MONTHYEARRA-24-0012, Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report2024-02-0505 February 2024 Independent Spent Fuel Storage Installation - Annual Radioactive Effluent Release Report RA-24-0015, Submittal of 2023 Sea Turtle Annual Report2024-01-10010 January 2024 Submittal of 2023 Sea Turtle Annual Report RA-23-0325, Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX2024-01-0808 January 2024 Submittal of Procedures CSD-EP-HNP-0101-01, 02, CSD-EP-ONS-0101-01, CSD-EP-RNP-0101-01, and EP-RNP-EPLAN-ANNEX RA-24-0006, 10 CFR 50.54(q) Evaluation2024-01-0404 January 2024 10 CFR 50.54(q) Evaluation RA-23-0313, Baffle-Former Bolt (Bfb) Subsequent Inspection Interval Evaluation2023-12-14014 December 2023 Baffle-Former Bolt (Bfb) Subsequent Inspection Interval Evaluation RA-23-0306, Procedures CSD-EP-BNP-0101-01, EAL Technical Basis Document, Revision 006 and CSD-EP-CNS-0101-01, EAL Technical Basis Document, Revision 005, Summary Of.2023-12-12012 December 2023 Procedures CSD-EP-BNP-0101-01, EAL Technical Basis Document, Revision 006 and CSD-EP-CNS-0101-01, EAL Technical Basis Document, Revision 005, Summary Of. RA-23-0318, Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-12-0404 December 2023 Supplement to Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0284, RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation2023-11-16016 November 2023 RA-23-0284 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation RA-23-0276, Response to Request for Additional Information Regarding License Amendment Request to Align Certain Technical Specification Requirements with Industry Standards Provided in Improved Standard Technical Specific2023-11-0606 November 2023 Response to Request for Additional Information Regarding License Amendment Request to Align Certain Technical Specification Requirements with Industry Standards Provided in Improved Standard Technical Specific RA-23-0281, Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes2023-11-0101 November 2023 Procedure EP-ALL-EPLAN, Duke Energy Common Emergency Plan, Revision 5, Summary of Changes RA-23-0121, License Amendment Request to Adopt TSTF-258-A, Revision 4, Regarding Changes to Technical Specification Section 5.7, High Radiation Area2023-10-0505 October 2023 License Amendment Request to Adopt TSTF-258-A, Revision 4, Regarding Changes to Technical Specification Section 5.7, High Radiation Area RA-23-0218, Review Request for the Aging Management Program and Inspection Plan for the Shearon Harris Nuclear Power Plant, Unit 1, Reactor Vessel Internals2023-09-21021 September 2023 Review Request for the Aging Management Program and Inspection Plan for the Shearon Harris Nuclear Power Plant, Unit 1, Reactor Vessel Internals RA-23-0225, Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes2023-09-20020 September 2023 Procedure AD-EP-ALL-0109, Offsite Protective Action Recommendations, Revision 9, and the Joint Information Center (JIC) Relocation, Summary of Changes RA-22-0290, License Amendment Request to Exclude the Dynamic Effects of Specific Postulated Pipe Ruptures from the Design and Licensing Basis Based on Leak-Before-Break Methodology2023-08-30030 August 2023 License Amendment Request to Exclude the Dynamic Effects of Specific Postulated Pipe Ruptures from the Design and Licensing Basis Based on Leak-Before-Break Methodology RA-23-0216, Independent Spent Fuel Storage Installation, Registration of Use of Spent Fuel Casks2023-08-22022 August 2023 Independent Spent Fuel Storage Installation, Registration of Use of Spent Fuel Casks RA-23-0199, Response to Request for Additional Information (RAI) Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Inservice Inspection of the Torus Metallic Liner2023-08-18018 August 2023 Response