January 6, 2026 Mr. Christopher H. Mudrick, Sr.
Senior Vice President Constellation Energy Generation, LLC President and Chief Nuclear Officer Constellation Nuclear 200 Exelon Way Kennett Square, PA 19348
SUBJECT:
BRAIDWOOD STATION, UNITS 1 AND 2; BYRON STATION, UNIT NOS. 1 AND 2; CLINTON POWER STATION, UNIT NO. 1; DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3; LASALLE COUNTY STATION, UNITS 1 AND 2; LIMERICK GENERATING STATION, UNITS 1 AND 2; NINE MILE POINT NUCLEAR STATION, UNIT 2; PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3; AND QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 - ISSUANCE OF AMENDMENTS TO ADOPT TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER TSTF-599 (EPID L-2025-LLA-0125)
Dear Mr. Mudrick:
The U.S. Nuclear Regulatory Commission (NRC or the Commission) has issued the enclosed amendments (listed below) in response to the Constellation Energy Generation, LLC (CEG) application dated August 5, 2025 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML25218A063):
- 1.
Amendment No. 244 to Renewed Facility Operating License No. NPF-72 and Amendment No. 244 to Renewed Facility Operating License No. NPF-77 for Braidwood Station, Units 1 and 2, respectively;
- 2.
Amendment No. 242 to Renewed Facility Operating License No. NPF-37 and Amendment No. 242 to Renewed Facility Operating License No. NPF-66 for Byron Station, Unit Nos. 1 and 2, respectively;
- 3.
Amendment No. 258 to Facility Operating License No. NPF-62 for Clinton Power Station, Unit No. 1;
- 4.
Amendment No. 288 to Renewed Facility Operating License No. DPR-19 and Amendment No. 281 to Renewed Facility Operating License No. DPR-25 for Dresden Nuclear Power Station, Units 2 and 3, respectively;
- 5.
Amendment No. 266 to Renewed Facility Operating License No. NPF-11 and Amendment No. 251 to Renewed Facility Operating License No. NPF-18 for LaSalle County Station, Units 1 and 2, respectively;
- 6.
Amendment No. 269 to Renewed Facility Operating License No. NPF-39 and Amendment No. 231 to Renewed Facility Operating License No. NPF-85 Limerick Generating Station, Units 1 and 2, respectively;
- 7.
Amendment No. 200 to Renewed Facility Operating License No. NPF-69 for Nine Mile Point Nuclear Station, Unit 2;
- 8.
Amendment No. 347 to Subsequent Renewed Facility Operating License No. DPR-44 and Amendment No. 350 to Subsequent Renewed Facility Operating License No. DPR-56 for Peach Bottom Atomic Power Station, Units 2 and 3, respectively; and
- 9.
Amendment No. 303 to Renewed Facility Operating License No. DPR-29 and Amendment No. 299 to Renewed Facility Operating License No. DPR-30 for Quad Cities Nuclear Power Station, Units 1 and 2, respectively.
The amendments revise the technical specifications (TSs) for each facility in accordance with Technical Specifications Task Force (TSTF) Traveler TSTF-599, Revision 1, Eliminate Periodic Surveillance Test of Simultaneous Start of Redundant Diesel Generators. Specifically, the proposed change would delete a surveillance requirement (SR) in TS 3.8.1, AC [alternating current] Sources - Operating, to verify that diesel generators achieve a specific frequency and voltage within a specified time period when started simultaneously.
A copy of the NRC staffs Safety Evaluation is also enclosed. The Notice of Issuance will be included in the Commissions monthly Federal Register notice.
Sincerely,
/RA/
Scott P. Wall, Senior Project Manager Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation Docket Nos.: STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-461, 50-237, 50-249, 50-373, 50-374, 50-352, 50-353, 50-410, 50-277, 50-278, 50-254, and 50-265
Enclosures:
- 1. Amendment No. 244 to NPF-72
- 2. Amendment No. 244 to NPF-77
- 3. Amendment No. 242 to NPF-37
- 4. Amendment No. 242 to NPF-66
- 5. Amendment No. 258 to NPF-62
- 6. Amendment No. 288 to DPR-19
- 7. Amendment No. 281 to DPR-25
- 8. Amendment No. 266 to NPF-11
- 9. Amendment No. 251 to NPF-18
- 10. Amendment No. 269 to NPF-39
- 11. Amendment No. 231 to NPF-85
- 12. Amendment No. 200 to NPF-69
- 13. Amendment No. 347 to DPR-44
- 14. Amendment No. 350 to DPR-56
- 15. Amendment No. 303 to DPR-29
- 16. Amendment No. 299 to DPR-30
- 17. Safety Evaluation
- 18. Notices and Environmental Findings cc: Listserv
CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. STN 50-456 BRAIDWOOD STATION, UNIT 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 244 Renewed License No. NPF-72
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the renewed license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-72 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendix A as revised through Amendment No. 244 and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated into the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Renewed Facility Operating License and Technical Specifications Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 11:56:47 -05'00'
CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. STN 50-457 BRAIDWOOD STATION, UNIT 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 244 Renewed License No. NPF-77
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the renewed license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-77 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendix A as revised through Amendment No. 244 and the Environmental Protection Plan contained in Appendix B, both of which are attached to Renewed License No. NPF-72, dated January 27, 2016, are hereby incorporated into the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Renewed Facility Operating License and Technical Specifications Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 11:57:09 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NOS. 244 AND 244 RENEWED FACILITY OPERATING LICENSE NOS. NPF-72 AND NPF-77 BRAIDWOOD STATION, UNITS 1 AND 2 DOCKET NOS. STN 50-456 AND STN 50-457 Replace the following pages of the Renewed Facility Operating Licenses and Appendix A, Technical Specifications, with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Renewed Facility Operating Licenses REMOVE INSERT License NPF-72 License NPF-72 Page 3 Page 3 License NPF-77 License NPF-77 Page 3 Page 3 Technical Specifications REMOVE INSERT 3.8.1 - 13 3.8.1 - 13 Renewed License No. NPF-72 Amendment No. 244 (2)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Part 70, to receive, possess and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (3)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C.
This renewed license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level The licensee is authorized to operate the facility at reactor core power levels not in excess of 3645 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)
Technical Specifications The Technical Specifications contained in Appendix A as revised through Amendment No. 244 and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated into the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
Renewed License No. NPF-77 Amendment No. 244 (2)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Part 70, to receive, possess and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (3)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C.
The renewed license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level The licensee is authorized to operate the facility at reactor core power levels not in excess of 3645 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)
Technical Specifications The Technical Specifications contained in Appendix A as revised through Amendment No. 244 and the Environmental Protection Plan contained in Appendix B, both of which are attached to Renewed License No. NPF-72, dated January 27, 2016, are hereby incorporated into the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. STN 50-454 BYRON STATION, UNIT NO. 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 242 Renewed License No. NPF-37
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the renewed license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-37 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendix A as revised through Amendment No. 242 and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated into this renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Renewed Facility Operating License and Technical Specifications Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 11:57:42 -05'00'
CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. STN 50-455 BYRON STATION, UNIT NO. 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 242 Renewed License No. NPF-66
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance: (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-66 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendix A (NUREG-1113), as revised through Amendment No. 242, and the Environmental Protection Plan contained in Appendix B, both of which were attached to Renewed License No. NPF-37, dated November 19, 2015, are hereby incorporated into this renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Renewed Facility Operating License and Technical Specifications Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 11:58:06 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NOS. 242 AND 242 RENEWED FACILITY OPERATING LICENSE NOS. NPF-37 AND NPF-66 BYRON STATION, UNIT NOS. 1 AND 2 DOCKET NOS. STN 50-454 AND STN 50-455 Replace the following pages of the Renewed Facility Operating Licenses and Appendix A, Technical Specifications, with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Renewed Facility Operating Licenses REMOVE INSERT License NPF-37 License NPF-37 Page 3 Page 3 License NPF-66 License NPF-66 Page 3 Page 3 Technical Specifications REMOVE INSERT 3.8.1 - 13 3.8.1 - 13 Renewed License No. NPF-37 Amendment No. 242 (2)
Pursuant to the Act and 10 CFR Part 70, to receive, possess and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Updated Final Safety Analysis Report, as supplemented and amended; (3)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C.
