MONTHYEARML24121A2092024-04-26026 April 2024 Request for Exemption of NRC Review Fees for Electric Power Research Institute (EPRI) - Analysis of PWR LOCA-Induced Fuel Fragmentation Relocation and Dispersal (FFRD) for Fuel Operating to Extended Burnup: Alternative Licensing Strategy Project stage: Request ML24121A2082024-04-30030 April 2024 EPRI - LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2-Loop, 3-Loop, and 4-Loop Plants - Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation Project stage: Request ML24170A8962024-06-24024 June 2024 NRC Form 897, Topical Report Withholding Determination, for EPRI Technical Report Report 3002028674 LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2-Loop, 3-Loop, and 4-Loop Plants (L-2024-TOP-0015) Project stage: Other ML24170A8132024-06-25025 June 2024 Acceptance and Withholding Determination for EPRI Alternative Licensing Strategy Which Addresses PWR LOCA-Induced Fuel Fragmentation, Relocation, and Dispersal Project stage: Other ML24170A8912024-06-25025 June 2024 NRC Form 898, Topical Report Completeness Determination, for EPRI Technical Report 3002028674/5, LOCA Analysis of Fuel Fragmentation, Relocation, and Dispersal for Westinghouse 2-Loop, 3-Loop, and 4-Loop Plants Project stage: Other ML24225A1352024-08-27027 August 2024 Revision of Dates for Review of Electric Power Research Alternative Licensing Strategy Topical Reports Project stage: Approval ML24318C2522024-11-21021 November 2024 E Mail Issuance of Plan for EPRI Regulatory Audit of Technical Report 3002028675 Np 3002028674 P LOCA Analysis of FFRD for Westinghouse 2, 3, and 4 Loop Plant EPID L 2024 NTR0003 Project stage: Approval ML25014A2902025-02-0303 February 2025 E-mail - Revised Audit Plan for EPRI Report 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for Westinghouse 2-Loop, 3-Loop & 4-Loop Plants, Eval of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Frag, Rev 0 Project stage: Other ML25014A3112025-02-0303 February 2025 Nonprop - Revised Audit Plan for EPRI Report 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for Westinghouse 2-Loop, 3-Loop & 4-Loop Plants, Eval of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Frag, Rev 0 Project stage: Other ML25049A0442025-02-26026 February 2025 Nonproprietary - Final RAIs for EPRI Report 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for W 2-Loop, 3-Loop and 4-Loop Plants - Proprietary, Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation, Project stage: RAI ML25049A0432025-02-26026 February 2025 E-Mail-FINAL RAIs for EPRI Report 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for W 2-Loop, 3-Loop and 4-Loop Plants-Proprietary, Eval of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation, Rev. 0 Project stage: RAI ML25055A1142025-02-26026 February 2025 E-Mail - Issuance of Report for Electric Power Research Institute Regulatory Audit in Support of Review of Technical Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components, Revision 0 Project stage: Approval ML25055A1172025-02-26026 February 2025 Nonproprietary - Report for Electric Power Research Institute Regulatory Audit in Support of Review of Technical Report 3002025288, Enhanced Risk-Informed Categorization Methodology for Pressure Boundary Components, Revision 0 Project stage: Approval ML25080A2172025-03-21021 March 2025 Email - Final RAI-EPRI Rpt 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for W 2-, 3-, 4-Loop Plants - Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation - Rev. 0 Project stage: Other ML25080A2192025-03-21021 March 2025 Nonproprietary - Final RAI-EPRI Rpt 3002028675(NP)/3002028674(P), LOCA Analysis of FFRD for W 2-, 3-, 4-Loop Plants - Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation - Rev. 0 Project stage: Other ML25080A3202025-03-21021 March 2025 NRC Email Documenting the Change from 60 to 90 Days Project stage: Other ML25080A3272025-03-21021 March 2025 NRC Email Acknowledging the Change and Stating Path Forward Project stage: Other ML25080A3262025-03-21021 March 2025 EPRI Email Pointing Out the Change to 60 Days Project stage: Other ML25105A2842025-04-29029 April 2025 Enclosure 1: LOCA Analysis of FFRD for Westinghouse 2-Loop, 3-Loop and 4-Loop Plants Audit Report Nonproprietary (1) Project stage: Other ML25105A2832025-04-29029 April 2025 LOCA Analysis of FFRD for Westinghouse 2-Loop, 3-Loop and 4-Loop Plants Audit Report Cover Letter Project stage: Other 2024-06-25
