EPID:L-2024-NTR-0003, EPRI - LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2-Loop, 3-Loop, and 4-Loop Plants - Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation (Approved, Closed) EPID:L-2024-TOP-0015, EPRI - LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2-Loop, 3-Loop, and 4-Loop Plants - Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation (Approved, Closed) |
Results
Other: ML24170A813, ML24170A891, ML24170A896, ML25014A290, ML25014A311, ML25080A217, ML25080A219, ML25080A320, ML25080A326, ML25080A327, ML25105A283, ML25105A284
|
MONTHYEARML24121A2092024-04-26026 April 2024 Request for Exemption of NRC Review Fees for Electric Power Research Institute (EPRI) - Analysis of PWR LOCA-Induced Fuel Fragmentation Relocation and Dispersal (FFRD) for Fuel Operating to Extended Burnup: Alternative Licensing Strategy Project stage: Request ML24121A2082024-04-30030 April 2024 EPRI - LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2-Loop, 3-Loop, and 4-Loop Plants - Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation Project stage: Request ML24170A8962024-06-24024 June 2024 NRC Form 897, Topical Report Withholding Determination, for EPRI Technical Report Report 3002028674 LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2-Loop, 3-Loop, and 4-Loop Plants (L-2024-TOP-0015) Project stage: Other ML24170A8912024-06-25025 June 2024 NRC Form 898, Topical Report Completeness Determination, for EPRI Technical Report 3002028674/5, LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2-Loop, 3-Loop, and 4-Loop Plants Project stage: Other ML24170A8132024-06-25025 June 2024 Acceptance and Withholding Determination for EPRI Alternative Licensing Strategy Which Addresses PWR LOCA-Induced Fuel Fragmentation, Relocation, and Dispersal Project stage: Other ML24225A1352024-08-27027 August 2024 Revision of Dates for Review of Electric Power Research Alternative Licensing Strategy Topical Reports Project stage: Approval ML24318C2522024-11-21021 November 2024 E Mail Issuance of Plan for EPRI Regulatory Audit of Technical Report 3002028675 Np 3002028674 P LOCA Analysis of FFRD for Westinghouse 2, 3, and 4 Loop Plant EPID L 2024 NTR0003 Project stage: Approval ML25014A3112025-02-0303 February 2025 Nonprop - Revised Audit Plan for EPRI Report 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for Westinghouse 2-Loop, 3-Loop & 4-Loop Plants, Eval of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Frag, Rev 0 Project stage: Other ML25014A2902025-02-0303 February 2025 E-mail - Revised Audit Plan for EPRI Report 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for Westinghouse 2-Loop, 3-Loop & 4-Loop Plants, Eval of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Frag, Rev 0 Project stage: Other ML25049A0432025-02-26026 February 2025 E-Mail-FINAL RAIs for EPRI Report 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for W 2-Loop, 3-Loop and 4-Loop Plants-Proprietary, Eval of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation, Rev. 0 Project stage: RAI ML25055A1172025-02-26026 February 2025 Nonproprietary - Report for Electric Power Research Institute Regulatory Audit in Support of Review of Technical Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components, Revision 0 Project stage: Approval ML25049A0442025-02-26026 February 2025 Nonproprietary - Final RAIs for EPRI Report 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for W 2-Loop, 3-Loop and 4-Loop Plants - Proprietary, Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation, Project stage: RAI ML25055A1142025-02-26026 February 2025 E-Mail - Issuance of Report for Electric Power Research Institute Regulatory Audit in Support of Review of Technical Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components, Revision 0 Project stage: Approval ML25080A3262025-03-21021 March 2025 EPRI Email Pointing Out the Change to 60 Days Project stage: Other ML25080A2192025-03-21021 March 2025 Nonproprietary - Final RAI-EPRI Rpt 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for W 2-, 3-, 4-Loop Plants - Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation - Rev. 0 Project stage: Other ML25080A3202025-03-21021 March 2025 NRC Email Documenting the Change from 60 to 