The renewed license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level The licensee is authorized to operate the facility at reactor core power levels not in excess of 3645 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)
Technical Specifications The Technical Specifications contained in Appendix A as revised through Amendment No. 242 and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, are hereby incorporated into this renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
(3)
Deleted.
(4)
Deleted.
Renewed License No. NPF-66 Amendment No. 242 (2)
Pursuant to the Act and 10 CFR Part 70, to receive, possess and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Updated Final Safety Analysis Report, as supplemented and amended; (3)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility.
C.
The renewed license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level The licensee is authorized to operate the facility at reactor core power levels not in excess of 3645 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)
Technical Specifications The Technical Specifications contained in Appendix A (NUREG-1113), as revised through Amendment No. 242, and the Environmental Protection Plan contained in Appendix B, both of which were attached to Renewed License No. NPF-37, dated November 19, 2015, are hereby incorporated into this renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
(3)
Deleted.
CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. 50-461 CLINTON POWER STATION, UNIT NO. 1 AMENDMENT TO FACILITY OPERATING LICENSE Amendment No. 258 License No. NPF-62
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Facility Operating License No. NPF-62 is hereby amended to read as follows:
(2)
Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 258, are hereby incorporated into this license. Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 11:58:35 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NO. 258 FACILITY OPERATING LICENSE NO. NPF-62 CLINTON POWER STATION, UNIT NO. 1 DOCKET NO. 50-461 Replace the following pages of the Facility Operating License and Appendix A, Technical Specifications (TSs), with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License NPF-62 License NPF-62 Page 3 Page 3 TSs TSs 3.8 - 15 3.8 - 15 Amendment No. 258 (4)
Constellation Energy Generation, LLC, pursuant to the Act and to 10 CFR Parts 30, 40, and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (5)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; (6)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility. Mechanical disassembly of the GE14i isotope test assemblies containing Cobalt-60 is not considered separation; and (7)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, to intentionally produce, possess, receive, transfer, and use Cobalt-60.
C.
This license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level Constellation Energy Generation, LLC is authorized to operate the facility at reactor core power levels not in excess of 3473 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)
Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 258, are hereby incorporated into this license.
Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. 50-237 DRESDEN NUCLEAR POWER STATION, UNIT 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 288 Renewed License No. DPR-19
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. DPR-19 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 288, are hereby incorporated into this renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 11:58:59 -05'00'
CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. 50-249 DRESDEN NUCLEAR POWER STATION, UNIT 3 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 281 Renewed License No. DPR-25
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 3.B. of Renewed Facility Operating License No. DPR-25 is hereby amended to read as follows:
B.
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 281, are hereby incorporated into this renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 11:59:19 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NOS. 288 AND 281 RENEWED FACILITY OPERATING LICENSE NOS. DPR-19 AND DPR-25 DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 DOCKET NOS. 50-237 AND 50-249 Replace the following pages of the Renewed Facility Operating Licenses and Appendix A, Technical Specifications (TSs), with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License DPR-19 License DPR-19 Page 3 Page 3 License DPR-25 License DPR-25 Page 4 Page 4 TSs TSs 3.8.1 - 7 3.8.1 - 7 3.8.1 - 16 3.8.1 - 16 Renewed License No. DPR-19 Amendment No. 288 (2)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Part 70, to receive, possess and use at any time special nuclear materials as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Updated Final Safety Analysis Report, as supplemented and amended; (3)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct special nuclear materials as may be produced by the operation of the facility.
C.
This renewed operating license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I; is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level The licensee is authorized to operate the facility at steady state reactor core power levels not in excess of 2957 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 288, are hereby incorporated into this renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.
(3)
Operation in the coastdown mode is permitted to 40% power.
Renewed License No. DPR-25 Amendment No. 281
- f.
Surveillance Requirement 4.9.A.10 - Diesel Storage Tank Cleaning (Unit 3 and Unit 2/3 only)
Each of the above Surveillance Requirements shall be successfully demonstrated prior to entering into MODE 2 on the first plant startup following the fourteenth refueling outage (D3R14).
- 3.
This renewed operating license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations: 10 CFR Part 20, Section 30.34 of 10 CFR Part 30, Section 40.41 of 10 CFR Part 40, Sections 50.54 and 50.59 of 10 CFR Part 50, and Section 70.32 of 10 CFR Part 70; is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
A.
Maximum Power Level The licensee is authorized to operate the facility at steady state power levels not in excess of 2957 megawatts (thermal), except that the licensee shall not operate the facility at power levels in excess of five (5) megawatts (thermal), until satisfactory completion of modifications and final testing of the station output transformer, the auto-depressurization interlock, and the feedwater system, as described in the licensees telegrams; dated February 26, 1971, have been verified in writing by the Commission.
B.
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 281, are hereby incorporated into this renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.
C.
Reports The licensee shall make certain reports in accordance with the requirements of the Technical Specifications.
D.
Records The licensee shall keep facility operating records in accordance with the requirements of the Technical Specifications.
E.
Restrictions Operation in the coastdown mode is permitted to 40% power.
CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. 50-373 LASALLE COUNTY STATION, UNIT 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 266 Renewed License No. NPF-11
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC, dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-11 is hereby amended to read as follows:
(2)
Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 266, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated in the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 11:59:45 -05'00'
CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. 50-374 LASALLE COUNTY STATION, UNIT 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 251 Renewed License No. NPF-18
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC, dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act) and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-18 is hereby amended to read as follows:
(2)
Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 251, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated in the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 12:00:09 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NOS. 266 AND 251 RENEWED FACILITY OPERATING LICENSE NOS. NPF-11 AND NPF-18 LASALLE COUNTY STATION, UNITS 1 AND 2 DOCKET NOS. 50-373 AND 50-374 Replace the following pages of the Renewed Facility Operating Licenses and Appendix A, Technical Specifications (TSs), with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License NPF-11 License NPF-11 Page 3 Page 3 License NPF-18 License NPF-18 Page 3 Page 3 TSs TSs 3.8.1 - 8 3.8.1 - 8 3.8.1 - 20 3.8.1 - 20
Renewed License No. NPF-11 Amendment No. 266 (3)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of LaSalle County Station, Units 1 and 2, and such Class B and Class C low-level radioactive waste as may be produced by the operation of Braidwood Station, Units 1 and 2, Byron Station, Units 1 and 2, and Clinton Power Station, Unit 1.
C.
This renewed license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level The licensee is authorized to operate the facility at reactor core power levels not in excess of full power (3546 megawatts thermal).
