NL-14-0085, Units 1 and 2, Response to the Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Flooding Walkdowns

From kanterella
Jump to navigation Jump to search

Units 1 and 2, Response to the Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Flooding Walkdowns
ML14030A255
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 01/29/2014
From: Ivey B
Southern Co, Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-14-0085
Download: ML14030A255 (4)


Text

B. l. "Pete" lvey Southern Nuclear Vice President Operating Company, Inc.

Regulatory Affairs 40 Inverness Center Parkway Post Office Box 1295 Birmingham, AL 35242 Tel 205.992.7619 Fax 205.992 .5217 January 29, 2014 Docket Nos.: 50-321 NL-14-0085 50-366 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington , D. C. 20555-0001 Edwin I. Hatch Nuclear Plant - Units 1 and 2 Response to the Request for Additional Information Associated with Near-Term Task Force Recommendation 2.3, Flooding Walkdowns References :

1. NRC Letter, Request for Information Pursuant to 10 CFR 50.54(f) Regarding Recommendations 2.1, 2.3, and 9.3, of the NTTF Review of Insights from the Fukushima Daiichi Accident, dated March 12, 2012. ML12073A348.
2. NRC Letter, Endorsement of Nuclear Energy Institute (NEI) 12-07, "Guidelines for Performing Verification Walkdowns of Plant Flood Protection Features," dated May 31, 2012. ML12144A142.
3. Letter to NRC, Edwin I. Hatch Nuclear Plant - Units 1 and 2, Flooding Recommendation 2.3 Walkdown Report, dated November 27, 2012.

ML12355A048.

4. NRC Letter, Request for Additional Information Associated with NTTF Recommendation 2.3, Flooding Walkdowns, dated December 23, 2013.

ML13325A891 .

Ladies and Gentlemen:

On March 12, 2012, the NRC staff issued Reference 1 requesting information in accordance with 10 CFR 50.54(f) . Enclosure 4 of that letter contains specific Requested Information associated with Near-Term Task Force Recommendation 2.3 for Flooding. Using NEI 12-07, as endorsed by the NRC in Reference 2, Southern Nuclear Operating Company (SNC) submitted Reference 3 in response to the request for information.

One of the requirements of NEI 12-07 is to identify the available physical margin (APM) associated with each applicable flood protection feature, determine if the margin provided is small, and evaluate any small margins that have potentially significant consequences through the corrective action process. The results of this effort were to be maintained on site for future NRC audits.

U. S. Nuclear Regulatory Commission NL-14-0085 Page 2 Following the NRC staff's initial review of the walkdown reports, regulatory site audits were conducted at a sampling of plants. Based on the walkdown report reviews and site audits, the staff identified additional information necessary to allow them to complete the assessments. Accordingly, by Reference 4 the NRC staff has issued a request for addition information (RAI). The RAI questions and the responses are provided below:

NRC RAI 1: Confirm that the process for evaluating APM was reviewed .

SNC Response: Southern Nuclear Operating Company has completed a review of the process used at the Edwin I. Hatch Nuclear Plant - Units 1 and 2 to evaluate APMs.

NRC RAI 2: Confirm that the APM process is now or was always consistent with the guidance in NEI 12-07 and discussed in this RAI.

SNC Response: The original walkdown effort followed the guidance provided in NEI 12-07. Additional actions have been taken to make the process consistent with the information provided in this RAI .

NRC RAI 3: If changes are necessary, provide a general description of any process changes to establish this consistency.

SNC Response: While the original walkdown effort followed the guidance provided in NEI 12-07, small margins have now been defined. Also , a specific APM had not been assigned to the seals associated with flood protection features. These items have now been addressed in accordance with the guidance provided in this RAI and entered into the corrective action process, as appropriate, for further evaluation.

