MONTHYEARNOC-AE-08002287, Due Date Extension for Three-Month Response to Generic Letter 2008-012008-04-0909 April 2008 Due Date Extension for Three-Month Response to Generic Letter 2008-01 Project stage: Request NOC-AE-08002284, Three-Month Response to Generic Letter 2008-012008-05-12012 May 2008 Three-Month Response to Generic Letter 2008-01 Project stage: Request ML0819004452008-07-29029 July 2008 Approval of Extension for 3-Month Extension to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other ML0821104352008-08-0101 August 2008 Request for Additional Information Reactor Equipment Cooling System Project stage: RAI ML0825600052008-09-22022 September 2008 Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems, Proposed Alternate Course of Action Project stage: Other NOC-AE-08002355, Nine-Month Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems.2008-10-13013 October 2008 Nine-Month Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems. Project stage: Other NOC-AE-09002384, Nine-Month Supplemental Response to Generic Letter 2008-012009-01-22022 January 2009 Nine-Month Supplemental Response to Generic Letter 2008-01 Project stage: Supplement ML0928600792009-10-13013 October 2009 Request for Additional Information GL 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: RAI NOC-AE-10002511, Month Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems.2010-02-16016 February 2010 Month Supplemental Response to Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal and Containment Spray Systems. Project stage: Supplement NOC-AE-10002579, Nine-Month Supplemental Response to Generic Letter 2008-012010-07-27027 July 2010 Nine-Month Supplemental Response to Generic Letter 2008-01 Project stage: Supplement ML1115805052011-06-10010 June 2011 Closeout of Generic Letter 2008-01, Managing Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems Project stage: Other 2008-09-22
[Table View] |
|
---|
Category:Letter type:NOC
MONTHYEARNOC-AE-240040, Application for Order Consenting to Direct Transfer of Licenses2024-07-31031 July 2024 Application for Order Consenting to Direct Transfer of Licenses NOC-AE-240040, Operator Licensinq Examination Schedule Revision 32024-05-15015 May 2024 Operator Licensinq Examination Schedule Revision 3 NOC-AE-240040, Annual Dose Report for 20232024-04-29029 April 2024 Annual Dose Report for 2023 NOC-AE-240040, Financial Assurance for Decommissioning - 2024 Update2024-03-28028 March 2024 Financial Assurance for Decommissioning - 2024 Update NOC-AE-240040, Unit L & 2, Supplement to Modify the Implementation Date for License Amendment Request to Revise Alternate Source Term Dose Calculation2024-02-0808 February 2024 Unit L & 2, Supplement to Modify the Implementation Date for License Amendment Request to Revise Alternate Source Term Dose Calculation NOC-AE-230039, Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/20230032023-12-12012 December 2023 Docket Nos. Stn 50-498, Stn 50-499 - Reply to a Notice of Violation, NRC Inspection Report 05000498/2023003 and 05000499/2023003 NOC-AE-230040, Update Foreign Ownership, Control, or Influence (FOCI)2023-12-0505 December 2023 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-230039, Submittal of Update Foreign Ownership, Control or Influence (FOCI)2023-07-11011 July 2023 Submittal of Update Foreign Ownership, Control or Influence (FOCI) NOC-AE-220039, Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 252023-02-0606 February 2023 Physical Security Plan, Training and Qualification Plan, Safeguards Contingency Plan, and Independent Spent Fuel Storage Installation Security Program Revision 25 NOC-AE-220038, Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask2022-06-23023 June 2022 Independent Spent Fuel Storage Installation Registration of Dry Spent Fuel Storage Cask NOC-AE-210038, Submittal of Operations Quality Assurance Plan Changes QA-089, QA-091, and Revision 252022-01-0404 January 2022 Submittal of Operations Quality Assurance Plan Changes QA-089, QA-091, and Revision 25 NOC-AE-21003858, 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes2021-12-0606 December 2021 10 CFR 50.46 Thirty-Day Report of Significant ECCS Model Changes