MONTHYEARML23165A0222023-03-0202 March 2023 News Release-23-015: NRC Grants Timely Renewal Exemption to Allow Continued Operation of Diablo Canyon Nuclear Power Plant ML22199A0542022-07-0707 July 2022 News Release-22-025: NRC to Hold Public Meeting in San Luis Obispo to Discuss Diablo Canyon Nuclear Power Plant Decommissioning Plan ML22199A0692022-06-13013 June 2022 News Release-IV-22-007: NRC Names New Senior Resident Inspector at the Diablo Canyon Nuclear Power Plant Press Release-22-019, NRC Responds to Inspector General'S Diablo Canyon Event Inquiry2022-05-0303 May 2022 Press Release-22-019: NRC Responds to Inspector General'S Diablo Canyon Event Inquiry Press Release-IV-21-005, NRC to Hold Virtual Meeting to Discuss 2020 Performance of 10 Region IV Nuclear Power Plants2021-04-30030 April 2021 Press Release-IV-21-005: NRC to Hold Virtual Meeting to Discuss 2020 Performance of 10 Region IV Nuclear Power Plants Press Release-IV-20-018, NRC Names New Senior Resident Inspector at the Diablo Canyon Nuclear Power Plant2020-09-30030 September 2020 Press Release-IV-20-018: NRC Names New Senior Resident Inspector at the Diablo Canyon Nuclear Power Plant Press Release-IV-20-007, NRC to Hold Virtual Meeting to Discuss 2019 Performance of 12 Region IV Nuclear Power Plants2020-06-22022 June 2020 Press Release-IV-20-007: NRC to Hold Virtual Meeting to Discuss 2019 Performance of 12 Region IV Nuclear Power Plants Press Release-19-039, NRC Announces Public Meetings Dates and Venues for Community Advisory Boards Near Decommissioning Nuclear Power Plants2019-08-21021 August 2019 Press Release-19-039: NRC Announces Public Meetings Dates and Venues for Community Advisory Boards Near Decommissioning Nuclear Power Plants Press Release-IV-18-011, NRC to Hold Public Meeting to Discuss 2017 Performance of Diablo Canyon Nuclear Power Plant2018-07-20020 July 2018 Press Release-IV-18-011: NRC to Hold Public Meeting to Discuss 2017 Performance of Diablo Canyon Nuclear Power Plant Press Release-18-008, NRC Issues Annual Assessments for Nation'S Nuclear Plants2018-03-0505 March 2018 Press Release-18-008: NRC Issues Annual Assessments for Nation'S Nuclear Plants Press Release-IV-17-013, NRC to Hold Public Meeting on Diablo Canyon Nuclear Power Plant2017-06-0707 June 2017 Press Release-IV-17-013: NRC to Hold Public Meeting on Diablo Canyon Nuclear Power Plant Press Release-IV-16-021, NRC Schedules Regulatory Conference to Discuss Proposed Violation at Diablo Canyon Nuclear Power Plant2016-10-28028 October 2016 Press Release-IV-16-021: NRC Schedules Regulatory Conference to Discuss Proposed Violation at Diablo Canyon Nuclear Power Plant Press Release-IV-16-017, NRC Names New Senior Resident Inspector at Diablo Canyon Nuclear Power Plant2016-08-26026 August 2016 Press Release-IV-16-017: NRC Names New Senior Resident Inspector at Diablo Canyon Nuclear Power Plant Press Release-IV-16-011, NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant2016-05-24024 May 2016 Press Release-IV-16-011: NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant Press Release-16-001, NRC Grants Weapons Pre-Emption Authority to Nuclear Facilities in Two States2016-01-0606 January 2016 Press Release-16-001: NRC Grants Weapons Pre-Emption Authority to Nuclear Facilities in Two States Press Release-15-068, NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors2015-10-27027 October 2015 Press Release-15-068: NRC Accelerates Schedule for Earthquake Risk Analysis at U.S. Reactors Press Release-15-054, NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants2015-09-0303 September 2015 Press Release-15-054: NRC Issues Mid-Cycle Assessments for Nation'S Nuclear Plants Press Release-15-043, NRC Seeks Public Comment on Environmental Issues for Diablo Canyon Nuclear Plant License Renewal2015-07-0101 July 2015 Press Release-15-043: NRC Seeks Public Comment on Environmental Issues for Diablo Canyon Nuclear Plant License Renewal Press Release-15-035, NRC Licensing Board to Hear Oral Arguments