MONTHYEARIR 05000254/20240102024-10-28028 October 2024 Age Related Degradation Inspection Report 05000254/2024010 and 05000265/2024010 and Notice of Violation IR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) IR 05000254/20240022024-08-12012 August 2024 Integrated Inspection Report 05000254/2024002 and 05000265/2024002 IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 IR 05000254/20230062024-02-28028 February 2024 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2023006 and 05000265/2023006) IR 05000254/20230042024-02-0505 February 2024 Integrated Inspection Report 05000254/2023004 and 05000265/2023004 IR 05000254/20234032023-12-22022 December 2023 Public- Quad Cities Nuclear Power Station Security Baseline Inspection Report 05000254/2023403 and 05000265/2023403 IR 05000254/20230102023-12-20020 December 2023 Comprehensive Engineering Team Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20230032023-11-0909 November 2023 Integrated Inspection Report 05000254/2023003 and 05000265/2023003 IR 05000254/20230112023-09-20020 September 2023 Safety-Conscious Work Environment Issue of Concern Team Inspection Report 05000254/2023011 and 05000265/2023011 IR 05000254/20230052023-08-25025 August 2023 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2023005; 05000265/2023005) IR 05000254/20230022023-08-0808 August 2023 Integrated Inspection Report 05000254/2023002 and 05000265/2023002 IR 05000254/20234012023-06-26026 June 2023 Cyber Security Inspection Report 05000254/2023401 and 05000265/2023401 IR 05000265/20230402023-06-22022 June 2023 Reissue Quad Cities Nuclear Power Station 95001 Supplemental Inspection Supplemental Report 05000265/2023040 and Follow Up Assessment Letter ML23167B1722023-06-16016 June 2023 95001 Supplemental Inspection Report 05000265/2023040 and Follow-Up Assessment Letter IR 05000254/20234022023-05-15015 May 2023 Security Baseline and ISFSI Inspection Reports 05000254/2023402, 05000265/2023402, 07200053/2023401 IR 05000254/20230012023-05-0808 May 2023 Integrated Report 05000254/2023001 and 05000265/2023001 ML23065A2832023-03-0707 March 2023 Request for Information for the NRC Quadrennial Comprehensive Engineering Team Inspection: Inspection Report 05000254/2023010 and 05000265/2023010 IR 05000254/20233012023-03-0707 March 2023 NRC Initial License Examination Report 05000254/2023301; 05000265/2023301 IR 05000254/20220062023-03-0101 March 2023 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2022006 and 05000265/2022006) IR 05000254/20220042023-02-10010 February 2023 Integrated Inspection Report 05000254/2022004 and 05000265/2022004 IR 05000254/20220112023-01-0606 January 2023 Triennial Fire Protection Inspection Report 05000254/2022011 and 05000265/2022011 IR 05000254/20220102022-12-13013 December 2022 Phase 4 Post-Approval License Renewal Inspection Report 05000254/2022010 and 05000265/2022010 ML22313A1502022-11-29029 November 2022 EA-22-062 QC ERV Final Action IR 05000254/20224012022-11-22022 November 2022 Security Baseline Inspection Report 05000254/2022401 and 05000265/2022401 IR 05000254/20220132022-11-17017 November 2022 Biennial Problem Identification and Resolution Inspection Report 05000254/2022013 and 05000265/2022013 IR 05000254/20220032022-11-0303 November 2022 Integrated Inspection Report 05000254/2022003 and 05000265/2022003 IR 05000254/20220052022-08-22022 August 2022 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2022005; 05000265/2022005) IR 05000254/20225012022-08-15015 August 2022 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2022501 and 05000265/2022501 IR 05000254/20220022022-08-0909 August 2022 Integrated Inspection Report 05000254/2022002 and 05000265/2022002 IR 05000254/20220902022-08-0808 August 2022 NRC Inspection Report 05000254/2022090 and 05000265/2022090; Preliminary White Finding IR 05000254/20220122022-07-11011 July 2022 Triennial Inspection of Evaluation of Changes, Tests and Experiments Baseline Inspection Report 05000254/2022012 and 05000265/2022012 IR 05000254/20220012022-05-11011 May 2022 Integrated Inspection Report 05000254/2022001 and 05000265/2022001 IR 05000254/20210062022-03-0202 March 2022 Annual Assessment Letter for Quad Cities Nuclear Power Station, Units 1 and 2 (Report 05000254/2021006 and 05000265/2021006) IR 05000254/20210042022-02-0202 February 2022 Integrated Inspection Report 05000254/2021004 and 05000265/2021004 ML22033A1672022-02-0202 February 2022 Notification of NRC Baseline Inspection and Request for Information Inspection Report 05000265/2022001 IR 05000254/20214022021-12-0101 December 2021 Security Baseline Inspection Report 05000254/2021402 and 05000265/2021402 IR 05000254/20210102021-11-24024 November 2021 Design Basis Assurance Inspection (Programs) Inspection Report 05000254/2021010 and 05000265/2021010 IR 05000254/20210032021-10-28028 October 2021 Integrated Inspection Report 05000254/2021003 and 05000265/2021003 IR 05000254/20214012021-09-0909 September 2021 Security Baseline Inspection Report 05000254/2021401 and 05000265/2021401 IR 05000254/20210052021-09-0101 September 2021 Updated Inspection Plan for Quad Cities Nuclear Power Station (Report 05000254/2021005 and 05000265/2021005) ML21238A3142021-08-26026 August 2021 Notification of an NRC Triennial Heat Sink Performance Inspection and Request for Information; Inspection Report 05000254/2021004; 05000265/2021004 IR 05000254/20213012021-08-23023 August 2021 NRC Initial License Examination Report 05000254/2021301; 05000265/2021301 IR 05000254/20210022021-08-0909 August 2021 Integrated Inspection Report 05000254/2021002 and 05000265/2021002 IR 05000254/20214032021-06-28028 June 2021 Quad Nuclear Power Station - Material Control and Accounting Program Inspection Report 05000254/2021403 and 05000265/2021403 IR 05000254/20210012021-04-26026 April 2021 Integrated Inspection Report 05000254/2021001 and 05000265/2021001 IR 05000254/20200062021-03-0404 March 2021 Annual Assessment Letter for Quad Cities Nuclear Power Station Units 1 and 2 (Report 05000254/2020006 and 05000265/2020006) 2024-09-12
