MONTHYEARIR 05000272/20244032024-09-25025 September 2024 and Salem Nuclear Generating Station, Units 1 and 2, Cybersecurity Inspection Report 05000354/2024403, 05000272/2024403, and 05000311/2024403 (Cover Letter Only) IR 05000272/20244022024-09-23023 September 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024402, 05000272/2024402, and 05000311/2024402 (Cover Letter Only) ML24267A1082024-09-23023 September 2024 Submittal of the Reactor Vessel Material Surveillance Program Capsule Technical Report IR 05000272/20240052024-08-29029 August 2024 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Report 05000272/2024005 and 05000311/2024005) IR 05000272/20240022024-07-30030 July 2024 Integrated Inspection Report 05000272/2024002 and 05000311/2024002 LR-N24-0012, Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding2024-07-24024 July 2024 Application to Revise Technical Specifications and 10 CFR 50.12 Exemption Request to Implement Optimized ZIRLO Fuel Rod Cladding ML24145A1772024-07-15015 July 2024 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 236, 349, and 331 Modify Exclusion Area Boundary IR 05000272/20245012024-06-12012 June 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Emergency Preparedness Biennial Exercise Inspection Report 05000354/2024501, 05000272/2024501 and 05000311/2024501 ML24099A1572024-05-29029 May 2024 Issuance of Amendment Nos. 348 and 330 Permanent Extension of Type a and Type C Containment Leak Rate Test Frequencies ML24150A0032024-05-28028 May 2024 Request for Exemptions from 10 CFR 50.82(a)(8)(i)(A) and 10 CFR 50.75(h)(1)(iv) and Proposed Amendment to the Decommissioning Trust Agreement LR-N24-0041, Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response2024-05-22022 May 2024 Stations, Revisions to Emergency Plan Document Nc EP-EP-ZZ-01102, Rev. 28, Emergency Coordinator Response IR 05000272/20240102024-05-16016 May 2024 Fire Protection Team Inspection Report 05000272/2024010 and 05000311/2024010 LR-N24-0038, Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger2024-05-0909 May 2024 Pressure Boundary Leakage Through a Reactor Coolant Pump Thermal Barrier Heat Exchanger IR 05000272/20240012024-05-0707 May 2024 Integrated Inspection Report 05000272/2024001 and 05000311/2024001 LR-N24-0039, Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage2024-05-0606 May 2024 Steam Generator Tube Inspection Report - Twenty-ninth Refueling Outage LR-N24-0034, 2023 Annual Radioactive Effluent Release Report (ARERR)2024-04-30030 April 2024 2023 Annual Radioactive Effluent Release Report (ARERR) LR-N24-0035, 2023 Annual Radiological Environmental Operating Report (AREOR)2024-04-30030 April 2024 2023 Annual Radiological Environmental Operating Report (AREOR) LR-N24-0024, Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-26026 April 2024 Response to Request for Additional Information Associated with License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary LR-N24-0011, Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary2024-04-0505 April 2024 Supplemental Information to License Amendment Request (LAR) to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20240112024-04-0101 April 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Plant Modification and Annual Problem Identification and Resolution Inspection Report 05000354/2024011, 05000272/2024011, and 05000311/2024011 LR-N24-0028, and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal2024-03-28028 March 2024 and Salem Generating Station - Notice of Intent to Pursue Subsequent License Renewal LR-N24-0021, and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums2024-03-20020 March 2024 and Salem Generating Station, Units 1 and 2 - Guarantees of Payment of Deferred Premiums ML24071A2132024-03-12012 March 2024 Senior Reactor and Reactor Operator Initial License Examinations LR-N24-0020, Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report2024-03-0707 March 2024 Generation Station and Salem Generating Station, Units 1 & 2 - Annual Property Insurance Status Report LR-N24-0022, Spent Fuel Cask Registration2024-02-29029 February 2024 Spent Fuel Cask Registration IR 05000272/20230062024-02-28028 February 2024 Annual Assessment Letter for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023006 and 05000311/2023006 IR 05000272/20244012024-02-26026 February 2024 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2024401, 05000272/2024401 and 05000311/2024401 (Cover Letter Only) LR-N24-0009, In-Service Inspection Activities2024-02-0505 February 2024 In-Service Inspection Activities IR 05000272/20230042024-02-0505 February 2024 Integrated Inspection Report 05000272/2023004 and 05000311/2023004 ML24009A1022024-01-26026 January 2024 – Exemption from Select Requirements of 10 CF Part 73 (EPID L-2023-LLE-0045 (Security Notifications, Reports, and Recordkeeping and Suspicious Activity Reporting)) IR 05000272/20234012024-01-22022 January 2024 Material