(2)
Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 266, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated in the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
(3)
DELETED (4)
DELETED (5)
DELETED Am. 198 09/16/10 Am. 194 08/28/09 Am. 194 08/28/09 Am. 194 08/28/09 Am. 266 01/06/26
Renewed License No. NPF-18 Amendment No. 251 (2)
Pursuant to the Act and 10 CFR Part 70, to receive, possess and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (3)
Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Pursuant to the Act and 10 CFR Parts 30, 40, and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of LaSalle County Station, Units 1 and 2, and such Class B and Class C low-level radioactive waste as may be produced by the operation of Braidwood Station, Units 1 and 2, Byron Station, Units 1 and 2, and Clinton Power Station, Unit 1.
C.
This renewed license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level The licensee is authorized to operate the facility at reactor core power levels not in excess of full power (3546 megawatts thermal). Items in shall be completed as specified. Attachment 1 is hereby incorporated into this license.
(2)
Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A, as revised through Amendment No. 251, and the Environmental Protection Plan contained in Appendix B, are hereby incorporated in the renewed license. The licensee shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
Am. 185 09/16/10 Am. 251 01/06/26
0 CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. 50-352 LIMERICK GENERATING STATION, UNIT 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 269 Renewed License No. NPF-39
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC, dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-39 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 269, are hereby incorporated into this renewed license. Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 12:00:47 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NO. 269 RENEWED FACILITY OPERATING LICENSE NO. NPF-39 LIMERICK GENERATING STATION, UNIT 1 DOCKET NO. 50-352 Replace the following pages of the Renewed Facility Operating License and Appendix A, Technical Specifications (TSs), with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License NPF-39 License NPF-39 Page 3 Page 3 TSs TSs 3/4 8 - 7 3/4 8 - 7 3/4 8 - 9 3/4 8 - 9 Renewed License No. NPF-39 Amendment No. 269 (2)
Pursuant to the Act and 10 CFR Part 70, to receive, possess and to use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (3)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Pursuant to the Act and 10 CFR Parts 30, 40, 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility, and to receive and possess, but not separate, such source, byproduct, and special nuclear materials as contained in the fuel assemblies and fuel channels from the Shoreham Nuclear Power Station.
C.
This renewed license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I (except as exempted from compliance in Section 2.D. below) and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level Constellation Energy Generation, LLC is authorized to operate the facility at reactor core power levels not in excess of 3515 megawatts thermal (100% rated power) in accordance with the conditions specified herein and in Attachment 1 to this license. The items identified in Attachment 1 to this renewed license shall be completed as specified. Attachment 1 is hereby incorporated into this renewed license.
(2)
Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 269, are hereby incorporated into this renewed license. Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) 13.
Verifying that the following diesel generator lockout features prevent diesel generator starting only when required:
a)
Control Room Switch In Pull-To-Lock (With Local/Remote Switch in Remote) b)
Local/Remote Switch in Local c)
Emergency Stop f.
Deleted.
g.
In accordance with the Surveillance Frequency Control Program by:
1.
Draining each fuel oil storage tank, removing the accumulated sediment and cleaning the tank using a sodium hypochlorite or equivalent solution, and 2.
Performing a pressure test of those portions of the diesel fuel oil system designed to Section III, subsection ND of the ASME Code in accordance with ASME Code Section XI Article IWD-5000.
LIMERICK - UNIT 1 3/4 8-7 Amendment No. 32, 71, 186, 269
ELECTRICAL POWER SYSTEMS A.C. SOURCES - SHUTDOWN LIMITING CONDITION FOR OPERATION 3.8.1.2 As a minimum, the following A.C. electrical power sources shall be OPERABLE:
a.
One circuit between the offsite transmission network and the onsite Class 1E distribution system, and b.
Two diesel generators each with:
1.
A day fuel tank containing a minimum of 250 gallons of fuel.
2.
A fuel storage system containing a minimum of 33,500 gallons of fuel.
3.
A fuel transfer pump.
APPLICABILITY: OPERATIONAL CONDITIONS 4, 5, and *.
ACTION:
a.
With less than the above required A.C. electrical power sources OPERABLE, suspend CORE ALTERATIONS, handling of irradiated fuel in the secondary containment, and crane operations over the spent fuel storage pool when fuel assemblies are stored therein. In addition, when in OPERATIONAL CONDITION 5 with the water level less than 22 feet above the reactor pressure vessel flange, immediately initiate corrective action to restore the required power sources to OPERABLE status as soon as practical.
b.
The provisions of Specification 3.0.3 are not applicable.
SURVEILLANCE REQUIREMENTS 4.8.1.2 At least the above required A.C. electrical power sources shall be demonstrated OPERABLE per Surveillance Requirements 4.8.1.1.1 and 4.8.1.1.2, except for 4.8.1.1.1.b, 4.8.1.1.2.e.4, 4.8.1.1.2.e.5, 4.8.1.1.2.e.6, 4.8.1.1.2.e.7, 4.8.1.1.2.e.8.b, 4.8.1.1.2.e.11, 4.8.1.1.2.e.12, and 4.8.1.1.2.h.
- When handling irradiated fuel in the secondary containment.
LIMERICK - UNIT 1 3/4 8-9 Amendment No. 32,192,193,227,264,269
1 CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. 50-353 LIMERICK GENERATING STATION, UNIT 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 231 Renewed License No. NPF-85
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC, dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-85 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 231, are hereby incorporated into this renewed license. Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 12:01:10 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NO. 231 RENEWED FACILITY OPERATING LICENSE NO. NPF-85 LIMERICK GENERATING STATION, UNIT 2 DOCKET NO. 50-353 Replace the following pages of the Renewed Facility Operating License and Appendix A, Technical Specifications (TSs), with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License NPF-85 License NPF-85 Page 3 Page 3 TSs TSs 3/4 8 - 7 3/4 8 - 7 3/4 8 - 9 3/4 8 - 9 Renewed License No. NPF-85 Amendment No. 231 (2)
Pursuant to the Act and 10 CFR Part 70, to receive, possess and to use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (3)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess and use at any time any byproduct, source and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Pursuant to the Act and 10 CFR Parts 30, 40, 70, to receive, possess, and use in amounts as required any byproduct, source or special nuclear material without restriction to chemical or physical form, for sample analysis or instrument calibration or associated with radioactive apparatus or components; and (5)
Pursuant to the Act and 10 CFR Parts 30, 40 and 70, to possess, but not separate, such byproduct and special nuclear materials as may be produced by the operation of the facility, and to receive and possess, but not separate, such source, byproduct, and special nuclear materials as contained in the fuel assemblies and fuel channels from the Shoreham Nuclear Power Station.
C.
This renewed license shall be deemed to contain and is subject to the conditions specified in the Commissions regulations set forth in 10 CFR Chapter I (except as exempted from compliance in Section 2.D. below) and is subject to all applicable provisions of the Act and to the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified or incorporated below:
(1)
Maximum Power Level Constellation Energy Generation, LLC is authorized to operate the facility at reactor core power levels of 3515 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)
Technical Specifications The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, as revised through Amendment No. 231, are hereby incorporated into this renewed license. Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
ELECTRICAL POWER SYSTEMS SURVEILLANCE REQUIREMENTS (Continued) 13.
Verifying that the following diesel generator lockout features prevent diesel generator starting only when required:
a)
Control Room Switch In Pull-To-Lock (With Local/Remote Switch in Remote) b)
Local/Remote Switch in Local.
c)
Emergency Stop f.
Deleted.
g.
