NG-18-0013, Response to Second Request for Additional Information, Fifth Inservice Inspection Lnterval Program Plan, Relief Request RR-03

From kanterella
Jump to navigation Jump to search

Response to Second Request for Additional Information, Fifth Inservice Inspection Lnterval Program Plan, Relief Request RR-03
ML18026A779
Person / Time
Site: Duane Arnold NextEra Energy icon.png
Issue date: 01/26/2018
From: Dean Curtland
NextEra Energy Duane Arnold
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
NG-18-0013
Download: ML18026A779 (6)


Text

NEXTeraM ENERGY~

DUANE ARNOLD January 26, 2018 NG-18-0013 10 CFR 50.55a U. S. Nuclear Regulatory Commission ATTN: Document Control Desk Washington, DC 20555-0001 Duane Arnold Energy Center Docket No. 50-331 Renewed Op. License No. DPR-49 Response to Second Request for Additional Information. Fifth lnseNice Inspection lnteNal Program Plan. Relief Request RR-03

References:

1) Letter. Curtland (NextEra) to U.S. NRC. "Fifth lnservice Inspection lnteNal Program Plan. dated March 7. 2017 (ML17069A172)
2) Electronic Communication. Second Round of Request for Additional Information for DAEC Fifth lnservice Inspection lnteNal Program Plan. Relief Request No. RR-03. dated January 5, 2018.

In the Reference 1 letter, NextEra Energy Duane Arnold, LLC (hereafter NextEra Energy Duane Arnold) submitted our Fifth lnservice Inspection lnteNal Program Plan pursuant to 10 CFR 50.55a. The NRC Staff requested, via Reference 2, additional information regarding Relief Request RR-03 which is contained in Reference 1 .

The Enclosure to this letter contains the requested information.

Ne xtEra Energy Duane Arnold, LLC , 3277 DAEC Road, Palo , IA 52324

Document Control Desk NG-18-0013 Page 2 of 2 This letter does not contain any new or revised commitments.

If you have any questions or require additional information, please contact J. Michael Davis at 319-851-7032.

I declare under penalty of perjury that the foregoing is true and correct.

Executed on January 26, 2018 Dean Curtland Site Director NextEra Energy Duane Arnold, LLC Enclosure cc: NRC Regional Administrator NRC Resident Inspector NRC Project Manager

Enclosure to NG-18-0013 Response to Second Request for Additional Information, Fifth lnservice Inspection Interval Program Plan, Relief Request RR-03 3 pages follow

Enclosure to NG-18-0013 Page 1 of 3

1.0 INTRODUCTION

In the Reference 1 letter, NextEra Energy Duane Arnold, LLC (hereafter NextEra Energy Duane Arnold) submitted our Fifth lnservice Inspection Interval Program Plan pursuant to 10 CFR 50.55a. The NRC Staff requested, via Reference 2, additional information regarding Relief Request RR-03 which is contained in Reference 1. The requested information is given below.

2.0 REQUEST FOR ADDITIONAL INFORMATION By letter dated March 7, 2017 (Agency wide Documents Access and Management System Accession No. ML17069A172), NextEra Energy Duane Arnold, LLC (the licensee) submitted the fifth inservice inspection (ISi) interval program plan for Duane Arnold Energy Center (DAEC) for the U. S. Nuclear Regulatory Commission (NRC) review and approval. The program plan contains several relief requests from certain American Society of Mechanical Engineers Boiler and Pressure Vessel Code (ASME Code),Section XI, requirements.

Among them, Relief Request RR-03 proposed to use an alternative based on ASME Code Case N-702, "Alternative Requirements for Boiling Water Reactor (BWR) Nozzle Inner Radius and Nozzle-to-Shell Welds," for inspection of nozzle inner radius and nozzle-to-shell welds at Duane Arnold Energy Center (DAEC).

Background

On October 26, 2017 (ADAMS Accession No. ML17300A195), the licensee provided response to the NRC staff's request for additional information (RAI),

sent via an email dated August 8, 2017 (ADAMS Accession No. ML17220A333).

The NRC staff reviewed the RAI response and determined that additional information was required to complete the response. On November 7, 2017, a teleconference was held between the NRC staff and the NextEra representatives to discuss the needed information. As a result, on December 7, 2017 (ADAMS Accession No. ML17341A852), the licensee provided supplemental response to the original RAI. The NRC staff has reviewed this supplemental response and found four issues with the licensee's supplemental response:

