10 CFR 72.48(d)(2) Biennial Report
ML14171A626
Person / Time
Site: Hatch, 07200036  Southern Nuclear icon.png
Issue date: 06/20/2014
From: Pierce C
Southern Co, Southern Nuclear Operating Co
To:
Document Control Desk, NRC/NMSS/SFST
References
NL-14-0947
Download: ML14171A626 (2)


Text

Charles R. Pierce Southern Nuclear Regulatory Affairs Director Operating Company, Inc.

40 Inverness Center Parkway Post Office Box 1295 Birmingham. Alabama 35201 Tel 205.992.7872 Fax 205.992.7601 SOUTHERN<<\

JUN 2 0 2014 COMPANY Docket Nos.: 50-321 NL-14-0947 50-366 72-36 ATTN: Document Control Desk Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards U. S. Nuclear Regulatory Commission Washington, D. C. 20555-0001 Edwin I. Hatch Nuclear Plant 10 CFR 72.48(d)(2) Biennial Report Ladies and Gentlemen:

The provisions of 10 CFR 72.48 allow licensees to make changes to the design of the independent spent fuel storage installation (ISFSI) and certified cask designs without prior NRC approval. The requirements of 10 CFR 72.48(d)(2) include a biennial report of changes implemented in accordance with the provisions of 10 CFR 72.48. The purpose of this report is to inform the NRC that Southern Nuclear Operating Company has not implemented any changes to the Edwin I.

Hatch Nuclear Plant ISFSI in accordance with the provisions of 10 CFR 72.48 for the reporting period of February 1, 2012, through February 1, 2014. Accordingly, no activities are required to be reported for this period.

This letter contains no NRC commitments. If you have any questions, please contact Ken McElroy at (205) 992-7369.

Respectfully submitted,

{!.fl. fL_

C. R. Pierce Regulatory Affairs Director CRPfTWS/Iac

U.S. Nuclear Regulatory Commission NL-14-0947 Page 2 cc: Southern Nuclear Operating Company Mr. S. E. Kuczynski, Chairman, President & CEO Mr. D. G. Bast, Executive Vice President & Chief Nuclear Officer Mr. D. R. Vineyard, Vice President- Hatch Mr. B. L. lvey, Vice President- Regulatory Affairs Mr. D. R. Madison, Vice President - Fleet Operations Mr. B. J. Adams, Vice President - Engineering Mr. G. L. Johnson, Regulatory Affairs Manager - Hatch RTYPE: CHA02.004 U.S. Nuclear Regulatory Commission Mr. V. M. McCree, Regional Administrator Mr. R. E. Martin, NRR Senior Project Manager - Hatch Mr. E. D. Morris, Senior Resident Inspector- Hatch Mr. R. Carrion, NRC Region II Inspector