to Request for Additional Information (RAI) Regarding Proposed Alternative in Accordance with 10 CFR 50.55a(z)(1) for Inservice Inspection of the Torus Metallic Liner RA-23-0122, License Amendment Request to Revise the 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors, Categorization Process to .2023-08-17017 August 2023 License Amendment Request to Revise the 10 CFR 50.69, Risk-Informed Categorization and Treatment of Structures, Systems and Components for Nuclear Power Reactors, Categorization Process to . RA-23-0195, Notice of Intentions Regarding Apparent Violation Response; (EA-23-060)2023-07-20020 July 2023 Notice of Intentions Regarding Apparent Violation Response; (EA-23-060) RA-23-0154, Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy - Response to Request for Additional Information Regarding Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0136, Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1)2023-07-20020 July 2023 Duke Energy Response to Request for Additional Information Regarding Proposed Alternative for Steam Generator Welds in Accordance with 10 CFR 50.55a(z)(1) RA-23-0141, Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule2023-07-12012 July 2023 Revision to Reactor Vessel Surveillance Capsule Withdrawal Schedule RA-23-0142, Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require2023-07-0707 July 2023 Mcguire, Units 1 and 2, Oconee, Units 1, 2, and 3, H. B. Robinson, Unit 2, Response to Request for Additional Information Regarding the License Amendment Request to Revise Restrictive Technical Specification Surveillance Require RA-23-0045, Inservice Inspection Program Owner'S Activity Report for Unit 2 Refueling Outage 262023-06-28028 June 2023 Inservice Inspection Program Owner'S Activity Report for Unit 2 Refueling Outage 26 RA-23-0145, Independent Spent Fuel Storage Installation (Isfsi), Registration for Use of General License Spent Fuel Casks2023-06-15015 June 2023 Independent Spent Fuel Storage Installation (Isfsi), Registration for Use of General License Spent Fuel Casks RA-23-0135, Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory2023-06-0707 June 2023 Submittal of 30 Day Report Per 10 CFR 26.719(c), Unsatisfactory Performance of Health and Human Services Certified Laboratory RA-23-0139, Registration for Use of General License Spent Fuel Casks2023-06-0606 June 2023 Registration for Use of General License Spent Fuel Casks RA-23-0120, Supplemental Information Regarding Addition of Feedwater Isolation on Steam Generator Level High-High to Technical Specification 3.3.22023-05-31031 May 2023 Supplemental Information Regarding Addition of Feedwater Isolation on Steam Generator Level High-High to Technical Specification 3.3.2 RA-23-0005, License Amendment Request to Align Certain Technical Specification Requirements with Industry Standards Provided in Improved Standard Technical Specifications2023-05-31031 May 2023 License Amendment Request to Align Certain Technical Specification Requirements with Industry Standards Provided in Improved Standard Technical Specifications RA-23-0041, Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations2023-05-30030 May 2023 Response to NRC Regulatory Issue Summary 2023-01 Preparation and Scheduling of Operator Licensing Examinations RA-23-0047, Duke Energy Annual Radiological Environmental Operating Report - 20222023-04-26026 April 2023 Duke Energy Annual Radiological Environmental Operating Report - 2022 RA-23-0044, Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.462023-04-26026 April 2023 Aduke Energy Annual Report of Changes Pursuant to 10 CFR 50.46 RA-23-0064, Inservice Testing Program Plan and Snubber Program Plan for Sixth 10-Year Inservice Testing (1ST) Program Interval2023-04-24024 April 