  • The response states that there are no acceptance criteria for probability of failure (PoF) due to normal operation. The NRC staff noted that the acceptance criteria for PoF due to normal operation was established in the safety evaluation (SE) for the Boiling Water Reactor Vessel Internals Project (BWRVIP) report, BWRVIP-108, "Technical Basis for the Reduction of Inspection Requirements for the Boiling Water Reactor Nozzle-to-Vessel Shell Welds and Nozzle Blend Radii," (ADAMS Accession No. ML073600374).
  • The resp9nse states that linear elastic fracture mechanics (LEFM) is overly conservative for vessel material behavior at normal operating temperatures, and the number reported in the BWRVIP-108 SE for normal

Enclosure to NG-18-0013 Page 2 of 3 operation PoF was used for comparative purposes only. The NRC staff noted that normal operation includes heatup, cooldown, and hydro/pressure test, covering the entire temperature range. Therefore, using LEFM is appropriate. Further, the supplemental response by Boiling Water Reactor Vessel Internals Project (BWRVIP) in letter dated September 13, 2007 (ML072600167) to support BWRVIP-108 contains PoF values for both the normal operating condition and the low temperature overpressure (LTOP) condition for all simulation cases without emphasizing one condition. Therefore, during the BWRVIP-108 review, the BWRVIP and the NRC treated both normal operation condition and LTOP condition equally.

  • The response states that the PoF due to normal operation is irrelevant because when the plant stays within the required pressure-temperature (P-T) curve limits the regulatory required margin to failure is met. The NRC staff noted that the P-T limit or pressurized thermal shock (PTS) requirements are completely separated from the ASME inspection requirements. A plant meeting the P-T limit (BWRs and PWRs) or PTS (PWRs) requirements still needs to perform ASME Code required inspections. The inspection alternative proposed in BWRVIP-108 was based on the probabilistic fracture mechanics (PFM) results for the normal and LTOP conditions. Therefore, the PoF due to normal operation is essential information for the NRC staff's evaluation.
  • The response implied that conditional PoF is more relevant in this evaluation. In the risk evaluation, the NRC staff always considers the event frequency and the conditional PoF. If the event frequency is zero, then the value of conditional PoF is meaningless. Both were considered by the BWRVIP and the NRC staff during the BWRVIP-108 review.

Hence, the NRC staff determined that the following follow-up RAI is needed to complete the review of RR-03.

Follow-up RAI The licensee's October 26, 2017, response to the RAI contains a plant-specific PFM for the LTOP condition to support Relief Request RR-03. However, the PFM results in the supplemental response by Boiling Water Reactor Vessel Internals Project (BWRVIP) in letter dated September 13, 2007 (ML072600167) to support BWRVIP-108, indicated that the PFM results for normal operation are more limiting than the LTOP condition. Since the approval of BWRVIP-108 was based on the BWRVIP's PFM results, which indicated that both the normal condition and the LTOP condition satisfy the NRC's safety goal of 5x10-6, performing PFM results for the normal condition is essential. Please provide the PFM results for the normal condition, or quantitative information to demonstrate that the normal condition is not limiting for DAEC.

Enclosure to NG-18-0013 Page 3 of 3

RESPONSE

SI Calculation No. 1701150.301 Revision 1 determined that probability of failure (PoF) per reactor year due to a Low Temperature Over Pressure (LTOP) event for the nozzle-to-shell-weld and nozzle blend radii in the Duane Arnold N1 nozzles are below the acceptance criterion of 5x 1o-6 per year. The work was performed using the same methodology used in BWRVIP-108, which is the technical basis for ASME Code Case N-702 and similar to the work in BWRVIP-05.

In the NRC Staff's request for additional information, sent via email dated January 5, 2018 the PoF due to normal operation was requested to complete their response for NextEra's Relief Request RR-03.

In response to the RAI, the PoF due to normal operation was calculated for both the nozzle-to-shell-weld and nozzle blend radii in the Duane Arnold N1 nozzles.

For both components, there were no failures in two million simulations, which means the PoF is less than 8x1 o-9 . This is significantly below the PoF due to an LTOP event and the acceptance criterion of 5x1 o-6 per year. The normal operation PoF was calculated using the same methodology as the normal operation PoF number reported in the Safety Evaluation of BWRVIP-108.

3.0 REFERENCES

1) Letter, Curtland (NextEra) to U.S. NRC, "Fifth lnservice Inspection Interval Program Plan, dated March 7, 2017(ML17069A172).
2) Electronic Communication, Request for Additional Information - Duane Arnold Energy Center - Relief Request RR Alternative Requirements for Nozzle Inner Radius and Nozzle-To-Shell Welds, dated August 08, 2017.
3) Letter, Curtland (NextEra) to U.S. NRC, "Supplemental Response to Request for Additional Information, Fifth lnservice Inspection Interval Program Plan, Relief Request RR-03," dated December 7, 2017 (ML17341A852).
4) Electronic Communication, Second Round of Request for Additional Information for DAEC Fifth lnservice Inspection Interval Program Plan, Relief Request No. RR-03, dated January 5, 2018.