NRC RAI 4: As a result of the audits and subsequent interactions with industry during public meetings, NRC staff recognized that evaluation of APM for seals (e.g., flood doors, penetrations, flood gates, etc.) was challenging for some licensees. Generally, licensees were expected to use either Approach A or Approach B (described below) to determine the APM for seals:

a) If seal pressure ratings were known , the seal ratings were used to determine APM (similar to example 2 in Section 3.13 of NEI 12-07). A numerical value for APM was documented. No further action was performed if the APM value was greater than the pre-established small-margin threshold value. If the APM value was small, an assessment of "significant consequences" was performed and the guidance in NEI 12-07 Section 5.8 was followed .

U.S. Nuclear Regulatory Commission NL-14-0085 Page 3 b) If the seal pressure rating was not known , the APM for seals in a flood barrier is assumed to be greater than the pre-established small-margin threshold value if the following conditions were met: (1) the APM for the barrier in which the seal is located is greater than the small-margin threshold value and there is evidence that the seals were designed/procured, installed , and controlled as flooding seals in accordance with the flooding licensing basis. Note that in order to determine that the seal has been controlled as a flooding seal, it was only necessary to determine that the seal configuration has been governed by the plant's design control process since installation. In this case, the APM for the seal could have been documented as "not small. "

As part of the RAI response, state if either Approach A or Approach 8 was used as part of the initial walkdowns or as part of actions taken in response to this RAI .

No additional actions are necessary if either Approach A or 8 was used.

If neither Approach A or 8 was used to determine the APM values for seals (either as part of the walkdowns or as part of actions taken in response to this RAI) , then perform the following two actions:

  • Enter the condition into the CAP (note: it is acceptable to utilize a single CAP entry to capture this issue for multiple seals). CAP disposition of "undetermined" APM values for seals should consider the guidance provided in NEI 12-07, Section 5.8. The CAP disposition should confirm all seals can perform their intended safety function against floods up to the current licensing basis flood height. Disposition may occur as part of the Integrated Assessment. If an Integrated Assessment is not performed, determine whether there are significant consequences associated with exceeding the capacity of the seals and take interim action(s) , if necessary, via the CAP processes. These actions do not need to be complete prior to the RAI response.
  • Report the APM as "undetermined" and provide the CAP reference in the RAI response.

SNC Response: Neither Approach A nor 8 , as described above, were used to determine the APM values for seals. All seals were inspected as part of the original walkdowns for signs of degradation, and corrective actions were taken, if required . As part of the actions taken to address this RAI , the seals have been assigned an APM value of "undetermined" and have been entered into the Corrective Action Program for further evaluation of their available physical margin. Implementation of interim actions will be pursued, if necessary.

This letter contains no new NRC commitments. If you have any questions, please contact John Giddens at 205.992.7924.

U. S. Nuclear Regulatory Commission NL-14-0085 Page4 Mr. B. L. lvey states he is a Vice President of Southern Nuclear Operating Company, is authorized to execute this oath on behalf of Southern Nuclear Operating Company and, to the best of his knowledge and belief, the facts set forth in this letter are true.

Respectfully submitted, Mr. B. L. lvey Vice President - Regulatory Affairs BLI/JMG Sworn to and subscribed before me this .itl 1-Jday of UtlY\1£C( ry ' 2014.

My commission expires: nHt rcA'\. )-3, :J.--o Jf cc: Southern Nuclear Operating Company Mr. S . E. Kuczynski, Chairman, President & CEO Mr. D . G . Bost, Executive Vice President & Chief Nuclear Officer Mr. D. R. Vineyard, Vice President - Hatch Mr. C . R. Pierce, Regulatory Affairs Director Mr. D. R. Madison, Vice President- Fleet Operations RType: CVC7000 U. S . Nuclear Regulatory Commission Mr. V . M. McCree, Regional Administrator Mr. R. E. Martin, NRR Senior Project Manager- Hatch Mr. E. D. Morris, Senior Resident Inspector- Hatch State of Georgia Mr. J. H. Turner, Environmental Director Protection Division