In accordance with the Surveillance Frequency Control Program by:
1.
Draining each fuel oil storage tank, removing the accumulated sediment and cleaning the tank using a sodium hypochlorite or equivalent solution, and 2.
Performing a pressure test of those portions of the diesel fuel oil system designed to Section III, subsection ND of the ASME Code in accordance with ASME Code Section XI Article IWD-5000.
LIMERICK - UNIT 2 3/4 8-7 Amendment No. 34, 147,231
ELECTRICAL POWER SYSTEMS A.C. SOURCES - SHUTDOWN LIMITING CONDITION FOR OPERATION 3.8.1.2 As a minimum, the following A.C. electrical power sources shall be OPERABLE:
a.
One circuit between the offsite transmission network and the onsite Class 1E distribution system, and b.
Two diesel generators each with:
1.
A day fuel tank containing a minimum of 250 gallons of fuel.
2.
A fuel storage system containing a minimum of 33,500 gallons of fuel.
3.
A fuel transfer pump.
APPLICABILITY: OPERATIONAL CONDITIONS 4, 5, and *.
ACTION:
a.
With less than the above required A.C. electrical power sources OPERABLE, suspend CORE ALTERATIONS, handling of irradiated fuel in the secondary containment, and crane operations over the spent fuel storage pool when fuel assemblies are stored therein. In addition, when in OPERATIONAL CONDITION 5 with the water level less than 22 feet above the reactor pressure vessel flange, immediately initiate corrective action to restore the required power sources to OPERABLE status as soon as practical.
b.
The provisions of Specification 3.0.3 are not applicable.
SURVEILLANCE REQUIREMENTS 4.8.1.2 At least the above required A.C. electrical power sources shall be demonstrated OPERABLE per Surveillance Requirements 4.8.1.1.1 and 4.8.1.1.2, except for 4.8.1.1.1.b, 4.8.1.1.2.e.4, 4.8.1.1.2.e.5, 4.8.1.1.2.e.6, 4.8.1.1.2.e.7, 4.8.1.1.2.e.8.b,4.8.1.1.2.e.11, 4.8.1.1.2.e.12, and 4.8.1.1.2.h.
- When handling irradiated fuel in the secondary containment.
LIMERICK - UNIT 2 3/4 8-9 Amendment No. 153,154,190,226,231
2 NINE MILE POINT NUCLEAR STATION, LLC LONG ISLAND LIGHTING COMPANY CONSTELLATION ENERGY GENERATION, LLC DOCKET NO. 50-410 NINE MILE POINT NUCLEAR STATION, UNIT 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 200 Renewed License No. NPF-69
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Renewed Facility Operating License No. NPF-69 is hereby amended to read as follows:
(2)
Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, as revised through Amendment No. 200, are hereby incorporated into this license. Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 12:01:37 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NO. 200 RENEWED FACILITY OPERATING LICENSE NO. NPF-69 NINE MILE POINT NUCLEAR STATION, UNIT 2 DOCKET NO. 50-410 Replace the following pages of the Renewed Facility Operating License and Appendix A, Technical Specifications (TSs), with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License NPF-69 License NPF-69 Page 4 Page 4 TSs TSs 3.8.1 - 18 3.8.1 - 18 Renewed License No. NPF-69 Amendment 117 through 197, 199, 200 (1)
Maximum Power Level Constellation Energy Generation, LLC is authorized to operate the facility at reactor core power levels not in excess of 3988 megawatts thermal (100 percent rated power) in accordance with the conditions specified herein.
(2)
Technical Specifications and Environmental Protection Plan The Technical Specifications contained in Appendix A and the Environmental Protection Plan contained in Appendix B, both of which are attached hereto, as revised through Amendment No. 200, are hereby incorporated into this license. Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications and the Environmental Protection Plan.
(3)
Fuel Storage and Handling (Section 9.1, SSER 4)*
- a. Fuel assemblies, when stored in their shipping containers, shall be stacked no more than three containers high.
- b. When not in the reactor vessel, no more than three fuel assemblies shall be allowed outside of their shipping containers or storage racks in the New Fuel Vault or Spent Fuel Storage Facility.
- c. The above three fuel assemblies shall maintain a minimum edge-to-edge spacing of twelve (12) inches from the shipping container array and approved storage rack locations.
- d. The New Fuel Storage Vault shall have no more than ten fresh fuel assemblies uncovered at any one time.
(4)
Turbine System Maintenance Program (Section 3.5.1.3.10 SER)
The operating licensee shall submit for NRC approval by October 31, 1989, a turbine system maintenance program based on the manufacturers calculations of missile generation probabilities.
(Submitted by NMPC letter dated October 30, 1989 from C.D. Terry and approved by NRC letter dated March 15, 1990 from Robert Martin to Mr. Lawrence Burkhardt, III).
- The parenthetical notation following the title of many license conditions denotes the section of the Safety Evaluation Report (SER) and/or its supplements wherein the license condition is discussed.
AC Sources - Operating 3.8.1 NMP2 3.8.1-18 Amendment 91, 152, 200 SURVEILLANCE REQUIREMENTS (continued)
SURVEILLANCE FREQUENCY SR 3.8.1.18 Deleted.
SR 3.8.1.19
- - - - - - - - - - - - - - -NOTE- - - - - - - - - - - - - - -
All DG starts may be preceded by an engine prelube period.
Verify each required DG start from standby conditions and achieves:
a.
In 10 seconds, voltage 3950 V for Division 1 and 2 DGs and 3820 V for Division 3 DG, and frequency 58.8 Hz for Division 1 and 2 DGs and 58.0 Hz for Division 3 DG; and b.
Steady state voltage 3950 V and 4370 V and frequency 58.8 Hz and 61.2 Hz.
In accordance with the Surveillance Frequency Control Program
3 CONSTELLATION ENERGY GENERATION, LLC PSEG NUCLEAR, LLC DOCKET NO. 50-277 PEACH BOTTOM ATOMIC POWER STATION, UNIT 2 AMENDMENT TO SUBSEQUENT RENEWED FACILITY OPERATING LICENSE Amendment No. 347 Subsequent Renewed License No. DPR-44
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Subsequent Renewed Facility Operating License No. DPR-44 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 347, are hereby incorporated in the license. Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Subsequent Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 12:02:06 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NO. 347 SUBSEQUENT RENEWED FACILITY OPERATING LICENSE NO. DPR-44 PEACH BOTTOM ATOMIC POWER STATION, UNIT 2 DOCKET NO. 50-277 Replace the following pages of the Subsequent Renewed Facility Operating License and Appendix A, Technical Specifications (TSs), with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License DPR-44 License DPR-44 Page 3 Page 3 TSs TSs 3.8 - 6 3.8 - 6 3.8 - 19 3.8 - 19 3.8 - 24 3.8 - 24
Page 3 Subsequent Renewed License No. DPR-44 Amendment No. 347 (1)
Constellation Energy Generation, LLC, pursuant to Section 104b of the Act and 10 CFR Part 50, Licensing of Production and Utilization Facilities, to possess, use, and operate the facility and PSEG Nuclear to possess the facility at the designated location in Peach Bottom, York County, Pennsylvania in accordance with the procedures and limitations set forth in this license; (2)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Part 70, to receive, possess, and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (3)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use at any time any byproduct, source, and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source, or special nuclear material without restriction to chemical or physical form for sample analysis or instrument calibration or when associated with radioactive apparatus or components; (5)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not to separate, such byproduct and special nuclear material as may be produced by operation of the facility, and such Class B and Class C low-level radioactive waste as may be produced by the operation of Limerick Generating Station, Units 1 and 2.
