Letter Sequence Other |
---|
|
Initiation
- Request, Request, Request, Request, Request, Request, Request, Request, Request, Request, Request
- Acceptance
Results
Other: ML18247A211, ML19008A394, ML19008A395, ML19008A396, ML19008A397, ML19008A405, ML20195A857, ML21050A309, ML21281A171, ML23055A028, ML23055A029, ML23067A100
|
MONTHYEARML18184A4442018-06-27027 June 2018 Lacrossesolutions, LLC - Application for Order Approving License Transfer and Conforming Administrative License Amendments Project stage: Request ML18247A2112018-10-0303 October 2018 LACBWR - Initial FRN Regarding the Lacrosse Solutions License Transfer Application and Associated Conforming Administrative License Amendments to Transfer License to the Dairyland Power Cooperative (CAC No. 000083; EPID L-2018-LNS-0002) Project stage: Other ML18283A0442018-11-0101 November 2018 Boiling Water Reactor - Acceptance Review of the Lacrosse Solutions License Transfer Application and Associated Conforming Administrative License Amendment to Transfer the Operating License to the Dairyland Power Cooperative ... Project stage: Acceptance Review ML19092A2412019-03-25025 March 2019 Lacrosse Boiling Water Reactor Report on Status of Decommissioning Funding for Shutdown Reactor Project stage: Request ML19008A3972019-09-24024 September 2019 LACBWR License Transfer SE - Enclosure 3 Project stage: Other ML19008A3932019-09-24024 September 2019 License Transfer to Dairyland Project stage: Request ML19008A3962019-09-24024 September 2019 LACBWR License Transfer Order - Enclosure 1 Project stage: Other ML19008A3952019-09-24024 September 2019 Order Approving Transfer of the License for the La Crosse Boiling Water Reactor to Dairyland Power Cooperative and Conforming Administrative License Amendment Project stage: Other ML19008A3942019-09-24024 September 2019 LACBWR License Transfer Amendment No. 76 - Enclosure 2 Project stage: Other ML19008A4052019-09-26026 September 2019 LACBWR License Transfer Issuance FRN Project stage: Other ML20188A2282020-06-24024 June 2020 Lacrossesolutions, LLC - Request for Extension of Order Approving Trans(Er of the License for the La Crosse Boiling Water Reactor to Dairyland Power Cooperative Project stage: Request ML20195A8572020-09-0101 September 2020 LACBWR License Transfer Order Extension Letter Project stage: Other ML20195A8462020-09-0101 September 2020 License Transfer Order Extension Approval Project stage: Request ML21050A3092021-03-0909 March 2021 LACBWR License Transfer Order Second Extension Letter Project stage: Other ML21218A0082021-08-10010 August 2021 NSIR Review of the Three Mile Island Physical Security Plan Revision 24 for the Verification of ASM 20-103 Incorporation Project stage: Approval ML21281A1712021-12-0707 December 2021 General Atomics Triga Reactor Facility - Approval of License Termination Based on the Final Status Survey Report and Supporting Information Project stage: Other ML22040A2752022-02-11011 February 2022 NSIR Staff Review of the Duane Arnold Energy Center Security Plan, Training and Qualification Plan, and Safeguards Contingency Plan, for the Verification of ASM EA-02-104 Incorporation Project stage: Approval ML22277A3502022-05-31031 May 2022, 5 July 2022, 9 August 2022, 16 August 2022, 22 August 2022, 7 September 2022 Class 1 Fssr Review - Clarification Activities Project stage: Request ML22223A0882022-07-28028 July 2022 Response to June 5, 2022 Request for Additional Information for Class 1 Survey Areas Project stage: Request ML22235A7922022-09-12012 September 2022 License Transfer Order Fourth Extension Approval Project stage: Request ML22278A0292022-10-12012 October 2022 Enclosure Request for Confirmatory Information Enclosure Related to the Review of the Class 1 Survey Units Project stage: Approval ML22278A0272022-10-12012 October 2022 Request for Confirmatory Information Related to the Review of the Class 1 Survey Units Project stage: Request ML22278A0282022-10-12012 October 2022 Request for Confirmatory Information Letter Re to the Review of the Class 1 Survey Units Project stage: Approval ML22321A0142022-11-0303 November 2022 Class 1 Fssr Review - Clarification Activities Part 2 Project stage: Request ML22321A3092022-12-0808 December 2022 License Transfer Order Fifth Extension Approval Project stage: Request ML23055A0292023-02-24024 February 2023 Staff Evaluation in Support of the La Crosse Class 1 Survey Unit Partial Site Release Project stage: Other ML23055A0282023-02-24024 February 2023 Completion of License Termination Activities and Release of Remaining Class 1 Survey Units from Possession Only License No. DPR-45 Project stage: Other ML23067A1002023-03-0808 March 2023 Amendment No. 9 to Indemnity Agreement No. B-62 for La Crosse Boiling Water Reactor Project stage: Other 2021-03-09
[Table View] |
Text
UNITED STATES NUCLEAR REGULATORY COMMISSION WASHINGTON, D.C. 20555-0001
Docket No. 50-409 72-046
AMENDMENT TO INDEMNITY AGREEMENT NO. B-62 AMENDMENT NO. 9
Effective March 15, 2023, Indemnity Agreement No. B-62, between LaCrosseSolutions, LLC, and the United States Nuclear Regulatory Commission, dated August 28, 1973, as amended, is hereby further amended as follows:
The name LaCrosseSolutions, LLC is deleted wherever it appears in the agreement and substituted in lieu thereof by the name: Dairyland Power Cooperative.
Item 1 of the Attachment to the indemnity agreement is modified by deleting the name LaCrosseSolutions, LLC wherever it appears in the agreement and substituted in lieu thereof by the name:
Item 1 - Licensee Dairyland Power Cooperative
Address 3200 East Avenue South La Crosse, Wisconsin 54602-0817
In light of the above, Indemnity Agreement No. B-62 is between Dairyland Power Cooperative, and the United States Nuclear Regulatory Commission.
FOR THE UNITED STATES NUCLEAR REGULATORY COMMISSION
Digitally signed by Frederick Frederick Miller Miller
____________________________________Date: 2023.03.08 14:39:58 -05'00' Fred R. Miller, Chief Financial Assessment Branch Division of Rulemaking, Environmental, and Financial Support Office of Nuclear Material Safety and Safeguards