2023 Inservice Testing Program Plan and Snubber Program Plan for Sixth 10-Year Inservice Testing (1ST) Program Interval RA-23-0046, Annual Radioactive Effluent Release Report - 20222023-04-24024 April 2023 Annual Radioactive Effluent Release Report - 2022 RA-23-0098, Annual Environmental (Nonradiological) Operating Report2023-04-19019 April 2023 Annual Environmental (Nonradiological) Operating Report RA-23-0096, Post Accident Monitoring (PAM) Instrumentation Report2023-04-12012 April 2023 Post Accident Monitoring (PAM) Instrumentation Report RA-23-0063, Notification of Deviation from BWRVIP Guidelines2023-04-11011 April 2023 Notification of Deviation from BWRVIP Guidelines RA-23-0080, Refueling Outage 32 Steam Generator Tube Inspection Report Supplement Pursuant to Technical Specifications Task Force (TSTF) Traveler TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube2023-04-0505 April 2023 Refueling Outage 32 Steam Generator Tube Inspection Report Supplement Pursuant to Technical Specifications Task Force (TSTF) Traveler TSTF-577, Revision 1, Revised Frequencies for Steam Generator Tube RA-23-0043, Refuel 33 (R2R33) Inservice Inspection Program Ninety Day Owner'S Activity Report and Analytical Evaluations2023-03-30030 March 2023 Refuel 33 (R2R33) Inservice Inspection Program Ninety Day Owner'S Activity Report and Analytical Evaluations RA-23-0036, Biennial Decommissioning Financial Assurance Reports2023-03-30030 March 2023 Biennial Decommissioning Financial Assurance Reports RA-23-0040, Onsite Property Insurance Coverage2023-03-30030 March 2023 Onsite Property Insurance Coverage RA-23-0039, 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums2023-03-30030 March 2023 10 CFR 140.21 Licensee Guarantees of Payment of Deferred Premiums RA-23-0055, Notice of Intent to Pursue Subsequent License Renewal for H. B. Robinson Steam Electric Plant, Unit Number 22023-03-24024 March 2023 Notice of Intent to Pursue Subsequent License Renewal for H. B. Robinson Steam Electric Plant, Unit Number 2 RA-23-0021, Unit 2 Cycle 26 Core Operating Limits Report (COLR)2023-02-22022 February 2023 Unit 2 Cycle 26 Core Operating Limits Report (COLR) RA-22-0257, Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1)2023-02-17017 February 2023 Proposed Alternative for Pressurizer Welds in Accordance with 10 CFR 50.55a(z)(1) RA-22-0091, Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements2023-02-16016 February 2023 Application to Revise Technical Specifications to Adopt TSTF-554, Revision 1, Revise Reactor Coolant Leakage Requirements RA-23-0015, Response to Request for Additional Information (RAI) Regarding Addition of Feedwater Isolation on Steam Generator Level High-High to Technical Specification 3.3.22023-02-0909 February 2023 Response to Request for Additional Information (RAI) Regarding Addition of Feedwater Isolation on Steam Generator Level High-High to Technical Specification 3.3.2 RA-22-0081, License Amendment Request to Address Administrative Changes to the Operating License and Technical Specifications2023-02-0707 February 2023 License Amendment Request to Address Administrative Changes to the Operating License and Technical Specifications RA-23-0001, Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI2023-02-0202 February 2023 Request to Use a Provision of a Later Edition and Addenda of the ASME Boiler and Pressure Vessel Code, Section XI RA-22-0118, License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies2023-02-0101 February 2023 License Amendment Request to Revise Restrictive Technical Specification Surveillance Requirement Frequencies RA-23-0029, Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable Containment Sump Water Level (Wide Range)2023-01-30030 January 2023 Technical Specifications Section 5.6.6 Post Accident Monitoring Instrumentation Report for Inoperable Containment Sump Water Level (Wide Range) 2024-02-05