NOC-AE-21003853, Revised Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material2021-12-0303 December 2021 Revised Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material NOC-AE-21003848, Unit 1 Cycle 24 Core Operating Limits Report2021-11-18018 November 2021 Unit 1 Cycle 24 Core Operating Limits Report NOC-AE-21003846, Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material2021-11-0404 November 2021 Response to End of Enforcement Discretion and Request for Approval of Alternate Disposal Procedures for Very Low-Level Radioactive Material NOC-AE-21003842, 10 CFR 50.59 Summary Report2021-09-23023 September 2021 10 CFR 50.59 Summary Report NOC-AE-21003841, Request for Relief from ASME Section Xl Code Requirements for Weld Examinations (Relief Request RR-ENG-3-25)2021-09-23023 September 2021 Request for Relief from ASME Section Xl Code Requirements for Weld Examinations (Relief Request RR-ENG-3-25) NOC-AE-21003832, Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-09-0909 September 2021 Supplement to License Amendment Request to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-21003812, Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections2021-08-10010 August 2021 Application to Revise Technical Specifications to Adopt TSTF-577, Revised Frequencies for Steam Generator Tube Inspections NOC-AE-21003825, Update of Foreign Ownership, Control, or Influence Information (FOCI)2021-08-0505 August 2021 Update of Foreign Ownership, Control, or Influence Information (FOCI) NOC-AE-21003824, Update Foreign Ownership, Control, or Influence (FOCI)2021-07-29029 July 2021 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-21003823, Update Foreign Ownership Control or Influence (FOCI)2021-07-28028 July 2021 Update Foreign Ownership Control or Influence (FOCI) NOC-AE-21003820, Nuclear Insurance Protection2021-07-20020 July 2021 Nuclear Insurance Protection NOC-AE-21003819, Inservice Inspection Summary Report - 2RE212021-07-15015 July 2021 Inservice Inspection Summary Report - 2RE21 NOC-AE-21003816, Commitment Change Summary Report2021-06-30030 June 2021 Commitment Change Summary Report NOC-AE-21003814, Technical Specification Bases Control Program2021-06-24024 June 2021 Technical Specification Bases Control Program NOC-AE-21003810, Update Foreign Ownership, Control, or Influence (FOCI)- CPS Energy2021-06-17017 June 2021 Update Foreign Ownership, Control, or Influence (FOCI)- CPS Energy NOC-AE-21003811, Update Foreign Ownership, Control, or Influence (FOCI)- Nrg Energy2021-06-17017 June 2021 Update Foreign Ownership, Control, or Influence (FOCI)- Nrg Energy NOC-AE-21003806, Inservice Inspection Program Plan and Inservice Testing Program Snubber Inservice Test Plan for the Fourth Ten-Year Interval2021-05-20020 May 2021 Inservice Inspection Program Plan and Inservice Testing Program Snubber Inservice Test Plan for the Fourth Ten-Year Interval NOC-AE-21003801, Annual Dose Report for 20202021-04-26026 April 2021 Annual Dose Report for 2020 NOC-AE-21003802, 2020 South Texas Project Electric Generating Station Annual Environmental Operating Report2021-04-26026 April 2021 2020 South Texas Project Electric Generating Station Annual Environmental Operating Report NOC-AE-21003804, Operator Licensing Examination Schedule2021-04-21021 April 2021 Operator Licensing Examination Schedule NOC-AE-21003800, Radioactive Effluent Release Report2021-04-19019 April 2021 Radioactive Effluent Release Report NOC-AE-21003799, Changes to South Texas Project Electric Generating Station (STPEGS) Emergency Plan2021-04-15015 April 2021 Changes to South Texas Project Electric Generating Station (STPEGS) Emergency Plan NOC-AE-21003795, Cycle 22 Core Operating Limits Report2021-04-15015 April 2021 Cycle 22 Core Operating Limits Report NOC-AE-21003796, Update Foreign Ownership, Control, or Influence (FOCI)2021-04-15015 April 2021 Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-21003790, Response to Apparent Violations in NRC Inspection Report 05000498/2020401 and 05000499/2020401: (EA-20-122) (Letter)2021-03-31031 March 2021 Response to Apparent Violations in NRC Inspection Report 05000498/2020401 and 05000499/2020401: (EA-20-122) (Letter) NOC-AE-21003791, Financial Assurance for