ND-21-0143, Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.2.03.08c.iii (Index Number 182)

From kanterella
Jump to navigation Jump to search
Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.2.03.08c.iii (Index Number 182)
ML21068A184
Person / Time
Site: Vogtle Southern Nuclear icon.png
Issue date: 03/09/2021
From: Yox M
Southern Nuclear Operating Co
To:
Document Control Desk, Office of Nuclear Reactor Regulation
References
ND-21-0143
Download: ML21068A184 (6)


Text

Michael J. Yox 7825 River Road hk. Southern Nuclear Regulatory Affairs Director Vogtle 3 & 4 Waynesboro, GA 30830 706-848-6459 tel MAR 0 9 2021 Docket No.: 52-026 ND-21-0143 10 CFR 52.99(c)(3)

U.S. Nuclear Regulatory Commission Document Control Desk Washington, DC 20555-0001 Southern Nuclear Operating Company Vogtle Electric Generating Plant Unit 4 Notice of Uncompleted ITAAC 225-davs Prior to Initial Fuel Load Item 2.2.03.08c.iii [Index Number 1821 Ladies and Gentlemen:

Pursuant to 10 CFR 52.99(c)(3), Southern Nuclear Operating Company hereby notifies the NRC that as of March 8, 2021, Vogtle Electric Generating Plant(VEGP) Unit 4 Uncompleted Inspection, Test, Analysis, and Acceptance Criteria (ITAAC) Item 2.2.03.08c.ill [Index Number 182] has not been completed greater than 225-days prior to initial fuel load. The Enclosure describes the plan for completing ITAAC 2.2.03.08c.ill [Index Number 182]. Southern Nuclear Operating Company will at a later date provide additional notifications for ITAAC that have not been completed 225-days prior to initial fuel load.

This notification is informed by the guidance described in NEI-08-01, Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52, which was endorsed by the NRC in Regulatory Guide 1.215. In accordance with NEI 08-01, this notification includes ITAAC for which required inspections, tests, or analyses have not been performed or have been only partially completed. All ITAAC will be fully completed and all Section 52.99(c)(1) ITAAC Closure Notifications will be submitted to NRC to support the Commission finding that all acceptance criteria are met prior to plant operation, as required by 10 CFR 52.103(g).

This letter contains no new NRC regulatory commitments.

If there are any questions, please contact Kelli Roberts at 706-848-6991 Respectfully submitted,

)^i Michael J. Yox ^

Regulatory Affairs DIrebfor Vogtle 3&4

Enclosure:

Vogtle Electric Generating Plant(VEGP) Unit 4 Completion Plan for Uncompleted ITAAC Item 2.2.03.08c.iii [Index Number 182]

MJY/WLP/sfr

U.S. Nuclear Regulatory Commission ND-21-0143 Page 2 of 3 To:

Southern Nuclear Operating Company/ Georgia Power Company Mr. Peter P. Sena III (w/o enclosures)

Mr. D. L. McKlnney (w/o enclosures)

Mr. M. D. Meier (w/o enclosures)

Mr. G. Chick Mr. S. Stimac Mr. P. Martino Mr. M. J. Yox Mr. A. S. Parton Ms. K. A. Roberts Mr. T. G. Petrak Mr. C. T. Defnall Mr. C. E. Morrow Mr. R. L. Belike Mr. S. Leighty Ms. A. C. Chamberlain Mr. J. C. Haswell Document Services RTYPE: VND.LI.L06 File AR.01.02.06 cc:

Nuclear Reouiatorv Commission Ms. M. Bailey (w/o enclosures)

Mr. M. King Ms. A. Veil Mr. C. P. Patel Mr. G. J. Khouri Mr. C. J. Even Mr. B. J. Kemker Ms. N. C. Coovert Mr. C. Welch Mr. J. Gaslevic Mr. O. Lopez-Santiago Mr. G. Armstrong Mr. M. Webb Mr. T. Fredette Mr. C. Santos Mr. B. Davis Mr. J. Vasquez Mr. J. Eargle Mr. E. Davidson Mr. T. Fanelli Mr. S. Rose Ms. K. McCurry

