Summary of January 23, 2024, Meeting with Nuclear Energy Institute Concerning NEI 20-07, Draft Revision E
ML24054A838
Person / Time
Site: 99902028
Issue date: 03/04/2024
From: Marshall M
NRC/NRR/DORL/LPL1
To: Gerond George
Nuclear Energy Institute
Shared Package
ML24054A839 List:
References
EPID L-2023-NFN-0012
Download: ML24054A838 (1)


Text

March 4, 2024 TO:

Gerond A. George, Chief Licensing Project Branch Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation FROM:

Michael L. Marshall, Jr., Senior Project Manager /RA/

Plant Licensing Branch 1 Division of Operating Reactor Licensing Office of Nuclear Reactor Regulation

SUBJECT:

SUMMARY

OF JANUARY 23, 2024, MEETING WITH NUCLEAR ENERGY INSTITUTE CONCERNING NEI 20-07, DRAFT REVISION E (EPID L-2023-NFN-0012)

On January 23, 2024, a closed public meeting was held between the U.S. Nuclear Regulatory Commission (NRC) and representatives of Nuclear Energy Institute (NEI) at NRC headquarters in Rockville, Maryland. The main purpose of the meeting was for NEI to provide an overview of Draft Revision E of NEI 20-07, Guidance for Addressing Common Cause Failure in High Safety-Significant Safety-Related Digital I&C Systems, to the NRC staff. NEI provided the draft document to the NRC in a letter dated July 24, 2023 (Agencywide Documents Access and Management System (ADAMS) Accession No. ML23205A188). The other purpose of the meeting was to provide NEI with the status of the NRC staffs review of NEIs withholding request for Draft Revision E of NEI 20-07. The meeting notice and agenda, dated December 19, 2023, are available in the ADAMS at Accession No. ML23353A055. A list of attendees is provided in the enclosure.

The NEI representatives provided an overview of the methodology in and the content of each section of the draft document. The NEI representatives stated the methodology described in the draft document is technology agnostic and is intended to be used for both operating reactors and advanced reactors. The NEI representatives stated that the Electric Power Research Institutes processes included in the methodology described in the draft document have not been endorsed or approved by the NRC.

In response to a question from NEI about biggest challenge with obtaining NRC endorsement or approval of NEI 20-07 by the end of the calendar year, the NRC staff informed the NEI representatives that the draft document would need to be finalized and submitted to the NRC for review. The NEI representatives did not provide a target date for finalizing and submitting the document for review.

The NRC staff informed the NEI representatives of the criteria from the regulations used to perform review of requests to withhold information from the public. The NRC staff informed the NEI representatives that the review of the NEI withholding request was nearly complete, and a decision would be issued in early February 2024.

No regulatory decisions were made during the meeting. Members of the public were not in attendance. Public Meeting Feedback forms were not received.

Please direct any inquiries to me at 301-415-2871 or michael.marshall@nrc.gov.

Project No: 99902028

Enclosure:

List of Attendees

Enclosure LIST OF ATTENDEES JANUARY 23, 2024, MEETING WITH NUCLEAR ENERGY INSTITUTE CONCERNING NEI 20-07, DRAFT REVISION E Name Organization Steven Alferink U.S. Nuclear Regulatory Commission (NRC)

Christina Antonescu NRC Sushil Birla NRC Norbert Carte NRC Leslie Fields NRC Ian Jung NRC Michael Marshall NRC Jason Page NRC David Rahn NRC Fanta Sacko NRC Daniel Silverstein NRC Michael Swim NRC Dinesh Taneja NRC Sunil Weerakkody NRC Jack Zhao NRC Alan Campbell Nuclear Energy Institute Mark Samselski Constellation Energy Generation, LLC Warren Odess-Gillett Westinghouse Electric Corporation Neil Archambo

Package, ML24054A839 Meeting Notice, ML23353A055 Meeting Summary, ML24054A838 OFFICE NRR/DORL/LPL1/PM NRR/DORL/LLPB/LA NRR/DORL/LLPB/BC NRR/DORL/LPL1/PM NAME MMarshall DHarrison GGeorge MMarshall DATE 02/23/2024 2/27/2024 02/29/2024 03/04/2024