ND-18-0339, Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.2.03.08c.vii (Index Number 192)

From kanterella
Jump to navigation Jump to search
Unit 4 - Notice of Uncompleted ITAAC 225-days Prior to Initial Fuel Load Item 2.2.03.08c.vii (Index Number 192)
ML18082A335
Person / Time
Site: Vogtle  Southern Nuclear icon.png
Issue date: 03/23/2018
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of New Reactors
References
ITAAC 2.2.03.08c.vii, ND-18-0339
Download: ML18082A335 (6)


Text

A , kI I Michael J. Yox 7825 River Road Sk. Southern Nuclear Regulatory Affairs Director Waynesboro, GA 30830 Vogtle3&4 706-848-6459 tel 410-474-8587 cell myox @southernco.com MAR 2 3 2018 Docket Nos.: 52-025 52-026 ND-18-0339 10CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 3 and Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.2.03.08c.vii [Index Number 1921 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of March 21, 2018, Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Uncompleted Inspections, Tests, Analyses, and Acceptance Criteria (ITAAC) Item 2.2.03.08c.vii [Index Number 192] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing this ITAAC. Southern Nuclear Operating Company will, at a later date, provide additional notifications for ITAAC that have not been completed 225-days priorto initial fuel load.

This notification is informed by the guidance described in NEI 08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Tom Petrak at 706-848-1575.

Respectfully submitted.

Michael J. Yox Regulatory Affairs Direc/or Vogtle 3 &4

Enclosure:

Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.2.03.08c.vii [Index Number 192]

MJY/KJD/amw

U.S. Nuclear Regulatory Commission ND-18-0339 Page 2 of 3 To:

Southern Nuclear Operating Company / Georgia Power Company Mr. D. A. Bost (w/o enclosures)

Mr. M. D. Rauckhorst (w/o enclosures)

Mr. M. D. Meier Mr. D. H. Jones (w/o enclosures)

Mr. D. L. McKlnney Mr. M. J. Yox Mr. D. L. Fulton Mr. J. B. Klecha Mr. G. Chick Mr. F. H. Willis Ms. A. L. Pugh Mr. A. 8. Parton Mr. W. A. Sparkman Mr. C. E. Morrow Ms. K. M. Stacy Mr. M. K. Washington Mr. J. P. Redd Ms. A. C. Chamberlain Mr. D. R. Culver Mr. T. G. Petrak Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reoulatorv Commission Mr. W. Jones (w/o enclosures)

Ms. J. M. Heisserer Mr. C. P. Patel Mr. M. E. Ernstes Mr. G. J. Khouri Mr. T. E. Chandler Ms. S. E. Temple Ms. P. Braxton Mr. N. D. Karlovich Mr. A. J. Lerch Mr. C. J. Even Mr. F. D. Brown Mr. B. J. Kemker Ms. A. E. Rivera-Varona Ms. L. A. Kent Mr. P. B. Donnelly Qqiethoroe Power Corporation Mr. R. B. Brinkman MunlclDal Electric Authoritv of Georgia Mr. J. E. Fuller Mr. S. M. Jackson

U.S. Nuclear Regulatory Commission ND-18-0339 Page 3 of 3 Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. C. Durham (w/o enclosures)

Mr. M. M. Corletti Ms. L. G. Iller Mr. D. Hawkins Ms. J. Monahan Mr. J. L. Coward Ms. N. E. Deangelis Other Mr. J. E. Hesler, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, inc.

Mr. 8. Roetger, Georgia Public Sen/ice Commission Ms. 8. W. Kernizan, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-18-0339 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-18-0339 Enclosure Vogtle Electric Generating Plant (VEGP) Unit 3 and Unit 4 Completion Plan for Uncompleted ITAAC 2.2.03.08c.vll [Index Number 192]

U.S. Nuclear Regulatory Commission ND-18-0339 Enclosure Page 2 of 3 ITAAC Statement Design Commitment:

S.c) The PXS provides RCS makeup, boration, and safety injection during design basis events.

Inspections. Tests. Analvses:

vii) Inspection of the as-built components will be conducted for the plate located above the containment recirculation screens.

Acceptance Criteria:

vii) The plate located above the containment recirculation screens is no more than 1 ft, 3 in above the top of the face of the screens and extends at least 8 ft, 3 in perpendicular to the front and at least 7 ft to the side of the face of the screens.

ITAAC Completion Description Multiple ITAAC are performed to demonstrate the Passive Core Cooling system (PXS) provides Reactor Coolant System (RCS) makeup, boration, and safety injection during design basis events. For this ITAAC, an inspection of the as-built components is conducted for the plate located above the containment recirculation screens (PXS-MY-Y02A and PXS-MY-Y02B) to confirm the plate is located no more than 1 ft, 3 in above the top of the face of the screens and extends at least 8 ft, 3 in perpendicular to the front and at least 7 ft to the side of the face of the screens.

Inspections are performed on the as-built components by taking as-built measurements using survey equipment in accordance with Nuclear Construction and Startup Procedure (NCSP) 3-24, "Field Surveying" (Reference 1). NCSP 3-24 is used to establish layout and control points for determining the distance between the plate surfaces to the top and side face of the containment recirculation screens. The protective plate maximum height dimension is the distance between the top of the screens and the underside of the protective piate module top plate at the exposed edges of the protective plate, which extend into the containment recirculation water flow (east toward steam generator 2, and north toward the corridor), as described in the Updated Final Safety Analysis Report (UFSAR) Subsection 6.3.2.2.7 (Reference 2). Measurements are taken using survey equipment in accordance with site survey and measurement procedures to derive the distance between the as built components.

The results of the inspection are documented in the Unit 3 and Unit 4 inspection reports (References 3 and 4, respectively) confirming the plate is no more than 1 ft, 3 in above the top of the face of the screens (as-built distance is WW ft, YY in), extends out at least 8 ft, 3 in perpendicular to the front of the screens (as-built distance is WW ft, YY in), and extends between XXX and XXX to the side of the face of the screens (as-built distance is WW ft, YY in),

which meets the ITAAC Acceptance Criteria.

References 3 and 4 are available for NRC inspection as part of the Unit 3 and Unit 4 ITAAC 2.2.03.08c.vii Completion Packages (References 5 and 6, respectively).

U.S. Nuclear Regulatory Commission ND-18-0339 Enclosure Page 3 of 3 List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company (SNC) performed a review of all ITAAC findings and associated corrective actions.

This review found there are no relevant ITAAC findings associated with this ITAAC.

References favaiiabie for NRG inspection)

1. Nuclear Construction and Startup Procedure (NCSP) 3-24, "Field Surveying"
2. Vogtle 3&4 Updated Final Safety Analysis Report, Subsection 6.3.2.2.7 "IRWST and Containment Recirculation Screens"
3. SV3-1100-XXX-XXXXXX Inspection Report for Unit 3 ITAAC 2.2.03.08c.vii [COL Index Number 192]
4. SV4-1100-XXX-XXXXXX Inspection Report for Unit 4 ITAAC 2.2.03.08c.vii [COL Index Number 192]
5. Completion Package for Unit 3 ITAAC 2.2.03.08c.vii [COL Index Number 192]
6. Completion Package for Unit 4 ITAAC 2.2.03.08c.vii [COL Index Number 192]
7. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"