Category:Press Release
MONTHYEARML24047A3052023-07-10010 July 2023 News Release-IV-23-007: NRC Names Nathan Brown Resident Inspector at Callaway Nuclear Power Plant ML23163A0512023-02-27027 February 2023 News Release-IV-23-002: NRC Names Scott Schwind Senior Resident Inspector at Callaway Nuclear Power Plant ML22131A1532022-04-25025 April 2022 News Release-IV-22-003-: NRC Names New Resident Inspector at Callaway Nuclear Power Plant ML22067A0642022-03-0707 March 2022 News Release-22-011: NRC Issues Annual Assessments for Nation'S Nuclear Power Plants Press Release-IV-21-009, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Callaway Nuclear Power Plant2021-07-13013 July 2021 Press Release-IV-21-009: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Callaway Nuclear Power Plant Press Release-IV-20-007, NRC to Hold Virtual Meeting to Discuss 2019 Performance of 12 Region IV Nuclear Power Plants2020-06-22022 June 2020 Press Release-IV-20-007: NRC to Hold Virtual Meeting to Discuss 2019 Performance of 12 Region IV Nuclear Power Plants Press Release-IV-17-016, NRC Names New Resident Inspector at Callaway Nuclear Power Plant2017-08-0707 August 2017 Press Release-IV-17-016: NRC Names New Resident Inspector at Callaway Nuclear Power Plant ML17151A2312017-05-30030 May 2017 Press Release-IV-17-012: NRC Names New Senior Resident Inspector at the Callaway Nuclear Power Plant Press Release-IV-17-012, NRC Names New Senior Resident Inspector at the Callaway Nuclear Power Plant2017-05-30030 May 2017 Press Release-IV-17-012: NRC Names New Senior Resident Inspector at the Callaway Nuclear Power Plant Press Release-15-068, NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors2015-10-27027 October 2015 Press Release-15-068: NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors Press Release-IV-15-028, - NRC to Begin Special Inspection at Callaway Nuclear Station2015-09-21021 September 2015 Press Release-IV-15-028 - NRC to Begin Special Inspection at Callaway Nuclear Station Press Release-15-014, NRC Renews Operating License of Callaway Nuclear Plant in Missouri2015-03-0606 March 2015 Press Release-15-014: NRC Renews Operating License of Callaway Nuclear Plant in Missouri Press Release-IV-15-004, NRC Names New Resident Inspector at Callaway Nuclear Plant2015-01-26026 January 2015 Press Release-IV-15-004: NRC Names New Resident Inspector at Callaway Nuclear Plant ML15026A7292015-01-26026 January 2015 Press Release-IV-15-004: NRC Names New Resident Inspector at Callaway Nuclear Plant Press Release-14-080, NRC Issues Final Environmental Impact Statement for Callaway Nuclear Power Plant License Renewal2014-11-17017 November 2014 Press Release-14-080: NRC Issues Final Environmental Impact Statement for Callaway Nuclear Power Plant License Renewal Press Release-14-057, NRC Issues Final Safety Evaluation Report for Callaway Nuclear Power Plant License Renewal Application2014-08-28028 August 2014 Press Release-14-057: NRC Issues Final Safety Evaluation Report for Callaway Nuclear Power Plant License Renewal Application Press Release-14-009, NRC Seeks Public Comment on Draft Environmental Report for Callaway Nuclear Plant License Renewal - Meetings Scheduled for March 192014-02-21021 February 2014 Press Release-14-009: NRC Seeks Public Comment on Draft Environmental Report for Callaway Nuclear Plant License Renewal - Meetings Scheduled for March 19 Press Release-IV-13-001, NRC to Discuss Preliminary Results of Inspection for Callaway Nuclear Plant License Renewal Application2013-01-0808 January 2013 Press Release-IV-13-001: NRC to Discuss Preliminary Results of Inspection for Callaway Nuclear Plant License Renewal Application Press Release-12-099, NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants2012-09-0606 September 2012 Press Release-12-099: NRC Issues Mid-Cycle Assessments for Nation? Nuclear Plants Press Release-12-058, Atomic Safety and Licensing Board to Hold Prehearing Conference on Callaway Nuclear Plant License Renewal2012-05-17017 May 2012 Press Release-12-058: Atomic Safety and Licensing Board to Hold Prehearing Conference on Callaway Nuclear Plant License Renewal Press Release-IV-12-014, NRC