U.S. Nuclear Regulatory Commission ND-21-0143 Page 3 of 3 Oqlethorpe Power Corporation Mr. R. B. Brinkman Mr. E. Rasmussen Municipal Electric Authority of Georgia Mr. J. E. Fuller Mr. 8. M. Jackson Dalton Utilities Mr. T. Bundros Westinqhouse Electric Company. LLC Dr. L. Oriani (w/o enclosures)

Mr. D. 0. Durham (w/o enclosures)

Mr. M. M. CorlettI Mr. Z. 8. Harper Mr. J. L. Coward Other Mr. 8. W. Kline, Bechtel Power Corporation Ms. L. Matis, Tetra Tech NUS, Inc.

Dr. W. R. Jacobs, Jr., Ph.D., GDS Associates, inc.

Mr. 8. Roetger, Georgia Public Service Commission Mr. R. L. Trokey, Georgia Public Service Commission Mr. K. C. Greene, Troutman Sanders Mr. 8. Blanton, Baich Bingham

U.S. Nuclear Regulatory Commission ND-21-0143 Enclosure Page 1 of 3 Southern Nuclear Operating Company ND-21-0143 Enclosure Vogtle Electric Generating Plant(VEGP) Unit 4 Compietion Plan for Uncompleted ITAAC Item 2.2.03.08c.iii [Index Number 182]

U.S. Nuclear Regulatory Commission ND-21-0143 Enclosure Page 2 of 3 ITAAC Statement Design Commitment 8.c) The PXS provides PCS makeup, boration, and safety injection during design basis events.

Inspections/Tests/Analvses iii) Inspections of the routing of the following pipe lines will be conducted:

- CMT inlet line, cold leg to high point

- PRHR HX inlet line, hot leg to high point.

Acceptance Criteria iii) These lines have no downward sloping sections between the connection to the PCS and the high point of the line.

ITAAC Completion Description Multiple ITAAC are performed to demonstrate that the Passive Core Cooling System (PXS) provides Reactor Coolant System (PCS) makeup, boration, and safety injection during design basis events. This ITAAC requires that inspections be conducted to verify that the routing of the Core Makeup Tank(CMT)inlet lines from the cold leg and the Passive Residual Heat Removal Heat Exchanger(PRHR HX)inlet line from the hot leg have no downward sloping sections between the connection to the PCS and the high point of the lines.

The inspection of the routing of each CMT and PRHR HX inlet lines is performed during a walk-down of the as-built lines in accordance with the site walk down inspection procedure (Reference 1). When required to confirm the downward slope or lack of a downward slope, the slope of the lines is determined using survey equipment in accordance with site procedures (Reference 2).

The inspection results are documented in the Unit 4 inspection report (Reference 3) and determine that each CMT and the PRHR HX inlet lines have no downward sloping sections between their connection to the PCS and their respective high point of the line which meets the ITAAC acceptance criteria.

References 1, 2 and 3 are available for NRC inspection as well as the Unit 4 completion package (Reference 4).

U.S. Nuclear Regulatory Commission ND-21-0143 Enclosure Page 3 of 3 List of ITAAC Findings In accordance with plant procedures for ITAAC completion, Southern Nuclear Operating Company(SNC) performed a review of all findings pertaining to the subject ITAAC and associated corrective actions. This review found there are no relevant ITAAC findings associated with this ITAAC.

References(available for NRG inspection)

1. NCSP02-24,"ITAAC Support Activities"
2. 26139-000-4MP-T81C-N3201,"Construction Survey"
3. SV4-PXS-ITR-800182,"Unit 4 ITAAC 182 Walkdown 2.2.03.08c.iii NRC Index Number 182"
4. 2.2.03.08c.iii-U4-CP-Rev0, ITAAC Completion Package
5. NEI 08-01, "Industry Guideline for the ITAAC Closure Process Under 10 CFR Part 52"