on Diablo Canyon Issues July 9 in Rockville, MD2015-06-0303 June 2015 Press Release-15-035: NRC Licensing Board to Hear Oral Arguments on Diablo Canyon Issues July 9 in Rockville, MD Press Release-IV-15-013, NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant2015-06-0101 June 2015 Press Release-IV-15-013: NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant Press Release-15-032, NRC Requires Additional Earthquake Risk Analysis for Two Western U.S. Reactors2015-05-13013 May 2015 Press Release-15-032: NRC Requires Additional Earthquake Risk Analysis for Two Western U.S. Reactors Press Release-IV-15-005, NRC Issues White Finding to Diablo Canyon Nuclear Power Plant2015-02-12012 February 2015 Press Release-IV-15-005: NRC Issues White Finding to Diablo Canyon Nuclear Power Plant Press Release-IV-14-027, NRC Schedules Regulatory Conference to Discuss Apparent Violation at Diablo Canyon Nuclear Power Plant2014-12-30030 December 2014 Press Release-IV-14-027: NRC Schedules Regulatory Conference to Discuss Apparent Violation at Diablo Canyon Nuclear Power Plant Press Release-IV-14-009, NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant2014-04-25025 April 2014 Press Release-IV-14-009: NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant Press Release-IV-13-038, NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant2013-12-11011 December 2013 Press Release-IV-13-038: NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant Press Release-IV-13-032, NRC Postpones Public Meeting on Diablo Canyon Because of Government Shutdown2013-10-0808 October 2013 Press Release-IV-13-032: NRC Postpones Public Meeting on Diablo Canyon Because of Government Shutdown Press Release-13-047, NRC Issues Order Designating 10 Facilities Eligible for Weapons Pre-Emption Authority2013-06-0505 June 2013 Press Release-13-047: NRC Issues Order Designating 10 Facilities Eligible for Weapons Pre-Emption Authority Press Release-IV-12-048, NRC to Hold Two Public Meetings on the Diablo Canyon Nuclear Power Plant on Nov. 282012-11-0909 November 2012 Press Release-IV-12-048: NRC to Hold Two Public Meetings on the Diablo Canyon Nuclear Power Plant on Nov. 28 Press Release-12-112, Additional NRC Analysis Confirms Earthquake Safety at Diablo Canyon Nuclear Power Plant2012-10-12012 October 2012 Press Release-12-112: Additional NRC Analysis Confirms Earthquake Safety at Diablo Canyon Nuclear Power Plant Press Release-11-095, NRC Issues Final Safety Evaluation Report for Diablo Canyon Power Plant License Renewal2011-06-0202 June 2011 Press Release-11-095: NRC Issues Final Safety Evaluation Report for Diablo Canyon Power Plant License Renewal Press Release-IV-11-023, NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant2011-05-12012 May 2011 Press Release-IV-11-023: NRC to Discuss Performance Assessment for Diablo Canyon Nuclear Power Plant Press Release-IV-11-021, NRC Names New Resident Inspector at Diablo Canyon Nuclear Power Plant2011-05-10010 May 2011 Press Release-IV-11-021: NRC Names New Resident Inspector at Diablo Canyon Nuclear Power Plant Press Release-11-042, NRC Monitors Notice of Unusual Event at Diablo Canyon Power Plant, Tsunami Issues2011-03-11011 March 2011 Press Release-11-042: NRC Monitors Notice of Unusual Event at Diablo Canyon Power Plant, Tsunami Issues Press Release-11-043, NRC Continues to Track Earthquake and Tsunami Issues2011-03-11011 March 2011 Press Release-11-043: NRC Continues to Track Earthquake and Tsunami Issues Press Release-IV-11-006, NRC to Hold Public Meeting to Discuss PG&E Digital Upgrade Proposal at the Diablo Canyon Nuclear Plant2011-01-26026 January 2011 Press Release-IV-11-006: NRC to Hold Public Meeting to Discuss PG&E Digital Upgrade Proposal at the Diablo Canyon Nuclear Plant Press Release-IV-11-004, NRC Hold Public Meeting to Discuss Results of License Renewal Inspection at the Diablo Canyon Nuclear Plant2011-01-13013 January 2011 Press Release-IV-11-004: NRC Hold Public Meeting to Discuss Results of License Renewal