C.
This subsequent renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter I: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Section 50.54 of Part 50, and Section 70.32 of Part 70; all applicable provisions of the Act and the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified below:
(1)
Maximum Power Level Constellation Energy Generation, LLC is authorized to operate the Peach Bottom Atomic Power Station, Unit 2, at steady state reactor core power levels not in excess of 4016 megawatts thermal.
(2)
Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 347, are hereby incorporated in the license.
Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications.
4 CONSTELLATION ENERGY GENERATION, LLC PSEG NUCLEAR, LLC DOCKET NO. 50-278 PEACH BOTTOM ATOMIC POWER STATION, UNIT 3 AMENDMENT TO SUBSEQUENT RENEWED FACILITY OPERATING LICENSE Amendment No. 350 Subsequent Renewed License No. DPR-56
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 2.C.(2) of Subsequent Renewed Facility Operating License No. DPR-56 is hereby amended to read as follows:
(2)
Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 350, are hereby incorporated in the license. Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Subsequent Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 12:02:33 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NO. 350 SUBSEQUENT RENEWED FACILITY OPERATING LICENSE NO. DPR-56 PEACH BOTTOM ATOMIC POWER STATION, UNIT 3 DOCKET NO. 50-278 Replace the following pages of the Subsequent Renewed Facility Operating License and Appendix A, Technical Specifications (TSs), with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License DPR-56 License DPR-56 Page 3 Page 3 TSs TSs 3.8 - 6 3.8 - 6 3.8 - 19 3.8 - 19 3.8 - 24 3.8 - 24
Page 3 Subsequent Renewed License No. DPR-56 Amendment No. 350 Pennsylvania in accordance with the procedures and limitations set forth in this license; (2)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Part 70, to receive, possess, and use at any time special nuclear material as reactor fuel, in accordance with the limitations for storage and amounts required for reactor operation, as described in the Final Safety Analysis Report, as supplemented and amended; (3)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40, and 70, to receive, possess, and use at any time any byproduct, source, and special nuclear material as sealed neutron sources for reactor startup, sealed sources for reactor instrumentation and radiation monitoring equipment calibration, and as fission detectors in amounts as required; (4)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30, 40 and 70, to receive, possess, and use in amounts as required any byproduct, source, or special nuclear material without restriction to chemical or physical form for sample analysis or instrument calibration or when associated with radioactive apparatus or components; (5)
Constellation Energy Generation, LLC, pursuant to the Act and 10 CFR Parts 30 and 70, to possess, but not to separate, such byproduct and special nuclear material as may be produced by operation of the facility, and such Class B and Class C low-level radioactive waste as may be produced by the operation of Limerick Generating Station, Units 1 and 2.
C.
This subsequent renewed license shall be deemed to contain and is subject to the conditions specified in the following Commission regulations in 10 CFR Chapter I: Part 20, Section 30.34 of Part 30, Section 40.41 of Part 40, Section 50.54 of Part 50, and Section 70.32 of Part 70; all applicable provisions of the Act and the rules, regulations, and orders of the Commission now or hereafter in effect; and is subject to the additional conditions specified below:
(1)
Maximum Power Level Constellation Energy Generation, LLC is authorized to operate the Peach Bottom Atomic Power Station, Unit No. 3, at steady state reactor core power levels not in excess of 4016 megawatts thermal.
(2)
Technical Specifications The Technical Specifications contained in Appendices A and B, as revised through Amendment No. 350, are hereby incorporated in the license.
Constellation Energy Generation, LLC shall operate the facility in accordance with the Technical Specifications.
AC Sources-Operating 3.8.1 SURVEILLANCE SR 3.8.1.20 Deleted.
SR 3.8.1.21
NOTE-------------------
When Unit 2 is in MODE 4 or 5, or moving irradiated fuel assemblies in the secondary containment, the Note to Unit 2 SR 3.8.2.1 is applicable.
PBAPS UNIT 3 For required Unit 2 AC sources, the SRs of Unit 2 Specification 3.8.1, except SR 3.8.1.8 (when only one Unit 2 offsite circuit is required), SR 3.8.1.12, SR 3.8.1.13, SR 3.8.1.17, SR 3.8.1.18 (ECCS load block requirement only), and SR 3.8.1.19, are applicable.
3.8-19 FREQUENCY In accordance with applicable SRs Amendment No. 350
AC Sources -Shutdown 3.8.2 SURVEILLANCE REQUIREMENTS SR 3.8.2.1 SR 3.8.2.2 PBAPS UNIT 3 SURVEILLANCE
NOTE--------------------
The following SRs are not required to be performed: SR 3.8.1.3, SR 3.8.1.9 through SR 3.8.1.11, SR 3.8.1.13 through SR 3.8.1.16, SR 3.8.1.18, and SR 3.8.1.19.
NOTE--------------------
The requirements of SR 3.8.1.12, SR 3.8.1.13, and SR 3.8.1.19 are not required to be met during periods that ECCS are not required.
For required Unit 3 AC sources the SRs of Specification 3.8.1, except SR 3.8.1.8 and SR 3.8.1.17 are applicable.
NOTE--------------------
When Unit 2 is not in MODE 1, 2, or 3, the Note to Unit 2 SR 3.8.2.1 is applicable.
For required Unit 2 AC sources, the SRs of Unit 2 Specification 3.8.1, except SR 3.8.1.8 (when only one Unit 2 offsite circuit is required), SR 3.8.1.12, SR 3.8.1.13, SR 3.8.1.17, SR 3.8.1.18 (ECCS load block requirement only) and SR 3.8.1.19 are applicable.
3.8-24 FREQUENCY In accordance with applicable SRs In accordance with applicable SRs Amendment No. 350
5 CONSTELLATION ENERGY GENERATION, LLC AND MIDAMERICAN ENERGY COMPANY DOCKET NO. 50-254 QUAD CITIES NUCLEAR POWER STATION, UNIT 1 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 303 Renewed License No. DPR-29
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 3.B. of Renewed Facility Operating License No. DPR-29 is hereby amended to read as follows:
B.
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 303, are hereby incorporated into this renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 12:03:20 -05'00'
6 CONSTELLATION ENERGY GENERATION, LLC AND MIDAMERICAN ENERGY COMPANY DOCKET NO. 50-265 QUAD CITIES NUCLEAR POWER STATION, UNIT 2 AMENDMENT TO RENEWED FACILITY OPERATING LICENSE Amendment No. 299 Renewed License No. DPR-30
- 1.
The U.S. Nuclear Regulatory Commission (the Commission) has found that:
A.
The application for amendment by Constellation Energy Generation, LLC dated August 5, 2025, complies with the standards and requirements of the Atomic Energy Act of 1954, as amended (the Act), and the Commissions rules and regulations set forth in 10 CFR Chapter I; B.
The facility will operate in conformity with the application, the provisions of the Act, and the rules and regulations of the Commission; C.
There is reasonable assurance (i) that the activities authorized by this amendment can be conducted without endangering the health and safety of the public, and (ii) that such activities will be conducted in compliance with the Commissions regulations; D.
The issuance of this amendment will not be inimical to the common defense and security or to the health and safety of the public; and E.
The issuance of this amendment is in accordance with 10 CFR Part 51 of the Commissions regulations and all applicable requirements have been satisfied.
