Cheryl A. Gayheart Southern Nuclear Vice President -Farley Operating Company, Inc.

Farley Nuclear Plant Post Office Drawer 470 Ashford, Alabama 36312 Tel 334.814.4511 Fax 334.814.4575 SOUTHERNA tompikm April 21, 2014 Docket Nos.: 50-348 NL-14-0604 50-364 72-42 ATTN: Document Control Desk Director, Division of Spent Fuel Storage and Transportation Office of Nuclear Material Safety and Safeguards U. S. Nuclear Regulatory Commission Washington, D. C. 20555-0001 Joseph M. Farley Nuclear Plant - Units 1 and 2 Independent Spent Fuel Storage Installation Reoistration of Spent Fuel Cask Use Ladies and Gentlemen:

Southern Nuclear Operating Company (SNC) operates the Joseph M. Farley Nuclear Plant (FNP) Independent Spent Fuel Storage Installation (ISFSI) in accordance with the general license provisions of 10 CFR 72.210. The requirements of 10 CFR 72.212(b)(2) include registration ofa spent fuel cask within 30 days of using each cask for the storage of spent nuclear fuel.

Accordingly, SNC provides the following registration information associated with the HI-STORM 100 spent fuel cask systems placed intostorage in the FNP ISFSI.

Cask Certificate: 72-1014, Amendment 3 Overpack Model: HI-STORM 100S Overpack Serial Number: 582 MPC Model: MPC-32 MPC Serial Number: 0160 Date: March 24, 2014 Cask Certificate: 72-1014, Amendment 3 Overpack Model; HI-STORM 100S Overpack Serial Number: 583 MPC Model: MPC-32 MPC Serial Number: 0161 Date: April 8, 2014 Total Cask Systems Stored in the FNP ISFSI: 25

U. S. Nuclear Regulatory Commission NL-14-0604 Page 2 This letter contains no NRC commitments. Please contact Mr. Bill Arens at (334)-814-4765 if you have any questions.

Sincerely, Ms. C. /^ayheart Vice President - Farley CAG/JAC cc: Southern Nuclear Qperatino Company Mr. S. E. Kuczynski, Chairman, President & CEO Mr. D. G. Bost, Executive Vice President & Chief Nuclear Officer Mr. B. L. Ivey, Vice President - RegulatoryAffairs Mr. D. R. Madison. Vice President - Fleet Operations RTYPE; CFA04.054 U. S. Nuclear Regulatory Commission Mr. V. M. McCree, Regional Administrator Mr. S. A. Williams, Licensing Project Manager - Farley Mr. P. K. Niebaum, Senior Resident Inspector - Farley Mr. J. R. Sowa, Resident Inspector - Farley Mr. R. E. Martin, Senior Project Manager- Farley