NL-05-0693, March 2005 Monthly Operating Reports for Edwin I. Hatch Nuclear Plant, Units 1 and 2

From kanterella
(Redirected from NL-05-0693)
Jump to navigation Jump to search
March 2005 Monthly Operating Reports for Edwin I. Hatch Nuclear Plant, Units 1 and 2
ML051080291
Person / Time
Site: Hatch  Southern Nuclear icon.png
Issue date: 04/12/2005
From: Sumner H
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NL-05-0693
Download: ML051080291 (3)


Text

H.L Sumner, Jr. Southern Nuclear Vice President Operating Company, Inc.

Hatch Project Post Office Box 1295 Birmingham. Alabama 35201 Tel 205.992.7279 SOUTHERN A4' April 12, 2005 COMPANY Energy to Serve YorWorld' Docket Nos.: 50-321 NL-05-0693 50-366 U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, D. C. 20555-0001 Edwin 1. Hatch Nuclear Plant Monthly Operating Reports Ladies and Gentlemen:

Enclosed are the March 2005 Monthly Operating Reports as required by section 5.6.4 of the Technical Specifications.

Technical Specifications (TS) Amendments 245 and 189 for Units I and 2, respectively, have been approved to delete the requirements of TS section 5.6.4. Future reporting of operations data will be submitted using the Consolidated Data Entry system, in accordance with TSTF 369, Rev. 1.

If you have any questions, please advise.

Sincerely, 096*7q 54-S H. L. Sumner, Jr.

HLS/IFL/daj

Enclosures:

1. HNP Unit I Monthly Operating Report
2. HNP Unit 2 Monthly Operating Report cc: Southern Nuclear Operating Company Mr. J. T. Gasser, Executive Vice President Mr. G. R. Frederick, General Manager - Plant Hatch RTYPE: CHAO2.004 U. S. Nuclear Regulatory Commission Dr. W. D. Travers, Regional Administrator Mr. C. Gratton, NRR Project Manager - Hatch Mr. D. S. Simpkins, Senior Resident Inspector - Hatch I---
1j \ , 6

OPERATING DATA REPORT DOCKET NO. 50D-321 UNIT NAME FF.ltch 1 DATE T Frl07, 00 COMPLETED BY Rig .6E. Drawdy TELEPHONE 9ii12) 366-2007 REPORTING PERIOD: March 2005

1. Design Electrical Rating 885.00
2. Maximum Dependable Capacity (MWe-Net) 876.00 This Month Yr-to-Date Cumulative
3. Number of Hours the Reactor was Critical 744.00 1,962.18 208,954.12
4. Number of Hours Generator On-line 744.00 1,929.42 202,886.57
5. Reserve Shutdown Hours 0.00 0.00 0.00
6. Net Electrical Energy Generated (MWHrs) 669,312.00 1,694,426.00 150,268,708.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Reason Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Down 2 Comments

SUMMARY

Unit 1 began the month of March operating at rated thermal power (2804 CMWt). Shift reduced load to approximately 903 GMWe (-2720 CMWt) on March 19 to perform a rod pattern adjustment. Unit 1 was returned to rated thermal power on March 20. Shift maintained unit operation at rated thermal power for the remainder of the month. There were no challenges to the safety relief valves.

1 2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

E 1-1

OPERATING DATA REPORT DOCKET NO. 50-366 UNIT NAME Hatch 2 DATE April 07, 2005 COMPLETED BY RKE.?Dhrawdy TELEPHONE (9121 366-200,7

- -I - -

REPORTING PERIOD: March 2005

1. Design Electrical Rating 908.00
2. Maximum Dependable Capacity (MWe-Net) 883.00 This Month Yr-to-Date Cumulative
3. Number of Hours the Reactor was Critical 461.87 1,302.62 184,681.37
4. Number of Hours Generator On-line 425.33 1,265.41 180,226.98
5. Reserve Shutdown Hours 0.00 0.00 0.00
6. Net Electrical Energy Generated (MWHrs) 341,238.00 1,051,037.00 136,152,082.0 UNIT SHUTDOWNS Type Method of F: Forced Duration Shutting Cause & Corrective Action No. Date S: Scheduled (Hours) Reason 1 Down 2 Comments05-001 02/05/2005 S 318.67 C 4 The 18th Refueling Outage activities continued.

SUMMARY

Unit 2 began the month of March with continuation of its 18th Refueling Outage. Core reload was completed on March 1. Shift brought the reactor critical on March 12, and then tied the main generator to the grid on March 14. Power ascension to rated thermal power was stopped at approximately 522 GMWe (-1660 CMWt) on March 15 to repair 2B reactor feed pump. Power ascension resumed on March 16, but was stopped at approximately 840 (-2550 CMWt) on March 17 to repair 2A condensate booster pump. Shift reduced power to - 700 GMWe (-2170 CMWt) later on March 17 to perform a rod pattern adjustment. Power ascension began late on March 17, and was stopped at -896 GMWe (-2690 CMWt) for current rod pattern. Shift reduced load to -835 GMWe (-2515 CMWt) on March 18 to perform a rod pattern adjustment. Shift continued power ascension and reached maximum operating power of -932 GMWe (-2787 CMWI) on March 19. Shift reduced load to -880 GMWe (-2635 CMWt) on March 20 to perform a rod pattern adjustment, and ramped to maximum operating power early on March 20. Shift reduced load to

- 890 GMWe (-2660 CMWt) on March 22 to perform a rod pattern adjustment. Shift ramped the unit to maximum operating power early on March 23. Shift raised the unit to 100% rated thermal power (-2804 CMWt) on March 24.

Shift reduced load to -835 GMWe (-2515 CMWt) on March 27 to perform control rod drive exercise and main turbine stop valve testing. Shift reached 100% rated thermal power on March 28. Shift continued unit operation at rated thermal power for the remainder of the month. There were no challenges to the safety relief valves.

1 2 Reason: Method:

A Equipment Failure (Explain) 1 Manual B Maintenance or Test 2 Manual Trip/Scram C Refueling 3 Automatic Trip/Scram D Regulatory Restriction 4 Continuation E Operator Training & License Examination 5 Other (Explain)

F Administration G Operational Error (Explain)

H Other (Explain)

E 2-1