Category:Press Release
MONTHYEARML23165A2342023-03-0303 March 2023 News Release-23-019: NRC Issues Annual Assessments for Nations Nuclear Power Plants ML22199A0622022-06-15015 June 2022 News Release-III-22-016: NRC to Hold Public Meeting to Discuss 2021 Performance of Davis-Besse Nuclear Power Plant ML22067A0642022-03-0707 March 2022 News Release-22-011: NRC Issues Annual Assessments for Nation'S Nuclear Power Plants ML22063A4672022-03-0303 March 2022 News Release-III-22-003: NRC Finalizes White Finding at Davis-Besse Nuclear Power Plant ML22028A0492022-01-26026 January 2022 News Release-III-22-001: NRC Schedules a Regulatory Conference with Energy Harbor Nuclear Corp Press Release-III-21-010, NRC to Hold Virtual Meeting to Discuss 2020 Performance of Davis-Besse and Perry Nuclear Power Plants2021-06-15015 June 2021 Press Release-III-21-010: NRC to Hold Virtual Meeting to Discuss 2020 Performance of Davis-Besse and Perry Nuclear Power Plants Press Release-III-21-005, NRC Names New Resident Inspector at Davis-Besse Nuclear Power Plant2021-04-28028 April 2021 Press Release-III-21-005: NRC Names New Resident Inspector at Davis-Besse Nuclear Power Plant Press Release-III-20-008, NRC to Hold Virtual Meeting to Discuss 2019 Performance of Davis-Besse and Perry Nuclear Power Plants2020-07-16016 July 2020 Press Release-III-20-008: NRC to Hold Virtual Meeting to Discuss 2019 Performance of Davis-Besse and Perry Nuclear Power Plants Press Release-19-061, NRC Approves License Transfers for Firstenergy Nuclear Power Plants2019-12-0303 December 2019 Press Release-19-061: NRC Approves License Transfers for Firstenergy Nuclear Power Plants Press Release-III-19-020, NRC Names New Senior Resident Inspector at Clinton Nuclear Power Station2019-10-0202 October 2019 Press Release-III-19-020: NRC Names New Senior Resident Inspector at Clinton Nuclear Power Station Press Release-III-19-017, NRC to Hold Open House to Discuss 2018 Performance of Davis-Besse Nuclear Power Station2019-07-10010 July 2019 Press Release-III-19-017: NRC to Hold Open House to Discuss 2018 Performance of Davis-Besse Nuclear Power Station Press Release-III-18-021, NRC to Hold Public Meeting to Discuss Performance of Davis-Besse Nuclear Power Station2018-06-13013 June 2018 Press Release-III-18-021: NRC to Hold Public Meeting to Discuss Performance of Davis-Besse Nuclear Power Station Press Release-III-18-004, NRC Names New Resident Inspector at Davis-Besse Nuclear Power Plant2018-02-0707 February 2018 Press Release-III-18-004: NRC Names New Resident Inspector at Davis-Besse Nuclear Power Plant Press Release-III-17-021, NRC to Conduct Open House to Discuss 2016 Performance of Davis-Besse Nuclear Power Plant2017-07-0707 July 2017 Press Release-III-17-021: NRC to Conduct Open House to Discuss 2016 Performance of Davis-Besse Nuclear Power Plant Press Release-III-16-022, NRC Issues Confirmatory Order to Firstenergy Regarding Davis-Besse Nuclear Station2016-09-0202 September 2016 Press Release-III-16-022: NRC Issues Confirmatory Order to Firstenergy Regarding Davis-Besse Nuclear Station Press Release-III-16-014, NRC to Hold Open House to Discuss Agency'S Assessment of Davis-Besse Nuclear Plant2016-06-13013 June 2016 Press Release-III-16-014: NRC to Hold Open House to Discuss Agency'S Assessment of Davis-Besse Nuclear Plant Press Release-16-011, NRC Issues Annual Assessments for Nation'S Nuclear Plants2016-03-0404 March 2016 Press Release-16-011: NRC Issues Annual Assessments for Nation'S Nuclear Plants Press Release-15-082, NRC Renews Operating License of Davis-Besse Nuclear Power Plant in Ohio2015-12-0808 December 2015 Press Release-15-082: NRC Renews Operating License of Davis-Besse Nuclear Power Plant in Ohio Press Release-15-054, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2015-09-0303 September 2015 Press Release-15-054: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-III-15-016, NRC Schedules Open House June 11 to Discuss Performance of Davis-Besse Nuclear Plant2015-06-0202 June 2015 Press Release-III-15-016: NRC Schedules Open House June 11 to Discuss Performance of Davis-Besse Nuclear Plant ML15118A5852015-04-28028 April 2015 Press