE-1003 2nd Quarter 2016 Yes, Spring 2018 Harris, Robinson Amendment Rod Swap Methodology combined submittal Request Report for Startup Physics Testing Revision of Existing Fuels Methodology Report 15 License 24-month fuel cycle 3rd Quarter 2016 Yes, Fall 2018 Amendment conversion Request I RA-15-0005 Page 4 16 License Adopt TSTF-412, Provide 4th Quarter 2016 No Amendment Actions for One Steam Request Supply to Turbine Driven AFWAEFW Pump

__oVer_- _

17 License 50.69 - Graded Quality 4th Quarter 2017 No Brunswick, Harris, Amendment Assurance Program Catawba, McGuire, Request Oconee, Robinson combined submittal

2. Robinson Unit 2 does not plan to apply for a power uprate in the next 5 calendar years
3. The NRC staff may make the above information public.