- 2.
Accordingly, the license is amended by changes to the Technical Specifications as indicated in the attachment to this license amendment, and paragraph 3.B. of Renewed Facility Operating License No. DPR-30 is hereby amended to read as follows:
B.
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 299, are hereby incorporated into this renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.
- 3.
This license amendment is effective as of the date of its issuance and shall be implemented within 60 days of the date of issuance.
FOR THE NUCLEAR REGULATORY COMMISSION Ilka T. Berrios, Acting Chief Plant Licensing Branch III Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation
Attachment:
Changes to the Technical Specifications and Renewed Facility Operating License Date of Issuance: January 6, 2026 ILKA BERRIOS Digitally signed by ILKA BERRIOS Date: 2026.01.06 12:03:46 -05'00'
ATTACHMENT TO LICENSE AMENDMENT NOS. 303 AND 299 RENEWED FACILITY OPERATING LICENSE NOS. DPR-29 AND DPR-30 QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 DOCKET NOS. 50-254 AND 50-265 Replace the following pages of the Renewed Facility Operating Licenses and Appendix A, Technical Specifications (TSs), with the attached revised pages. The revised pages are identified by amendment number and contain marginal lines indicating the areas of change.
Remove Insert License DPR-29 License DPR-29 Page 4 Page 4 License DPR-30 License DPR-30 Page 4 Page 4 TSs TSs 3.8.1 - 6 3.8.1 - 6 3.8.1 - 16 3.8.1 - 16 Renewed License No. DPR-29 Amendment No. 303 B.
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 303, are hereby incorporated into this renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.
C.
The licensee shall maintain the commitments made in response to the March 14, 1983, NUREG-0737 Order, subject to the following provision:
The licensee may make changes to commitments made in response to the March 14, 1983, NUREG-0737 Order without prior approval of the Commission as long as the change would be permitted without NRC approval, pursuant to the requirements of 10 CFR 50.59. Consistent with this regulation, if the change results in an Unreviewed Safety Question, a license amendment shall be submitted to the NRC staff for review and approval prior to implementation of the change.
D.
Equalizer Valve Restriction Three of the four valves in the equalizer piping between the recirculation loops shall be closed at all times during reactor operation with one bypass valve open to allow for thermal expansion of water.
E.
The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822), and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined sets of plans1, which contain Safeguards Information protected under 10 CFR 73.21, is entitled: Quad Cities Nuclear Power Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 2, submitted by letter dated May 17, 2006.
Constellation Energy Generation, LLC shall fully implement and maintain in effect all provisions of the Commission-approved cyber security plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p).
The CSP was approved by License Amendment No. 249 as modified by License Amendment No. 259.
1 The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.
Renewed License No. DPR-30 Amendment No. 299 B.
Technical Specifications The Technical Specifications contained in Appendix A, as revised through Amendment No. 299, are hereby incorporated into this renewed operating license. The licensee shall operate the facility in accordance with the Technical Specifications.
C.
The licensee shall maintain the commitments made in response to the March 14, 1983, NUREG-0737 Order, subject to the following provision:
The licensee may make changes to commitments made in response to the March 14, 1983, NUREG-0737 Order without prior approval of the Commission as long as the change would be permitted without NRC approval, pursuant to the requirements of 10 CFR 50.59. Consistent with this regulation, if the change results in an Unreviewed Safety Question, a license amendment shall be submitted to the NRC staff for review and approval prior to implementation of the change.
D.
Equalizer Valve Restriction Three of the four valves in the equalizer piping between the recirculation loops shall be closed at all times during reactor operation with one bypass valve open to allow for thermal expansion of water.
E.
The licensee shall fully implement and maintain in effect all provisions of the Commission-approved physical security, training and qualification, and safeguards contingency plans including amendments made pursuant to provisions of the Miscellaneous Amendments and Search Requirements revisions to 10 CFR 73.55 (51 FR 27817 and 27822), and the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The combined set of plans1, which contain Safeguards Information protected under 10 CFR 73.21, is entitled: Quad Cities Nuclear Power Station Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, Revision 2, submitted by letter dated May 17, 2006.
Constellation Energy Generation, LLC shall fully implement and maintain in effect all provisions of the Commission-approved cyber security plan (CSP), including changes made pursuant to the authority of 10 CFR 50.90 and 10 CFR 50.54(p). The CSP was approved by License Amendment No. 244 and modified by License Amendment No. 254.
1 The Training and Qualification Plan and Safeguards Contingency Plan are Appendices to the Security Plan.
7 SAFETY EVALUATION BY THE OFFICE OF NUCLEAR REACTOR REGULATION RELATED TO AMENDMENT NO. 244 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-72 AMENDMENT NO. 244 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-77 AMENDMENT NO. 242 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-37 AMENDMENT NO. 242 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-66 AMENDMENT NO. 258 TO FACILITY OPERATING LICENSE NO. NPF-62 AMENDMENT NO. 288 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-19 AMENDMENT NO. 281 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-25 AMENDMENT NO. 266 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-11 AMENDMENT NO. 251 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-18 AMENDMENT NO. 269 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-39 AMENDMENT NO. 231 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-85 AMENDMENT NO. 200 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-69 AMENDMENT NO. 347 TO SUBSEQUENT RENEWED FACILITY OPERATING LICENSE NO. DPR-44 AMENDMENT NO. 350 TO SUBSEQUENT RENEWED FACILITY OPERATING LICENSE NO. DPR-56 AMENDMENT NO. 303 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-29 AND AMENDMENT NO. 299 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-30 CONSTELLATION ENERGY GENERATION, LLC BRAIDWOOD STATION, UNITS 1 AND 2 BYRON STATION, UNIT NOS. 1 AND 2 CLINTON POWER STATION, UNIT NO. 1 DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 LASALLE COUNTY STATION, UNITS 1 AND 2 LIMERICK GENERATING STATION, UNITS 1 AND 2 NINE MILE POINT NUCLEAR STATION, UNIT 2 PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 DOCKET NOS. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-461, 50-237, 50-249, 50-373, 50-374, 50-352, 50-353, 50-410, 50-277, 50-278, 50-254, AND 50-265 Application (i.e., initial and supplements)
Safety Evaluation Date August 5, 2025, ML25218A063 January 6, 2026 Principal Contributors to Safety Evaluation Khadijah West Scott Wall
1.0 PROPOSED CHANGE
S Constellation Energy Generation, LLC (CEG, the licensee) requested changes to the technical specifications (TSs) for Braidwood Station, Units 1 and 2 (Braidwood); Byron Station, Unit Nos. 1 and 2 (Byron); Clinton Power Station, Unit No. 1 (Clinton); Dresden Nuclear Power Station, Units 2 and 3 (Dresden); Lasalle County Station, Units 1 and 2 (Lasalle); Limerick Generating Station, Units 1 and 2 (Limerick); Nine Mile Point Nuclear Station, Unit 2 (NMP-2);
Peach Bottom Atomic Power Station, Units 2 and 3 (Peach Bottom); and Quad Cities Nuclear Power Station, Units 1 and 2 (Quad Cities) (collectively, the CEG facilities), by license amendment request (LAR, application). The proposed changes would revise the TSs for each facility based on Technical Specifications Task Force (TSTF) Traveler TSTF-599, Revision 1, Eliminate Periodic Surveillance Test of Simultaneous Start of Redundant Diesel Generators (TSTF-599) (Agencywide Documents Access and Management System (ADAMS) Accession No. ML25093A204), and the associated U.S. Nuclear Regulatory Commission (NRC, the Commission) staff final safety evaluation (SE) of Traveler TSTF-599 (ML25119A288).