Release No.15-028: NRC Issues Final Environmental Impact Statement for Davis-Besse Nuclear Power Plant License Renewal Press Release-III-14-033, NRC Schedules Open House August 7 to Discuss Performance of Davis-Besse Nuclear Power Station2014-07-28028 July 2014 Press Release-III-14-033: NRC Schedules Open House August 7 to Discuss Performance of Davis-Besse Nuclear Power Station Press Release-14-019, NRC Seeks Public Comment on Draft Environmental Report for Davis-Besse Nuclear Plant License Renewal - Meetings Scheduled for March 252014-03-13013 March 2014 Press Release-14-019: NRC Seeks Public Comment on Draft Environmental Report for Davis-Besse Nuclear Plant License Renewal - Meetings Scheduled for March 25 Press Release-III-14-004, NRC Regional Office to Discuss Davis-Besse Steam Generator Installation: Webinar to Be Held on February 202014-02-11011 February 2014 Press Release-III-14-004: NRC Regional Office to Discuss Davis-Besse Steam Generator Installation: Webinar to Be Held on February 20 Press Release-I-13-032, NRC Staff to Meet with Firstenergy on Sept. 24 in Coraopolis, Pa. to Discuss Performance of Company & Nuclear Power Plants2013-09-16016 September 2013 Press Release-I-13-032: NRC Staff to Meet with Firstenergy on Sept. 24 in Coraopolis, Pa. to Discuss Performance of Company & Nuclear Power Plants Press Release-13-073, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2013-09-0606 September 2013 Press Release-13-073: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-13-074, NRC Issues Final Safety Evaluation Report for Davis-Besse License Renewal Application2013-09-0606 September 2013 Press Release-13-074: NRC Issues Final Safety Evaluation Report for Davis-Besse License Renewal Application Press Release-III-13-021, NRC Will Hold a June 11 Open House on Davis-Besse Nuclear Power Plant 2012 Performance2013-06-0303 June 2013 Press Release-III-13-021: NRC Will Hold a June 11 Open House on Davis-Besse Nuclear Power Plant 2012 Performance Press Release-III-13-003, NRC Names New Resident Inspector at Davis-Besse Nuclear Power Plant2013-01-29029 January 2013 Press Release-III-13-003: NRC Names New Resident Inspector at Davis-Besse Nuclear Power Plant Press Release-12-118, ASLB to Hear Oral Arguments Nov. 5-6 on Contention Regarding Cracks in Davis-Besse Shield Building2012-10-24024 October 2012 Press Release-12-118: ASLB to Hear Oral Arguments Nov. 5-6 on Contention Regarding Cracks in Davis-Besse Shield Building Press Release-III-12-037, NRC, Firstenergy Nuclear Operating Co. to Discuss Company Nuclear Plants on Sept. 262012-09-20020 September 2012 Press Release-III-12-037: NRC, Firstenergy Nuclear Operating Co. to Discuss Company Nuclear Plants on Sept. 26 Press Release-III-12-033, NRC Schedules Public Meeting August 15 to Discuss Performance of Davis-Besse Nuclear Power Station2012-08-0707 August 2012 Press Release-III-12-033: NRC Schedules Public Meeting August 15 to Discuss Performance of Davis-Besse Nuclear Power Station Press Release-III-12-032, NRC to Hold Public Meeting to Discuss Its Review of Fenoc'S Root Cause Analysis of Davis-Besse Shield Building Cracks2012-08-0202 August 2012 Press Release-III-12-032: NRC to Hold Public Meeting to Discuss Its Review of Fenoc'S Root Cause Analysis of Davis-Besse Shield Building Cracks Press Release-12-087, NRC Issues Safety Evaluation Report with Open Items for Davis-Besse Nuclear Plant License Renewal Application2012-08-0101 August 2012 Press Release-12-087: NRC Issues Safety Evaluation Report with Open Items for Davis-Besse Nuclear Plant License Renewal Application Press Release-III-12-023, NRC Concludes Its Review of Fenoc'S Root Cause Analysis of Davis-Besse Shield Building Cracks2012-06-21021 June 2012 Press Release-III-12-023: NRC Concludes Its Review of Fenoc'S Root Cause Analysis of Davis-Besse Shield Building Cracks Press Release-12-057, Atomic Safety and Licensing Board Cancels Oral Arguments in Davis-Besse License Renewal Hearing Scheduled for May 182012-05-15015 May 2012 Press Release-12-057: Atomic Safety and Licensing Board Cancels Oral Arguments in Davis-Besse License Renewal Hearing Scheduled for May 18 Press Release-12-047, Atomic