Names New Senior Resident Inspector at Callaway Nuclear Power Plant2012-04-25025 April 2012 Press Release-IV-12-014: NRC Names New Senior Resident Inspector at Callaway Nuclear Power Plant Press Release-12-018, NRC Announces Hearing Opportunity, Public Meeting on Callaway Nuclear Power Plant License Renewal Application2012-02-24024 February 2012 Press Release-12-018: NRC Announces Hearing Opportunity, Public Meeting on Callaway Nuclear Power Plant License Renewal Application Press Release-11-229, NRC Announces Availability of License Renewal Application for Callaway Nuclear Power Plant2011-12-29029 December 2011 Press Release-11-229: NRC Announces Availability of License Renewal Application for Callaway Nuclear Power Plant Press Release-IV-11-041, NRC Names New Resident Inspector at Callaway Nuclear Power Plant2011-09-12012 September 2011 Press Release-IV-11-041: NRC Names New Resident Inspector at Callaway Nuclear Power Plant Press Release-IV-11-013, NRC to Hold Open House to Discuss 2010 Performance of Callaway Nuclear Plant2011-04-19019 April 2011 Press Release-IV-11-013: NRC to Hold Open House to Discuss 2010 Performance of Callaway Nuclear Plant Press Release-IV-11-007, NRC Sends Special Inspection Team to Callaway Nuclear Plant2011-03-21021 March 2011 Press Release-IV-11-007: NRC Sends Special Inspection Team to Callaway Nuclear Plant Press Release-10-154, National Academy of Sciences Seeks Nominations for Experts to Conduct NRC-Sponsored Cancer Risk Study2010-09-0303 September 2010 Press Release-10-154: National Academy of Sciences Seeks Nominations for Experts to Conduct NRC-Sponsored Cancer Risk Study Press Release-IV-10-018, NRC to Hold Open House to Discuss 2009 Performance of Callaway Nuclear Plant2010-04-26026 April 2010 Press Release-IV-10-018: NRC to Hold Open House to Discuss 2009 Performance of Callaway Nuclear Plant Press Release-IV-09-024, NRC Conducting Special Inspection at Callaway Nuclear Plant2009-06-22022 June 2009 Press Release-IV-09-024: NRC Conducting Special Inspection at Callaway Nuclear Plant Press Release-IV-09-016, NRC to Discuss 2008 Performance Assessment for Callaway Nuclear Plant2009-05-14014 May 2009 Press Release-IV-09-016: NRC to Discuss 2008 Performance Assessment for Callaway Nuclear Plant Press Release-08-225, NRC Accepts Application for New Reactor at Callaway2008-12-15015 December 2008 Press Release-08-225: NRC Accepts Application for New Reactor at Callaway Press Release-08-175, Callaway Application for New Reactor Available on NRC Website2008-09-19019 September 2008 Press Release-08-175: Callaway Application for New Reactor Available on NRC Website Press Release-IV-08-019, NRC to Discuss 2007 Performance Assessment for Callaway Nuclear Plant2008-05-16016 May 2008 Press Release-IV-08-019: NRC to Discuss 2007 Performance Assessment for Callaway Nuclear Plant Press Release-IV-07-035, - NRC Names New Senior Resident Inspector at Callaway Nuclear Plant2007-09-18018 September 2007 Press Release-IV-07-035 - NRC Names New Senior Resident Inspector at Callaway Nuclear Plant Press Release-IV-07-015, NRC to Discuss 2006 Performance Assessment for Callaway Nuclear Plant2007-05-24024 May 2007 Press Release-IV-07-015: NRC to Discuss 2006 Performance Assessment for Callaway Nuclear Plant Press Release-IV-06-005, NRC to Discuss 2005 Performance at Callaway Nuclear Plant2006-04-27027 April 2006 Press Release-IV-06-005: NRC to Discuss 2005 Performance at Callaway Nuclear Plant Press Release-IV-05-013, NRC to Discuss 2004 Performance Assessment for Callaway Nuclear Plant2005-04-18018 April 2005 Press Release-IV-05-013: NRC to Discuss 2004 Performance Assessment for Callaway Nuclear Plant Press Release-IV-04-036, NRC Assigns New Resident Inspector to Callaway Nuclear Plant2004-09-14014 September 2004 Press Release-IV-04-036: NRC Assigns New Resident Inspector to Callaway Nuclear Plant Press Release-IV-04-013, NRC to Meet with Union Electric Co. to Discuss Performance of Callaway Nuclear Power Plant2004-03-24024 March 2004 Press Release-IV-04-013: NRC to Meet with Union Electric Co. to Discuss Performance of Callaway Nuclear Power Plant Press Release-IV-03-028, NRC Cites