90 Days Project stage: Other ML25080A3272025-03-21021 March 2025 NRC Email Acknowledging the Change and Stating Path Forward Project stage: Other ML25080A2172025-03-21021 March 2025 Email - Final RAI-EPRI Rpt 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for W 2-, 3-, 4-Loop Plants - Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation - Rev. 0 Project stage: Other ML25105A2832025-04-29029 April 2025 LOCA Analysis of FFRD for Westinghouse 2-Loop, 3-Loop and 4-Loop Plants Audit Report Cover Letter Project stage: Other ML25105A2842025-04-29029 April 2025 Enclosure 1: LOCA Analysis of FFRD for Westinghouse 2-Loop, 3-Loop and 4-Loop Plants Audit Report Nonproprietary (1) Project stage: Other ML26030A0292026-02-0909 February 2026 E-mail - Issuance of Safety Evaluation for EPRI Technical Report 3002028674/5, LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2-Loop, 3-Loop, and 4-Loop Plants, for Proprietary Review Project stage: Approval 2024-08-27
[Table View] |
Text
1 Lois James From:
Lois James Sent:
Monday, February 9, 2026 11:39 AM To:
Kucuk, Aylin Cc:
RidsNrrOd Resource; RidsNrrDnrl Resource; RidsNrrDnrlNphp Resource; RidsNrrDorlLlpb Resource; RidsNrrLADHarrison Resource; RidsNrrDraApob Resource; RidsNrrDss Resource; RidsNrrDssScpb Resource; RidsACRS_MailCTR Resource; RidsNrrDssSfnb Resource; RidsNrrDorl Resource; RidsNrrDra Resource; RidsNrrDnrlNvib Resource; RidsNrrDssSfnb Resource; Lois James; Ekaterina Lenning; Demetrius Murray; John Lehning; Brandon Wise; Seung Min; Scott Krepel; Matthew Mitchell; Aida Rivera-Varona; 'David.McIntyre@nrc.gov'; 'fsmith@epri.com'; Kucuk, Aylin
Subject:
Issuance of Safety Evaluation for EPRI Technical Report 3002028674/5, LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2 Loop, 3-Loop, and 4-Loop Plants, for Proprietary Review (EPID L 2024 NTR 0003)
Dr. Aylin Kucuk Program Manager, Nuclear Fuels Electric Power Research Institute Palo Alto Office 3420 Hillview Ave.
Palo Alto, CA 94304-133
Dear Dr. Aylin Kucuk:
By letter dated April 26, 2024 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML24121A203), Electric Power Research Institute (EPRI) submitted EPRI Report 3002028673, Loss-of-Coolant-Accident-Induced Fuel Fragmentation, Relocation, and Dispersal with Leak-Before-Break Credit -
Alternative Licensing Strategy [ALS], to the U.S. Nuclear Regulatory Commission (NRC) for review and approval.
The NRC staff has completed its review of the subject topical report and documented our review in the enclosed safety evaluation (SE).
Pursuant to Section 2.390 of Title 10 of the Code of Federal Regulations (10 CFR), we have determined that the SE for MRP-480 may contain proprietary information. If you believe that any information in the draft SE is proprietary, please identify such information line-by-line and define the basis pursuant to the criteria of 10 CFR 2.390. Use double brackets and yellow highlight to identify any [ proprietary information ].
A copy of the SE for proprietary review has been placed in the NRC external sharing folder. Kurshad Muftuoglu has been given access to the folder. The SE is being provided for a proprietary information review. If EPRI provides comments on other areas, the NRC staff will exercise its discretion on whether to address those comments.
Please provide your response within 30 days of the date of this e-mail. Your response must be via a letter from an authorized individual. The final SE will be issued after making any necessary changes.
Note that at this stage of the process, the NRC staff has completed its review of the submitted information and will not entertain technical arguments. The NRC staff conclusions and conditions will not change unless new information is provided on the docket that was not available during our review. If EPRI would like to discuss the enclosed SE in detail, we can do that in a noticed meeting.
If you have any questions, please feel free to contact me at lois.james@nrc.gov.
2 Lois James, Senior Project Manager Licensing Projects Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket No.: 99902021 EPID: L-2024-NTR-0003 ADAMS Accession Nos.: ML26030A027 (pkg); ML26030A029 (email); ML25349A054 (SE for prop review); ML26030A030 (concurrence block)