[Table View] |
Text
1 Lois James From:
Lois James Sent:
Thursday, November 21, 2024 8:57 AM To:
akucuk@epri.com Cc:
RidsNrrOd Resource; RidsNrrDnrl Resource; RidsNrrDnrlNphp Resource; RidsNrrDorlLlpb Resource; RidsNrrLADHarrison Resource; RidsNrrDraApob Resource; RidsNrrDss Resource; RidsNrrDssScpb Resource; RidsACRS_MailCTR Resource; RidsNrrDssSfnb Resource; RidsNrrDorl Resource; RidsNrrDra Resource; RidsNrrDnrlNvib Resource; RidsNrrDssSfnb Resource; James Delosreyes; Lois James; Ekaterina Lenning; Demetrius Murray; John Lehning; Brandon Wise; Seung Min; David Rudland; Matthew Leech; Gerond George; Scott Krepel; Matthew Mitchell; Reinaldo Rodriguez; Michele Sampson (She/Her/Hers); Samuel Lee; Bo Pham; Aida Rivera-Varona; Jamie Pelton (She/Her); Meena Khanna (She/Her/Hers); Antonios Zoulis; Scott Burnell; Dave McIntyre; fsmith@epri.com; AKucuk@epri.com
Subject:
Issuance of Plan for Electric Power Research Institute Regulatory Audit in Support of Review of EPRI Report 3002028675 (NP)/3002028674 (P), LOCA Analysis of FFRD for W-2-, 3-and 4-Loop Plants - Eval of Cladding Rupture in High Burnup Fuel Fragmentation Attachments:
EPRI TRs 3002028674 and 3002028675 Regulatory Audit Plan.pdf Dr. Aylin Kucuk Program Manager, Nuclear Fuels Electric Power Research Institute Palo Alto Oice 3420 Hillview Ave.
Palo Alto, CA 94304-133
Dear Dr. Aylin Kucuk:
By letter dated April 26, 2024 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML24121A203), Electric Power Research Institute (EPRI) submitted (1) EPRI Report 3002028673, Loss-of-Coolant-Accident-Induced Fuel Fragmentation, Relocation, and Dispersal with Leak-Before-Break Credit -
Alternative Licensing Strategy [ALS], (2) EPRI Report 3002028675 (NP)/3002028674 (P), LOCA[Loss of Coolant Accident] Analysis of Fuel Fragmentation, Relocation, and Dispersal [FFRD] for Westinghouse 2-Loop, 3-Loop and 4-Loop Plants - Proprietary, Evaluation of Cladding Rupture in High Burnup Fuel Rods Susceptible to Fine Fragmentation (collectively called ALS for LOCA Analysis of FFRD), and (3) EPRI Report 3002023895, Materials Reliability Program: xLPR [Extremely Low Probability of Rupture] Estimation of PWR Loss-of-Coolant Accident Frequencies (MRP-480) to the U.S. Nuclear Regulatory Commission (NRC) for review and approval. The ALS for LOCA Analysis for FFRD topical report demonstrates acceptable performance for LOCA induced FFRD phenomena in high burnup pressurized water reactor (PWR) fuel.
By email dated June 25, 2024 (ADAMS Accession No. ML24170A812), the NRC accepted the EPRI topical reports (TRs) for review and approval. The NRC acceptance package includes completion forms and schedules for three TRs, and the withholding determination for the proprietary TR.
The NRC sta reviewed the EPRIs TR and determined that a regulatory audit would assist in the timely completion of the NRC stas review. The NRC sta will conduct a virtual regulatory audit to support its review of EPRI Report 3002028675 (NP)/3002028674 (P)in accordance with the enclosed audit plan.
ML24318C246 (pkg); ML24318C252 (email); ML24318C370 (audit plan)
^via eConcurrence *via e-mail NRR-106 OFFICE NRR/DORL/LLPB/PM NRR/DSS/SFNB/BC NRR/DNRL/NPHP/BC NRR/DRA/APLA/BC NAME LJames*
SKrepel*
MMitchell*
AZoulis^
DATE 11/13/2024 11/13/2024*
11/19/2024 11/20/2024 OFFICE NRR/DORL/LLPB/BC NRR/DORL/LLPB/PM NAME GGeorge^
LJames*
DATE 11/21/2024 11/21/2024