Inspection at the Diablo Canyon Nuclear Plant Press Release-11-006, NRC Issues Safety Evaluation Report for Diablo Canyon Nuclear Power Plant License Renewal Application2011-01-11011 January 2011 Press Release-11-006: NRC Issues Safety Evaluation Report for Diablo Canyon Nuclear Power Plant License Renewal Application Press Release-IV-10-030, NRC to Hold Public Meeting to Discuss Diablo Canyon Nuclear Power Plant Issues2010-08-26026 August 2010 Press Release-IV-10-030: NRC to Hold Public Meeting to Discuss Diablo Canyon Nuclear Power Plant Issues Press Release-IV-10-028, NRC to Hold Seismic Workshop September 8 - 92010-08-0505 August 2010 Press Release-IV-10-028: NRC to Hold Seismic Workshop September 8 - 9 Press Release-IV-10-026, NRC Monitors Alert at Diablo Canyon Nuclear Power Plant2010-06-23023 June 2010 Press Release-IV-10-026: NRC Monitors Alert at Diablo Canyon Nuclear Power Plant Press Release-IV-10-024, NRC to Hold Two Public Meetings on the Diablo Canyon Nuclear Power Plant on June 292010-06-11011 June 2010 Press Release-IV-10-024: NRC to Hold Two Public Meetings on the Diablo Canyon Nuclear Power Plant on June 29 Press Release-10-078, Licensing Board to Hear Oral Argument May 26 in San Luis Obispo, California, on Diablo Canyon Reactor License Renewal2010-05-0303 May 2010 Press Release-10-078: Licensing Board to Hear Oral Argument May 26 in San Luis Obispo, California, on Diablo Canyon Reactor License Renewal Press Release-IV-10-003, NRC to Conduct Environmental Scoping Meeting as Part of the License Renewal Application for Diablo Canyon Nuclear Plant2010-02-19019 February 2010 Press Release-IV-10-003: NRC to Conduct Environmental Scoping Meeting as Part of the License Renewal Application for Diablo Canyon Nuclear Plant Press Release-IV-10-002, NRC to Discuss Process for Review of License Renewal Application for Diablo Canyon Nuclear Plant2010-01-28028 January 2010 Press Release-IV-10-002: NRC to Discuss Process for Review of License Renewal Application for Diablo Canyon Nuclear Plant Press Release-IV-10-001, NRC to Hold Public Meeting to Discuss Results of Special Inspection at the Diablo Canyon Nuclear Plant2010-01-11011 January 2010 Press Release-IV-10-001: NRC to Hold Public Meeting to Discuss Results of Special Inspection at the Diablo Canyon Nuclear Plant Press Release-10-004, NRC Announces Opportunity for Hearing on Application to Renew Operating Licenses for Diablo Canyon Nuclear Power Plant2010-01-11011 January 2010 Press Release-10-004: NRC Announces Opportunity for Hearing on Application to Renew Operating Licenses for Diablo Canyon Nuclear Power Plant ML0935800832009-12-18018 December 2009 G20090719/LTR-09-0642/EDATS: SECY-2009-0560 - E-mail. Rochelle Becker Safety Culture/Request for Meeting Press Release-09-194, NRC Announces Availability of License Renewal Application for Diablo Canyon Nuclear Power Plant2009-12-0808 December 2009 Press Release-09-194: NRC Announces Availability of License Renewal Application for Diablo Canyon Nuclear Power Plant Press Release-IV-09-035, NRC Conducting Special Inspection at Diablo Canyon Nuclear Plant2009-11-24024 November 2009 Press Release-IV-09-035: NRC Conducting Special Inspection at Diablo Canyon Nuclear Plant Press Release-IV-09-015, NRC to Hold Two Public Meetings About Diablo Canyon Nuclear Plant on May 282009-05-12012 May 2009 Press Release-IV-09-015: NRC to Hold Two Public Meetings About Diablo Canyon Nuclear Plant on May 28 2023-03-02
[Table view] |
Text
NRC NEWS U.S. NUCLEAR REGULATORY COMMISSION Office of Public Affairs Telephone: 301/415-8200 Washington, D.C. 20555-0001 E-mail: opa.resource@nrc.gov Site: www.nrc.gov Blog: http://public-blog.nrc-gateway.gov No.11-095 June 2, 2011 NRC ISSUES FINAL SAFETY EVALUATION REPORT FOR DIABLO CANYON NUCLEAR POWER PLANT LICENSE RENEWAL The Nuclear Regulatory Commission has issued its safety evaluation report (SER) for the proposed renewal of the operating licenses for the Diablo Canyon Nuclear Power Plant, Units 1 and 2.