Decommissioning - 2021 Update2021-03-31031 March 2021 Financial Assurance for Decommissioning - 2021 Update NOC-AE-210037, STP Fire Hazards Analysis Report, Amendment 26 (Redacted)2021-03-30030 March 2021 STP Fire Hazards Analysis Report, Amendment 26 (Redacted) NOC-AE-21003792, STP Fire Hazards Analysis Report, Amendment 26 (Redacted)2021-03-30030 March 2021 STP Fire Hazards Analysis Report, Amendment 26 (Redacted) NOC-AE-200037, License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications2021-03-11011 March 2021 License Amendment Request to Revise Technical Specification 3.6.3 to Append a Note and Remove the Index from Technical Specifications NOC-AE-21003784, Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing2021-03-0808 March 2021 Response to Request for Additional Information Regarding 1RE22 Inspection Summary Report for Steam Generator Tubing NOC-AE-21003786, Annual Fitness for Duty Performance Report for 20202021-03-0101 March 2021 Annual Fitness for Duty Performance Report for 2020 NOC-AE-21003785, Evidence of Financial Protection2021-02-23023 February 2021 Evidence of Financial Protection NOC-AE-21003781, Notice Regarding Withdrawal of Funds from Nuclear Decommissioning Trust Subaccounts2021-01-27027 January 2021 Notice Regarding Withdrawal of Funds from Nuclear Decommissioning Trust Subaccounts NOC-AE-21003780, Submittal of Update Foreign Ownership, Control, or Influence (FOCI)2021-01-0707 January 2021 Submittal of Update Foreign Ownership, Control, or Influence (FOCI) NOC-AE-20003778, Changes to South Texas Project Electric Generating Station Emergency Plan2020-12-17017 December 2020 Changes to South Texas Project Electric Generating Station Emergency Plan NOC-AE-20003777, STPNOC Concerns Regarding the Proposed Change to the Evaluated Force-on-Force Inspection Guidance During the COVID-19 Public Health Emergency2020-12-10010 December 2020 STPNOC Concerns Regarding the Proposed Change to the Evaluated Force-on-Force Inspection Guidance During the COVID-19 Public Health Emergency NOC-AE-20003766, Supplement to Change Implementation Date for License Amendment Request to Revise the STPEGS Emergency Plan2020-12-0202 December 2020 Supplement to Change Implementation Date for License Amendment Request to Revise the STPEGS Emergency Plan NOC-AE-20003767, Request for a One-Time Exemption from 10 CFR 73, Appendix 8, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic2020-11-16016 November 2020 Request for a One-Time Exemption from 10 CFR 73, Appendix 8, Section VI, Subsection C.3.(1)(1) Regarding Annual Force-on-Force (FOF) Exercises, Due to Covid 19 Pandemic 2024-07-31
[Table view] |
Text
Nuclear Operating Company South Texas Pro/ect ElectricGeneratingStation P0 Box 289 Wadsworth, Texas 77483 J April 9, 2008 NOC-AE-08002287 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket No. STN 50-498, STN 50-499 Due Date Extension for Three-Month Response to Generic Letter 2008-01
Reference:
NRC Generic Letter 2008-01, "Managing. Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems," dated January 11, 2008 Because of the outage schedules for STP Unit 1 and Unit 2, STP Nuclear Operating Company (STPNOC) will not be able to complete the necessary assessments to fully respond to the referenced Generic Letter (GL) 2008-01 by the requested nine-month date (October 11, 2008).
GL 2008-01 includes provisions for a three-month response if a licensee cannot provide the information requested for the nine-month response. In a phone call on April 3, 2008, STPNOC and the NRC staff agreed that the three-month response can be deferred to May 12, 2008.
The additional time for the three-month letter will allow STPNOC to perform some of the GL 2008-01 evaluations required for Unit 1 during the spring outage currently in progress and better define the remaining Unit 1 evaluation scope. The extended due date provides time to prepare and submit the response after the outage is completed.
STPNOC is tracking the May 12, 2008 committed date for the three month response as action CR 08-796-9 (see Attachment).
If there are any questions or if additional information is needed, please contact Wayne Harrison at (361) 972-7298 or me at (361) 972-7136.