Safety and Licensing Board to Hold Oral Arguments May 18 on Davis-Besse Shield Building Cracking2012-05-0202 May 2012 Press Release-12-047: Atomic Safety and Licensing Board to Hold Oral Arguments May 18 on Davis-Besse Shield Building Cracking Press Release-III-12-007, NRC Begins Review of Fenoc'S Root Cause Analysis of Davis-Besse Shield Building Cracks2012-02-28028 February 2012 Press Release-III-12-007: NRC Begins Review of Fenoc'S Root Cause Analysis of Davis-Besse Shield Building Cracks Press Release-III-11-037, NRC to Hold Meeting with Firstenergy to Discuss Davis-Besse Shield Building Cracks2011-12-29029 December 2011 Press Release-III-11-037: NRC to Hold Meeting with Firstenergy to Discuss Davis-Besse Shield Building Cracks ML12200A2272011-12-0303 December 2011 Email from J. Zimmerman, NRR to M. Evans, NRR Et Al. Fw: Press Release Has Been Issued. Attachment Is Publicly Available Press Release-III-11-036, NRC Concludes Davis-Besse Nuclear Plant Safe to Restart and Issues Confirmatory Action Letter2011-12-0202 December 2011 Press Release-III-11-036: NRC Concludes Davis-Besse Nuclear Plant Safe to Restart and Issues Confirmatory Action Letter ML1133606772011-12-0202 December 2011 Press Release-iiii-11-036: NRC Concludes Davis-Besse Nuclear Plant Safe to Restart and Issues Confirmatory Action Letter Press Release-III-11-035, NRC Responds to Alert at Davis-Besse Nuclear Power Station2011-11-16016 November 2011 Press Release-III-11-035: NRC Responds to Alert at Davis-Besse Nuclear Power Station Press Release-11-016, Licensing Board to Hear Oral Argument March 1 on Davis-Besse Reactor License Renewal Application2011-02-0303 February 2011 Press Release-11-016: Licensing Board to Hear Oral Argument March 1 on Davis-Besse Reactor License Renewal Application ML1030100692010-10-28028 October 2010 Press Release-10-193: NRC to Conduct Environmental Scoping Meeting as Part of the License Renewal Application for Davis Besse; Meeting Nov. 4 Press Release-10-193, NRC to Conduct Environmental Scoping Meeting as Part of the License Renewal Application for Davis Besse; Meeting Nov. 42010-10-28028 October 2010 Press Release-10-193: NRC to Conduct Environmental Scoping Meeting as Part of the License Renewal Application for Davis Besse; Meeting Nov. 4 Press Release-10-191, NRC Announces Opportunity for Hearing on Application to Renew Operating License for Davis-Besse Nuclear Power Plant2010-10-26026 October 2010 Press Release-10-191: NRC Announces Opportunity for Hearing on Application to Renew Operating License for Davis-Besse Nuclear Power Plant Press Release-10-164, NRC Announces Availability of License Renewal Application for Davis-Besse Nuclear Plant2010-09-20020 September 2010 Press Release-10-164: NRC Announces Availability of License Renewal Application for Davis-Besse Nuclear Plant Press Release-10-154, National Academy of Sciences Seeks Nominations for Experts to Conduct NRC-Sponsored Cancer Risk Study2010-09-0303 September 2010 Press Release-10-154: National Academy of Sciences Seeks Nominations for Experts to Conduct NRC-Sponsored Cancer Risk Study Press Release-III-10-034, NRC Schedules Public Meeting to Discuss Special Inspection Team Results for Davis-Besse Nuclear Power Plant2010-08-25025 August 2010 Press Release-III-10-034: NRC Schedules Public Meeting to Discuss Special Inspection Team Results for Davis-Besse Nuclear Power Plant 2023-03-03
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Region III 2443 Warrenville Road Lisle IL 60532 No. III-10-022.C Contacts: May 26, 2010 Viktoria Mitlyng 630-829-9662 E-Mail: opa3@nrc.gov Prema Chandrathil 630-829-9663 Web site: www.nrc.gov
NRC ASKS FENOC TO DISCUSS BASIS FOR DAVIS-BESSE PLANT RESTART AT PUBLIC MEETING JUNE 3 The Nuclear Regulatory Commission (NRC) staff will meet with representatives of FirstEnergy Nuclear Operating Company (FENOC) on Thursday, June 3, to obtain information about the suitability of tests and repairs of Control Rod Drive Mechanism (CRDM) nozzles and the technical basis for the companys decision to start up the Davis-Besse nuclear station. The plant is located in Oak Harbor, Ohio, roughly 40 miles southeast of Toledo.