Control and Accounting Program Inspection Report 05000272/2023401 and 05000311/2023401 ML24004A1542024-01-0808 January 2024 Notification of Conduct of a Fire Protection Team Inspection LR-N23-0079, Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days2023-12-0707 December 2023 Special Report 23-02-00 Pursuant to the Requirements of Salem Unit 1 Technical Specification 3.3.3.7, Action 10, for the Unit 1 Main Steam Line Rad Monitor Inoperable for Greater than Seven Days LR-N23-0077, Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion2023-11-29029 November 2023 Loss of Coolant Accident Peak Cladding Temperature Margin Tracking - Annual Report 2023 & 30 Day Report for Salem Unit 1 Upflow Conversion ML23270C0072023-11-29029 November 2023 Notice of Proposed Amendment to Decommissioning Trust Agreement ML23324A3072023-11-17017 November 2023 Request for Exemption from Enhanced Weapons, Firearms Background Checks, and Security Event Notifications Implementation ML24250A0582023-11-14014 November 2023 PSEG to Marine Mammal Stranding Center, Salem Sea Turtle Stranding Response Services IR 05000272/20230032023-11-13013 November 2023 Integrated Inspection Report 05000272/2023003 and 05000311/2023003 LR-N23-0072, Core Operating Limits Report Cycle 302023-11-0101 November 2023 Core Operating Limits Report Cycle 30 IR 05000272/20230102023-10-12012 October 2023 Biennial Problem Identification and Resolution Inspection Report O5000272/2023010 and 05000311/2023010 IR 05000272/20234022023-10-12012 October 2023 and Salem Nuclear Generating Station, Units 1 and 2 - Security Baseline Inspection Report 05000354/2023402, 05000272/2023402 and 05000311/2023402 (Cover Letter Only) LR-N23-0045, and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement2023-09-0808 September 2023 and Peach Bottom Atomic Power Station, Units 2 and 3 - Notice of Proposed Amendment to Decommissioning Trust Agreement ML23249A2612023-09-0606 September 2023 License Amendment Request to Modify the Salem and Hope Creek Exclusion Area Boundary IR 05000272/20230052023-08-31031 August 2023 Updated Inspection Plan for Salem Nuclear Generating Station, Units 1 and 2 (Reports 05000272/2023005 and 05000311/2023005) ML23233A0762023-08-21021 August 2023 Requalification Program Inspection ML23192A8212023-08-14014 August 2023 and Salem Nuclear Generating Station, Unit Nos. 1 and 2 - Issuance of Amendment Nos. 234, 347, and 329 Revise Technical Specifications to Delete Meteorological Tower Location IR 05000272/20230022023-08-0909 August 2023 Integrated Inspection Report 05000272/2023002 and 05000311/2023002 LR-N23-0055, Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days2023-08-0303 August 2023 Special Report 272/23-01-00, Pursuant to the Requirements of Technical Specification 3.3.3.1, Action 23, for the Vent Noble Gas Rad Monitor Inoperable for Greater than Seven Days IR 05000354/20230022023-08-0303 August 2023 Integrated Inspection Report 05000354/2023002 and Independent Spent Fuel Storage Installation Inspection Report 07200048/2023001 LR-N23-0054, In-Service Inspection Activities2023-07-26026 July 2023 In-Service Inspection Activities 2024-09-25
[Table view] |
Text
June 23, 2022 Mr. Eric Carr President and Chief Nuclear Officer PSEG Nuclear, LLC P.O. Box 236 Hancocks Bridge, NJ 08038
SUBJECT:
SALEM NUCLEAR GENERATING STATION, UNITS 1 AND 2 - SENIOR REACTOR AND REACTOR OPERATOR INITIAL LICENSE EXAMINATIONS
Dear Mr. Carr:
In a telephone conversation on June 8, 2022, between Mr. C. Lally, Chief Examiner, and Mr. R. Chan, Facility Exam Author, arrangements were made for the administration of licensing examinations at Salem Nuclear Generating Station, Units 1 and 2, during the week of February 13, 2023. In addition, the U.S. Nuclear Regulatory Commission (NRC) will make an examination validation visit to your facility the week of January 16, 2023.
As agreed upon during the telephone conversation, your staff will prepare the examinations based on the guidelines in Revision 12 to NUREG-1021, Operator Licensing Examination Standards for Power Reactors. The NRCs regional office will discuss with your staff any changes that might be necessary before the examinations are administered.
To meet the above schedule, it will be necessary for your staff to furnish the operating test outlines by September 12, 2022. The NRC staff will provide the written examination outline by August 2, 2022. The written examinations, operating tests, and supporting reference materials identified in NUREG-1021, Examination Standard (ES)-2.1, Preparing for Operator Licensing Initial Examinations, will be due by November 28, 2022. Pursuant to Title 10, Section 55.40(b)(3), of the Code of Federal Regulations (10 CFR 55.40(b)(3)), an authorized representative of the facility licensee shall approve the examinations and tests before they are submitted to the Commission for review and approval. All materials shall be complete and ready-to-use.