Scott M. Head Manager, Licensing
Attachment:
Commitment STI 32291660
cc:
(paper copy) (electronic copy)
Regional Administrator, Region IV A. H. Gutterman, Esquire U. S. Nuclear Regulatory Commission Morgan, Lewis & Bockius LLP 611 Ryan Plaza Drive, Suite 400 Arlington, Texas 76011-8064 Mohan C. Thadani U. S. Nuclear Regulatory Commission Mohan C. Thadani Thad Hill Senior Project Manager Eddy Daniels U.S. Nuclear Regulatory Commission Catherine Callaway One White Flint North (MS 7 D1) Brad Porlier 11555 Rockville Pike Steve Winn Rockville, MD 20852 Staney Rostad NRG South Texas LP Senior Resident Inspector Ed Alarcon U. S. Nuclear Regulatory Commission J. J. Nesrsta P. O. Box 289, Mail Code: MN116 R. K. Temple Wadsworth, TX 77483 Kevin Polio City Public Service C. M. Canady Jon C. Wood City of Austin Cox Smith Matthews Electric Utility Department 721 Barton Springs Road C. Kirksey Austin, TX 78704 City of Austin Richard A. Ratliff Bureau of Radiation Control Texas Department of State Health Services 1100 West 49th Street Austin, TX 78756-3189
Attachment NOC-AE-08002287 Page 1 of 1 Commitment Provide three-month Due 5/12/2008 CR 08-796-9 response to GL 2008-01 STI 32291660
Text
Nuclear Operating Company South Texas Pro/ect ElectricGeneratingStation P0 Box 289 Wadsworth, Texas 77483 J April 9, 2008 NOC-AE-08002287 10 CFR 50.4 U.S. Nuclear Regulatory Commission ATTN: Document Control Desk 11555 Rockville Pike Rockville, MD 20852 South Texas Project Units 1 and 2 Docket No. STN 50-498, STN 50-499 Due Date Extension for Three-Month Response to Generic Letter 2008-01
Reference:
NRC Generic Letter 2008-01, "Managing. Gas Accumulation in Emergency Core Cooling, Decay Heat Removal, and Containment Spray Systems," dated January 11, 2008 Because of the outage schedules for STP Unit 1 and Unit 2, STP Nuclear Operating Company (STPNOC) will not be able to complete the necessary assessments to fully respond to the referenced Generic Letter (GL) 2008-01 by the requested nine-month date (October 11, 2008).
GL 2008-01 includes provisions for a three-month response if a licensee cannot provide the information requested for the nine-month response. In a phone call on April 3, 2008, STPNOC and the NRC staff agreed that the three-month response can be deferred to May 12, 2008.
The additional time for the three-month letter will allow STPNOC to perform some of the GL 2008-01 evaluations required for Unit 1 during the spring outage currently in progress and better define the remaining Unit 1 evaluation scope. The extended due date provides time to prepare and submit the response after the outage is completed.
STPNOC is tracking the May 12, 2008 committed date for the three month response as action CR 08-796-9 (see Attachment).
If there are any questions or if additional information is needed, please contact Wayne Harrison at (361) 972-7298 or me at (361) 972-7136.
Scott M. Head Manager, Licensing
Attachment:
Commitment STI 32291660
cc:
(paper copy) (electronic copy)
Regional Administrator, Region IV A. H. Gutterman, Esquire U. S. Nuclear Regulatory Commission Morgan, Lewis & Bockius LLP 611 Ryan Plaza Drive, Suite 400 Arlington, Texas 76011-8064 Mohan C. Thadani U. S. Nuclear Regulatory Commission Mohan C. Thadani Thad Hill Senior Project Manager Eddy Daniels U.S. Nuclear Regulatory Commission Catherine Callaway One White Flint North (MS 7 D1) Brad Porlier 11555 Rockville Pike Steve Winn Rockville, MD 20852 Staney Rostad NRG South Texas LP Senior Resident Inspector Ed Alarcon U. S. Nuclear Regulatory Commission J. J. Nesrsta P. O. Box 289, Mail Code: MN116 R. K. Temple Wadsworth, TX 77483 Kevin Polio City Public Service C. M. Canady Jon C. Wood City of Austin Cox Smith Matthews Electric Utility Department 721 Barton Springs Road C. Kirksey Austin, TX 78704 City of Austin Richard A. Ratliff Bureau of Radiation Control Texas Department of State Health Services 1100 West 49th Street Austin, TX 78756-3189
Attachment NOC-AE-08002287 Page 1 of 1 Commitment Provide three-month Due 5/12/2008 CR 08-796-9 response to GL 2008-01 STI 32291660