NL-17-0544, Completion of License Renewal Activities Prior to Entering the Period of Extended Operation

From kanterella
Jump to navigation Jump to search
Completion of License Renewal Activities Prior to Entering the Period of Extended Operation
ML17205A355
Person / Time
Site: Farley Southern Nuclear icon.png
Issue date: 07/24/2017
From: Madison D
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-17-0544
Download: ML17205A355 (2)


Text

~ Southern Nuclear Dennis A. Madison VIce President- Plant Farley Southern Nuclear Operating Company Farley Nuclear Plant Post Office Drawer 470 Ashford, AL 36312 Tel 334.814.4511 Fax 334.814.4575 July 24, 2017 Docket Nos.: 50-348 NL-17-0544 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant- Unit 1 Completion of License Renewal Activities Prior to Entering the Period of Extended Operation

References:

1. NUREG-1825, "Safety Evaluation Report Related to the License Renewal of the Joseph M. Farley Nuclear Plant, Units 1 and 2" dated May 2005 (ML051250126}
2. Issuance of Renewed Facility Operating License Nos. NPF-2 and NPF-8 for Joseph M. Farley Nuclear Plant, Units 1 and 2. (ML051290086)

Ladies and Gentlemen:

Pursuant to Condition 2.C.(5) of the Joseph M. Farley Nuclear Plant (FNP) Unit 1 Renewed Facility Operating License NPF-2, which was issued per Reference 2, Southern Nuclear Operating Company (SNC) confirms that FNP Unit 1 license renewal commitments of Reference 1, required to be implemented no later than June 25, 2017 and prior to entry into the period of extended operation (PEO), are complete and can be verified by NRC inspection.

Commitment number 12 from Reference 1 was to implement the Non-EO Cables Program prior to the PEO, in accordance with sections X1.E1 and X1.E3 of NUREG-1801. Per EPRI guidance, the seeping included a cable for a blackout recovery function. Plant Farley design has redundancy for this cable. The cable originally scheduled to be tested for this function is carrying the switchyard loads. Because of the risk to plant operation of transferring loads to the redundant cable, the inspection schedule was revised and the redundant cable was tested prior to PEO. The cable originally scheduled for testing will be tested prior to the end of 2017. This change was captured in the Corrective Action Program as CR 10378523.

Commitment 12 is complete.

This letter contains no new NRC commitments. If you have any questions, please contact Elizabeth Williford at 334.814.4765.

Respectfully submitted,