The NRC and the public need to have confidence that Davis-Besse will operate safely after it returns to service, said Mark Satorius, regional administrator of NRC Region III office in Lisle, Ill.
Thats why we called on FirstEnergy to tell us in a public forum if they understand what happened, if they are confident in their repairs; and how they will ensure the integrity of the reactor vessel head moving forward.
On March 12, 2010, while performing NRC-required inspections of CRDM nozzles at the Davis-Besse Nuclear Power Plant, workers discovered indications of cracks in multiple nozzles that penetrate the reactor vessel head and are designed to guide the control rods into the reactor core to shut down the reactor. Additionally, a small amount boric acid was found during examinations of the outer surface of the reactor vessel head.
There was no danger to the public from these cracks. The plant has been in a refueling outage since the problem was identified.
On March 16, 2010, the NRC dispatched a Special Inspection Team to Davis-Besse to review the circumstances surrounding the discovery of crack indications in multiple CRDM nozzles. The team has monitored and reviewed First Energys testing methods, analysis of flaws, conclusions concerning the number of nozzles to be repaired, the proposed repair method and the repair process. NRC inspectors have monitored the utilitys testing and repair activities real-time - including coverage of these activities on weekends - asking questions and addressing issues the utility had to immediately address.
In addition, the NRC has contracted with a government national laboratory to perform an independent analysis of First Energy's ultrasonic testing (UT) data. While the Special Inspection Team is also working to verify the adequacy of the utilitys analysis, this independent review will provide the
NRC with additional validation of the quality of the licensee's assessment of their examination results.
The inspection team will remain onsite to monitor repair activities and subsequent testing; observe the utilitys activities to return the plant to service; and complete gathering data. Following analysis of the observations and review of the collected data, the special inspection team will draw its conclusions about the companys adherence to NRC reactor vessel head requirements, the companys current activities associated with the discovery of nozzle cracks and actions to address it.
The meeting, which will be open to the public, is scheduled to begin at 6 p.m. EDT at Camp Perry Lodging & Conference Center, 1000 Lawrence Road, Building 600 (Clubhouse), in Port Clinton.
The NRC will be available to respond to questions or comments from the public before the close of the meeting. Toll-free teleconference phone lines will be available to those members of the public who are not able to attend the meeting. Call Viktoria Mitlyng at 630/829-9662 for further information.
The NRC will schedule another public meeting to present to the public and the company the special inspection teams preliminary conclusions on the current nozzle cracking event.
The NRC is concerned about this issue because a crack in CRDM nozzles, which penetrate the reactor vessel head, can if not repaired, lead to structural damage of the reactor head - one of the barriers that prevent radioactive material in the reactor from escaping into the plant containment building.
In 2002, plant workers at Davis-Besse discovered a football-size cavity in the reactor vessel head caused by leakage of borated reactor water from severe cracks in CRDM nozzles. The leaks resulted in the accumulation of large quantities of boric acid residue on the reactor vessel head that was not cleaned for a long period of time and caused a cavity to form in the carbon steel portion of the vessel head, leaving only the stainless steel liner between the nuclear material in the reactor vessel head and the plant containment building. The damaged reactor head was replaced in 2002; the replacement head is the one in service today.
The current situation is not comparable to what occurred at Davis-Besse in 2002. Neither the small amount of boric acid (one tablespoon) present on the head nor the identified flaws in the nozzles challenge the structural integrity of the reactor vessel head.
The NRC special inspection report will be available within 45 days of the inspections completion through the NRC RIII Office of Public Affairs and at the NRC web site: http://www.nrc.gov/reading-rm/adams/web-based.html.
NRC news releases are available through a free list serve subscription at the following Web address:
http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link. E-mail notifications are sent to subscribers when news releases are posted to NRC's Web site.