Specifically, the proposed change would delete a surveillance requirement (SR) in TS 3.8.1, AC [alternating current] Sources - Operating, to verify that diesel generators (DGs) achieve a specific frequency and voltage within a specified time period when started simultaneously.
1.1
System Description
The Class 1E AC electrical power distribution systems onsite standby power sources provide independence and redundancy to ensure an available source of power to the engineered safety feature (ESF) systems when the offsite or preferred power sources are unavailable. Specifically, the onsite standby power source consists of emergency DGs to power ESF buses. A safety injection (SI) signal or a loss of offsite power (i.e., an ESF bus degraded voltage or undervoltage) signal will automatically start the DGs. If DGs start due to a loss of offsite power signal (independent of or coincident with an SI signal), the DGs will automatically tie to their respective ESF buses. If the DGs receive an SI signal alone, they will start and operate in standby mode (i.e., without tying to the ESF buses.) Following the trip of offsite power, nonpermanent loads are stripped from the ESF buses. When the DGs are tied to the ESF buses, emergency loads are then sequentially connected to their respective ESF buses by the automatic load sequencer. The sequencing logic controls the permissive and starting signals to motor breakers to prevent overloading the DGs by automatic load application.
In the event of a loss of preferred (offsite) power, the ESF electrical loads are automatically connected to the DGs in sufficient time to provide for safe reactor shutdown and to mitigate the consequences of a design basis accident, such as a loss of coolant accident.
1.2 Proposed TS Changes to Adopt TSTF-599 The licensee proposed deleting the SR that requires a simultaneous start of the DGs. For the CEG facilities (except for Limerick and NMP-2), it is found in SR 3.8.1.20 of TS 3.8.1. For NMP-2, the requirement is found in SR 3.8.1.18 of TS 3.8.1. For Limerick, the requirement is found in SR 4.8.1.1.2.f of TS 3/4 8.1, AC Sources - Operating.
In addition to the DG simultaneous start test, TSTF-599 also deletes from Standard TS (STS) any references to SR 3.8.1.20 in located in other TS. Similarly, the licensee proposed the following associated changes:
For Limerick The licensee requested to remove footnote
- referenced in SR 4.8.1.1.2.f.
In TS 3.8.1.2, AC Sources - Shutdown, the licensee proposed deleting a reference to SR 4.8.1.1.2.f found in SR 4.8.1.2.
For Dresden, LaSalle, Peach Bottom, and Quad Cities The licensee requested to change a NOTE above the SR section that begins SR 3.8.1.1 through SR 3.8.1.20 to SR 3.8.1.1 through SR 3.8.1.19 For Dresden, LaSalle, and Quad Cities The licensee requested to delete from SR 3.8.1.21 (list of SRs applicable to opposite units required DGs) the reference to SR 3.8.1.20.
For Peach Bottom The licensee requested to delete reference SR 3.8.1.20 from TS 3.8.2, AC Sources -
Shutdown, SR 3.8.2.1 and SR 3.8.1.2, which list the SRs required during shutdown for the associated unit and opposite unit For NMP-2 The licensee noted that the NMP-2 TSs has different numbering than the STSs.
Specifically, SR 3.8.1.18 is deleted from the Limerick TS which is equivalent to STS SR 3.8.1.20.
1.3 Proposed Changes to Technical Specification Bases Consistent with Title 10 of the Code of Federal Regulations (10 CFR) Section 50.36(a)(1), the licensee submitted corresponding changes to the TS Bases, for information only, that provide the reasons for the proposed TSs changes. The regulation at 10 CFR 50.36(a)(1) states that a summary statement of the bases or reasons for such specifications, other than those covering administrative controls, shall also be included in the application, but shall not become part of the TS. The licensee shall make changes to the plant TS Bases in accordance with the TS Bases Control Program, found at TS 5.5.10 for Dresden, NMP-2, Peach Bottom, and Quad Cities,.at TS 5.5.11 for Clinton and LaSalle, at TS 5.5.14 for Braidwood and Byron, and at TS 6.8.4.h for Limerick.
2.0 REGULATORY EVALUATION
2.1 Applicable Regulatory Requirements and Guidance Per 10 CFR 50.90, whenever a holder of a license wishes to amend the license, including technical specifications in the license, an application for amendment must be filed, fully describing the changes desired. Under 10 CFR Part 50.92(a), determinations on whether to grant an applied-for license amendment are to be guided by the considerations that govern the issuance of initial licenses or construction permits to the extent applicable and appropriate. Both the common standards for licenses and construction permits in 10 CFR Part 50.40(a), and those specifically for issuance of operating licenses in 10 CFR Part 50.57(a)(3), provide that there must be reasonable assurance that the activities at issue will not endanger the health and safety of the public.
The regulation in 10 CFR 50.36, Technical specifications, provides the regulatory requirements for the content of the TS. It requires, in part, that a summary statement of the bases for such specifications shall be included by applicants for a license authorizing operation of a production or utilization facility. Specifically, the regulation in 10 CFR 50.36(c)(3),
Surveillance requirements, states that [s]urveillance requirements are requirements related to test, calibration, or inspection to assure that the necessary quality of systems and components is maintained, that facility operation will be within safety limits, and that the limiting conditions for operation will be met.
NUREG-0800, Revision 3, Standard Review Plan for the Review of Safety Analysis Reports for Nuclear Power Plants: LWR [light-water reactor] Edition (SRP):
Chapter 16, Section 16.0, Technical Specifications, March 2010 (ML100351425). As described therein, as part of the regulatory standardization effort, the NRC staff has prepared STSs for each of the LWR nuclear designs. Accordingly, the NRC staffs review includes consideration of whether the proposed changes are consistent with the applicable STSs, as modified by NRC-approved travelers. The applicable STSs to the facilities are:
o NRC NUREG-1431, Standard Technical Specifications, Westinghouse Plants, Volume 1, Specifications, and Volume 2, Bases, Revision 5, September 2021 (ML21259A155 and ML21259A159, respectively).
o NRC NUREG-1433, Standard Technical Specifications, General Electric, BWR/4 Plants Volume 1, Specifications, and Volume 2, Bases, Revision 5, September 2021 (ML21272A357 and ML21272A358, respectively).
o NRC NUREG-1434, Standard Technical Specifications, General Electric, BWR/6 Plants Volume 1, Specifications, and Volume 2, Bases, Revision 5, September 2021 (ML21271A582 and ML21271A596, respectively).
3.0 TECHNICAL EVALUATION
3.1 Proposed TS Changes to Adopt TSTF-599 The NRC staff compared the licensees proposed TS changes in section 1.2 of this SE against the changes approved in TSTF-599. The NRC staff finds that the licensees proposed changes to the CEG facilities TSs in section 1.2 of this SE are consistent with those found acceptable in TSTF-599.