Callaway Nuclear Plant for Violation of Low to Moderate Safety Significance2003-06-23023 June 2003 Press Release-IV-03-028: NRC Cites Callaway Nuclear Plant for Violation of Low to Moderate Safety Significance Press Release-IV-03-008, NRC to Meet with Union Electric Co. to Discuss Performance of Callaway Nuclear Power Plant2003-03-20020 March 2003 Press Release-IV-03-008: NRC to Meet with Union Electric Co. to Discuss Performance of Callaway Nuclear Power Plant Press Release-IV-02-044, Michael Peck Named NRC Senior Resident Inspector at Callaway2002-10-18018 October 2002 Press Release-IV-02-044: Michael Peck Named NRC Senior Resident Inspector at Callaway Press Release-IV-02-022, NRC to Meet with Amerenue to Discuss Safety Performance at Callaway2002-04-16016 April 2002 Press Release-IV-02-022: NRC to Meet with Amerenue to Discuss Safety Performance at Callaway Press Release-IV-02-004, NRC to Meet with Ameren to Discuss Inspection Results2002-02-20020 February 2002 Press Release-IV-02-004: NRC to Meet with Ameren to Discuss Inspection Results Press Release-IV-02-003, NRC Dispatches Inspection Team to Callaway2002-01-31031 January 2002 Press Release-IV-02-003: NRC Dispatches Inspection Team to Callaway 2023-07-10
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs, Region IV 611 Ryan Plaza Drive - Suite 400 Arlington TX 76011-4005 No. IV-03-008 March 20, 2003 CONTACT: Victor Dricks E-mail: opa4@nrc.gov Phone: 817-860-8128 NRC TO MEET WITH UNION ELECTRIC CO. TO DISCUSS PERFORMANCE OF CALLAWAY NUCLEAR POWER PLANT Nuclear Regulatory Commission staff will meet with representatives of the Union Electric Company on Tuesday, April 1, to discuss the results of the agencys annual assessment of safety performance at the Callaway Nuclear Plant. The facility is located near Fulton, Missouri.
The meeting, which will be open to the public for observation, is scheduled to begin at 7:00 p.m. at the Capitol Plaza Hotel & Convention Center, 415 West McCarty Street, Jefferson City, Mo.
Before the session is adjourned, NRC staff will be available to answer questions from the public on the safety performance of the plant, as well as the role of the NRC in ensuring safe plant operation.
The performance period to be discussed is January 1 to December 31, 2002. In addition, NRC staff will provide an overview of how the agencys Reactor Oversight Process works.
A letter sent from the NRC Region IV Office to representatives of the Union Electric Co.
addresses the performance of the plant during the period and will serve as the basis for the meeting discussion. It is available on the NRC web site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/LETTERS/call_2002q4.pdf Overall, Callaway Plant operated in a manner that preserved public health and safety and met all cornerstone objectives with moderate degradation in safety performance, the letter states.
However, during the first quarter of 2002, the licensee failed to promptly identify and correct a problem - the presence of foreign material in a large water storage tank. This rendered inoperable the plants auxiliary feedwater system, which provides water to the plants steam generators under some conditions.
Additionally, Callaway has had difficulties with problem identification and resolution. The NRC plans to conduct an additional inspection of these areas in June, to determine whether improvements have been made.
In addition, the letter notes: As you are aware, since the terrorist attacks on September 11, 2001, the NRC has issued several Orders and threat advisories to enhance security capabilities and improve guard force readiness. We have conducted inspections to review your implementation of
these requirements and have monitored your actions in response to changing threat advisories. For calendar year 2003, we plan to continue these inspections and conduct portions of the security baseline inspection program, as well as perform additional inspections to evaluate your compliance with new requirements that may be ordered.
Current performance information for Callaway is available on the NRC web site at:
http://www.nrc.gov/NRR/OVERSIGHT/ASSESS/CALL/call_chart.html