We request that any personal, proprietary, sensitive unclassified, or safeguards information in your response be contained in a separate enclosure and appropriately marked. Delays in receiving the required examination and reference materials, or the submittal of inadequate or incomplete materials, may cause the examinations to be rescheduled.
To conduct the requested written examinations and operating tests, your staff will need to provide adequate space and accommodations and to make the simulation facility available on the dates noted above. In accordance with ES-3.5, Administering Operating Tests," your staff should retain the original simulator performance data (e.g., system pressures, temperatures,
E. Carr 2 and levels) generated during the dynamic operating tests until the NRC takes licensing action on all the applications and any adjudicatory actions on any hearing demands are complete.
ES-1.2, Guidelines for Taking NRC Examinations, contains a number of NRC guidelines for the written examinations and operating tests as they are being administered.
To permit timely NRC review and evaluation, your staff should submit preliminary reactor operator and senior reactor operator waiver or excusal requests (if any) (Office of Management and Budget (OMB) control number 3150-0090) at least 60 days before the first examination date (if possible). Contact Mr. C. Lally, Chief Examiner, to determine the method for submission of the waiver or excusal requests. Preliminary reactor operator and senior reactor operator license applications (OMB control number 3150-0090) and medical certifications (OMB control number 3150-0024) should be submitted at least 30 days before the first examination date. If the preliminary applications are not received at least 30 days before the examination date, a postponement may be necessary. Final signed applications certifying that all training has been completed and requesting any waivers or excusals, as applicable, should be submitted at least 14 days before the first examination date.
Although the guidelines for receiving waiver or excusal requests call for at least 30 days before the first examination date (preliminary) and 14 days before the first examination date (final), the requests should be submitted as early as possible in the process (see the 60-day guideline above). Resolutions resulting from verbal inquiries by the licensee to the NRC are not binding.
Submittals addressing waivers or excusals, or both, should be in writing (i.e., using NRC Form 398, Personal Qualifications StatementLicensee, or as directed by Mr. C. Lally when contacting him to determine the method for submission). The NRC will document its final decision on whether to grant a waiver or excusal on the final (not preliminary) NRC Form 398 submitted for the applicant. The NRC will not provide its decision until the final application is submitted to the agency.
Paperwork Reduction Act Statement This letter contains information collection requirements that are subject to the Paperwork Reduction Act of 1995 (44 U.S.C. 3501 et seq.). These information collections were approved by the Office of Management and Budget, approval number 3150-0018.
The burden to the public for these voluntary information collections is estimated to average 2,250 hours0.00289 days <br />0.0694 hours <br />4.133598e-4 weeks <br />9.5125e-5 months <br /> per examination or response, including the time for reviewing instructions, searching existing data sources, gathering and maintaining the data needed, and completing and reviewing the information collections. Send comments regarding this information collection to the FOIA, Library, and Information Collections Branch (T6-A10M), U.S. Nuclear Regulatory Commission, Washington, DC 20555 0001, or by e mail to Infocollects.Resource@nrc.gov, and to the OBM reviewer at: OBM Office of Information and Regulatory Affairs (3150-0018), Attn:
Desk Officer for the Nuclear Regulatory Commission, 725 17th Street, NW Washington, DC, 20503; e mail: oira_submission@omb.eop.gov.
Public Protection Notification The NRC may not conduct or sponsor, and a person is not required to respond to, a collection of information unless the document requesting or requiring the collection displays a currently valid OMB control number.
E. Carr 3 In accordance with 10 CFR 2.390, Public Inspections, Exemptions, Requests for Withholding, of the agencys Rules of Practice, a copy of this letter will be available electronically for public inspection through the Agencywide Documents Access and Management System (ADAMS).
ADAMS is accessible on the NRCs Web site at http://www.nrc.gov/reading-rm/adams.html.
After you have been notified by the NRC Chief Examiner or Branch Chief that operator licenses have been issued, please direct any inquiries concerning a formal presentation of certificates to this office. Our goal is to have the operator certificates available for your celebration. At least one-month advance notice of your celebration arrangements would be appreciated to plan our senior manager attendance and process the certificates.
Thank you for your cooperation in this matter. Mr. R. Chan has been advised of the policies and guidelines referenced in this letter. If you have any questions regarding the NRCs examination procedures and guidelines, please contact Mr. C. Lally at (610) 337-5124 or me at (610) 337-5306.
Sincerely, Digitally signed by Donald Donald E. E. Jackson Date: 2022.06.23 Jackson 14:47:51 -04'00' Donald E. Jackson, Chief Operations Branch Division of Operating Reactor Safety Docket Nos. 50-272 and 50-311 License Nos. DPR-70 and DPR-75 cc: Distribution via ListServ