In the NRC SE of TSTF-599, the NRC staff considered common cause failure is a very low likelihood event, and therefore concluded that the performance of STS SR 3.8.1.20 does not enhance safety over increased risk of equipment inoperability. Additionally, in recent decades, industry operating experience during loss of offsite power events has demonstrated consistent performance of the DG simultaneous start function. Therefore, as discussed in section 4.0 of the NRC staffs SE of TSTF-599, the NRC staff found proposed deletion of STS SR 3.8.1.20, along with the associated changes to STS TS 3.8.2 were acceptable because the TS would continue to meet 10 CFR 50.36(c)(3) since the remaining STS 3.8.1 DG SRs provide assurance that the necessary quality of systems and components are maintained. For these same reasons, the NRC staff concludes that the corresponding proposed changes to the CEG facilities TS in section 1.2 of this SE continue to meet the requirements of 10 CFR 50.36(c)(3).
3.2 TS Change Consistency The NRC staff reviewed the proposed TS changes for technical clarity and consistency with the existing requirements for customary terminology and formatting. The NRC staff finds that the proposed changes are consistent with chapter 16.0 of the SRP and are therefore acceptable.
4.0 CONCLUSION
The Commission has concluded, based on the considerations discussed above, that: (1) there is reasonable assurance that the health and safety of the public will not be endangered by operation in the proposed manner, (2) there is reasonable assurance that such activities will be conducted in compliance with the Commissions regulations, and (3) the issuance of the amendment will not be inimical to the common defense and security or to the health and safety of the public.
8 NOTICES AND ENVIRONMENTAL FINDINGS RELATED TO AMENDMENT NO. 244 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-72 AMENDMENT NO. 244 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-77 AMENDMENT NO. 242 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-37 AMENDMENT NO. 242 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-66 AMENDMENT NO. 258 TO FACILITY OPERATING LICENSE NO. NPF-62 AMENDMENT NO. 288 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-19 AMENDMENT NO. 281 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-25 AMENDMENT NO. 266 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-11 AMENDMENT NO. 251 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-18 AMENDMENT NO. 269 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-39 AMENDMENT NO. 231 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-85 AMENDMENT NO. 200 TO RENEWED FACILITY OPERATING LICENSE NO. NPF-69 AMENDMENT NO. 347 TO SUBSEQUENT RENEWED FACILITY OPERATING LICENSE NO. DPR-44 AMENDMENT NO. 350 TO SUBSEQUENT RENEWED FACILITY OPERATING LICENSE NO. DPR-56 AMENDMENT NO. 303 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-29 AND AMENDMENT NO. 299 TO RENEWED FACILITY OPERATING LICENSE NO. DPR-30 CONSTELLATION ENERGY GENERATION, LLC BRAIDWOOD STATION, UNITS 1 AND 2 BYRON STATION, UNITS 1 AND 2 CLINTON POWER STATION, UNIT 1 DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3 LASALLE COUNTY STATION, UNITS 1 AND 2 LIMERICK GENERATING STATION, UNITS 1 AND 2 NINE MILE POINT NUCLEAR STATION, UNIT 2 PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3 QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 DOCKET NOS. STN 50-456, STN 50-457, STN 50-454, STN 50-455, 50-461, 50-237, 50-249, 50-373, 50-374, 50-352, 50-353, 50-410, 50-277, 50-278, 50-254, AND 50-265 Application (i.e., initial and supplements)
Safety Evaluation Date August 5, 2025, ML25218A063 January 6, 2026
1.0 INTRODUCTION
Constellation Energy Generation, LLC (CEG, the licensee) requested changes to the technical specifications (TSs) for Braidwood Station, Units 1 and 2 (Braidwood); Byron Station, Units 1 and 2 (Byron); Clinton Power Station, Unit 1 (Clinton); Dresden Nuclear Power Station, Units 2 and 3 (Dresden); Lasalle County Station, Units 1 and 2 (Lasalle); Limerick Generating Station, Units 1 and 2 (Limerick); Nine Mile Point Nuclear Station, Unit 2 (NMP-2); Peach Bottom Atomic Power Station, Units 2 and 3 (Peach Bottom); and Quad Cities Nuclear Power Station, Units 1 and 2 (Quad Cities) (collectively, the CEG facilities), by license amendment request (LAR, application). The proposed changes would revise the TSs for each facility based on Technical Specifications Task Force (TSTF) Traveler TSTF-599, Revision 1, Eliminate Periodic Surveillance Test of Simultaneous Start of Redundant Diesel Generators (TSTF-599)
(Agencywide Documents Access and Management System (ADAMS) Accession No. ML25093A204), and the associated U.S. Nuclear Regulatory Commission (NRC, the Commission) staff final safety evaluation (SE) of Traveler TSTF-599 (ML25119A288).
2.0 STATE CONSULTATION
In accordance with the Commissions regulations, the Illinois and New York State officials, and Commonwealth of Pennsylvania officials were notified of the proposed issuance of the amendments on November 25, 2025. The relevant officials had no comments.
3.0 ENVIRONMENTAL CONSIDERATION
The amendment changes a requirement with respect to installation or use of a facility component located within the restricted area as defined in Title 10 of the Code of Federal Regulations (10 CFR), part 20. The NRC staff has determined that the amendment involves no significant increase in the amounts, and no significant change in the types of any effluents that may be released offsite, and that there is no significant increase in individual or cumulative occupational radiation exposure. The Commission has previously issued a proposed finding that the amendment involves no significant hazards consideration, which was published in the Federal Register on September 2, 2025 (90 FR 42453), and there has been no public comment on such finding. Accordingly, the amendment meets the eligibility criteria for categorical exclusion set forth in 10 CFR 51.22(c)(9) and 10 CFR 51.22(c)(10). Pursuant to 10 CFR 51.22(b) no environmental impact statement or environmental assessment need be prepared in connection with the issuance of the amendment.
SUBJECT:
BRAIDWOOD STATION, UNITS 1 AND 2; BYRON STATION, UNIT NOS. 1 AND 2; CLINTON POWER STATION, UNIT NO. 1; DRESDEN NUCLEAR POWER STATION, UNITS 2 AND 3; LASALLE COUNTY STATION, UNITS 1 AND 2; LIMERICK GENERATING STATION, UNITS 1 AND 2; NINE MILE POINT NUCLEAR STATION, UNIT 2; PEACH BOTTOM ATOMIC POWER STATION, UNITS 2 AND 3; AND QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 - ISSUANCE OF AMENDMENTS TO ADOPT TECHNICAL SPECIFICATIONS TASK FORCE TRAVELER TSTF-599 (EPID L-2025-LLA-0125) DATED JANUARY 6, 2026 DISTRIBUTION:
PUBLIC RidsNrrDorlLpl1 Resource RidsNrrDorlLpl3 Resource RidsRgn1MailCenter Resource RidsRgn3MailCenter Resource RidsNrrLASLent Resource RidsAcrs_MailCTR Resource RidsNrrPMConstellation Resource RidsNrrPMBraidwood Resource RidsNrrPMByron Resource RidsNrrPMClinton Resource RidsNrrPMDresden Resource RidsNrrPMLaSalle Resource RidsNrrPMLimerick Resource RidsNrrPMNineMilePoint Resource RidsNrrPMPeachBottom Resource RidsNrrPMQuadCities Resource RidsNrrDssStsb Resource KWest, NRR Accession No.: ML25351A217
- via eConcurrence NRR-058 OFFICE NRR/DORL/LPL3/PM NRR/DORL/LPL3/LA NRR/DSS/STSB/BC*
NAME SWall SLent SMehta DATE 12/17/2025 12/19/2025 12/2/2025 OFFICE NRR/DORL/LPL3/BC (A)
NRR/DORL/LPL3/PM NAME IBerrios SWall DATE 1/6/2026 1/6/2026 OFFICIAL RECORD COPY