In a letter dated April 10, Pacific Gas & Electric Company (PG&E) requested that NRC defer issuance of the renewed operating licenses, due to a delay in receiving a coastal consistency certification from the State of California only after PG&E has completed a 3D seismic study. In a response letter dated May 31, NRC notified PG&E that future milestones for the review of the license renewal application will be delayed with the exception of the issuance of the SER. The schedule for future milestones will be determined based on a timeline consistent with PG&Es expected receipt of a coastal consistency certification. Additionally, the SER will be supplemented, as necessary, prior to finalizing a decision on license renewal.
The SER report documents the results of the NRC staffs review of the license renewal application and site audits of the plants aging management programs to address the safety of plant operations during the period of extended operation. Overall, the results show that the applicant has identified actions that have been or will be taken to manage the effects of aging in the appropriate safety systems, structures and components of the plant, and that their functions will be maintained during the period of extended operation.
Issuing the SER is a significant milestone in the license renewal review process. This process proceeds along two tracks - one for review of safety issues and another for environmental issues. The staff is still in the process of reviewing the environmental part of the Diablo Canyon plants license renewal application. That review must be completed before a final decision is made on the renewal.
The SER and the license renewal application will be provided on a delayed schedule to the agencys Advisory Committee on Reactor Safeguards (ACRS), an independent body of experts that advises the Commission on reactor safety matters. The ACRS will discuss the SER during one of its monthly public meetings, the schedule of which will be determined at a later date and will be posted on the NRC website at: http://www.nrc.gov/public-involve/public-meetings/index.cfm. The ACRS will then issue a letter to the Commission discussing the results of its review.
In a letter dated June 2, Brian Holian, director of the Office of Nuclear Reactor Regulations Division of License Renewal, provided PG&E with the SER. The SER will be available on the NRCs website at: http://www.nrc.gov/reactors/operating/licensing/renewal/applications/diablo-canyon.html.
PG&E submitted an application to the NRC in November 2009 to extend the plant licenses by 20 years for each unit. The plant, operated by PG&E, is located in Avila Beach, Calif. The current 40-year operating licenses for Diablo Canyons Units 1 and 2 are due to expire on Nov. 2, 2024, and Aug. 26, 2025, respectively.
Documents related to Diablo Canyon Nuclear Power Plant, Units 1 and 2 are located at the following locations: The San Luis Obispo Public Library, 995 Palm Street, San Luis Obispo, Calif. 93401, and at the Paso Robles Public Library, 1000 Spring Street, Paso Robles, Calif. 93446.
Additional information concerning license renewal in general and the Diablo Canyons application in particular can be found at:
http://www.nrc.gov/reading-rm/doc-collections/fact-sheets/license-renewal-bg.html and http://www.nrc.gov/reactors/operating/licensing/renewal.html respectively.
News releases are available through a free listserv subscription at the following Web address:
http://www.nrc.gov/public-involve/listserver.html. The NRC homepage at www.nrc.gov also offers a SUBSCRIBE link.
E-mail notifications are sent to subscribers when news releases are posted to NRCs website.