[Table view] |
Text
Progress Energy 10 CFR 50.54(w)(3)
PO Box 1551 411 Fayetteville Street Mall Raleigh NC 27602 Serial: RA- 11-006 February 23, 2011 ATTN: Document Control Desk United States Nuclear Regulatory Commission Washington, DC 20555-0001 BRUNSWICK STEAM ELECTRIC PLANT, UNIT NOS. 1 AND 2 DOCKET NOS. 50-325 AND 50-324 / RENEWED LICENSE NOS. DPR-71 AND DPR-62 SHEARON HARRIS NUCLEAR POWER PLANT, UNIT NO. 1 DOCKET NO. 50-400 / RENEWED LICENSE NO. NPF-63 H. B. ROBINSON STEAM ELECTRIC PLANT, UNIT NO. 2 DOCKET NO. 50-261 / RENEWED LICENSE NO. DPR-23 CRYSTAL RIVER UNIT 3 NUCLEAR GENERATING PLANT DOCKET NO. 50-302 / LICENSE NO. DPR-72 ONSITE PROPERTY INSURANCE COVERAGE Ladies and Gentlemen:
Pursuant to 10 CFR 50.54(w)(3) regarding onsite property damage insurance, Carolina Power
& Light Company (CP&L), now doing business as Progress Energy Carolinas, Inc., (PEC),
and Florida Power Corporation (FPC), now doing business as Progress Energy Florida, Inc.,
(PEF), hereby submit information regarding the present level and source of onsite property damage insurance for the Brunswick Steam Electric Plant, Unit Nos. 1 and 2; the Shearon Harris Nuclear Power Plant, Unit No. 1; the H. B. Robinson Steam Electric Plant, Unit No. 2; and the Crystal River Unit 3 Nuclear Generating Plant. This information is required to be submitted to the United States Nuclear Regulatory Commission by April 1 of each year.
Insured Site - Brunswick Company: Nuclear Electric Insurance Limited Policy No.: P 10-003 (renewal date April 1, 2011)
Limits: $500,000,000 (Primary)
Company: Nuclear Electric Insurance Limited Policy No.: X10-004 (renewal date April 1, 2011)
Limits: $750,000,000 (Excess)
Insured Site - Crystal River Company: Nuclear Electric Insurance Limited Policy No.: P10-081 (renewal date April 1, 2011)
Limits: $500,000,000 (Primary)
Company: Nuclear Electric Insurance Limited Policy No.: X 10-015 (renewal date April 1, 2011)
Limits: $750,000,000 (Excess) 0 cý ý Q CC
United States Nuclear Regulatory Commission RA- 11-006 Page 2 Insured Site - Shearon Harris Company: Nuclear Electric Insurance Limited Policy No.: P 10-004 (renewal date April 1, 2011)
Limits: $500,000,000 (Primary)
Company: Nuclear Electric Insurance Limited Policy No.: X10-070 (renewal date April 1, 2011)
Limits: $750,000,000 (Excess)
Insured Site - Robinson Company: Nuclear Electric Insurance Limited Policy No.: P 10-005 (renewal date April 1, 2011)
Limits: $500,000,000 (Primary)
Company: Nuclear Electric Insurance Limited Policy No.: X10-005 (renewal date April 1, 2011)
Limits: $750,000,000 (Excess)
Insured Sites - Brunswick, Crystal River, Harris, Robinson Company: Nuclear Electric Insurance Limited Policy No.: BX 10-004 (renewal date April 1, 2011)
Limits: $1,000,000,000 (Blanket Excess)
No new regulatory commitments have been made in this submittal. If you have additional questions, please call me at (919) 546-4579.
Sincerely, Brian McCabe Manager - Nuclear Regulatory Affairs BCM/adz c: V. M. McCree, USNRC Regional Administrator - Region II F. E. Saba, NRR Project Manager - BSEP, Unit Nos. 1 and 2; CR3 B. L. Mozafari, NRR Project Manager - SHNPP, Unit No. 1; HBRSEP, Unit No. 2 USNRC Resident Inspector - BSEP, Unit Nos. 1 and 2 USNRC Resident Inspector - CR3 USNRC Resident Inspector - SHNPP, Unit No. 1 USNRC Resident Inspector - HBRSEP, Unit No. 2 E. S. Finley, Jr. - Chairman - North Carolina Utilities Commission R. Vance - North Carolina Utilities Commission S. Watson - North Carolina Utilities Commission W. L. Cox, III -Section Chief, North Carolina Department of Environment and Natural Resources