[Table view] Category:Letter
MONTHYEAR05000265/LER-2024-002-01, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-10-30030 October 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure SVP-24-065, Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor2024-10-29029 October 2024 Offsite Dose Calculation Manual (ODCM) Section 12.2.2 Radioactive Gaseous Effluent Monitoring Instrumentation Report Main Chimney High Range Noble Gas Monitor IR 05000254/20240102024-10-28028 October 2024 Age Related Degradation Inspection Report 05000254/2024010 and 05000265/2024010 and Notice of Violation RS-24-080, Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in .2024-10-16016 October 2024 Request to Replace Formerly Submitted Documents Available in the Agency Documents Access and Management System (ADAMS) with Documents Redacted in . RS-24-093, Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-10-10010 October 2024 Response to Request for Additional Information - Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-059, Correction to Registration of Use of Casks to Store Spent Fuel2024-10-0404 October 2024 Correction to Registration of Use of Casks to Store Spent Fuel ML24275A2442024-10-0303 October 2024 Reassignment of the U.S. Nuclear Regulatory Commission Branch Chief, Division of Operating Reactor Licensing ML24247A1642024-09-30030 September 2024 Alternative Request RP-01 IR 05000254/20244022024-09-12012 September 2024 Material Control and Accounting Program Inspection Report 05000254/2024402 and 05000265/2024402 (Public) SVP-24-054, Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds2024-09-11011 September 2024 Deviation from BWR Vessel and Internals Project (BWRVIP) Guidelines - Inspection of Top Guide Rim Welds ML24249A1362024-09-0404 September 2024 EN 57304 - Westinghouse Electric Company, LLC, Final Report - No Embedded Files. Notification of the Potential Existence of Defects Pursuant to 10 CFR Part 21 IR 05000254/20240052024-08-28028 August 2024 Updated Inspection Plan and Assessment Follow-Up Letter for Quad Cities Nuclear Power Station (Report 05000254/2024005; 05000265/2024005) RS-24-078, Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval2024-08-20020 August 2024 Alternative Request RV-08, Revision 1, Associated with Safety Relief Valve Testing Interval ML24183A1082024-08-0808 August 2024 – Issuance of Amendment Nos. 302 and 298 Adoption of Tstf-505, Provide Risk Informed Extended Completion Times – RITSTF Initiative 4b SVP-24-049, Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities2024-08-0707 August 2024 Owners Activity Report Submittal Sixth 10-Year Interval 2024 Refueling Outage Activities IR 05000254/20243012024-08-0101 August 2024 NRC Initial License Examination Report 05000254/2024301; 05000265/2024301 SVP-24-048, Registration of Use of Casks to Store Spent Fuel2024-07-31031 July 2024 Registration of Use of Casks to Store Spent Fuel 05000265/LER-2024-002, Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure2024-07-22022 July 2024 Turbine Trip and Automatic Scram Due to Digital EHC Power Supply Intermittent Failure RS-24-070, Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions2024-07-12012 July 2024 Independent Spent Fuel Storage Installation, Nine Mile Point, Units 1 and 2, Quad Cities, Units 1 and 2, R. E. Ginna - Nuclear Radiological Emergency Plan Document Revisions SVP-24-043, Registration of Use of Casks to Store Spent Fuel2024-07-0505 July 2024 Registration of Use of Casks to Store Spent Fuel SVP-24-041, Regulatory Commitment Change Summary Report2024-07-0505 July 2024 Regulatory Commitment Change Summary Report ML24162A0982024-07-0303 July 2024 – Issuance of Amendment Nos. 301 and 297 Adoption of 10 CFR 50.69 Risk Informed Categorization and Treatment of Structures, Systems, and Components for Nuclear Power Reactors SVP-24-040, Registration of Use of Casks to Store Spent Fuel2024-06-25025 June 2024 Registration of Use of Casks to Store Spent Fuel RS-24-061, Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations2024-06-14014 June 2024 Constellation Energy Generation, LLC, Response to NRC Regulatory Issue Summary 2024-01, Preparation and Scheduling of Operator Licensing Examinations SVP-24-039, Ile Post Exam Package Letter2024-06-12012 June 2024 Ile Post Exam Package Letter RS-24-053, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed2024-06-0606 June 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed ML24110A0492024-05-28028 May 2024 Audit Report Related to the TSTF-505 and 10 CFR 50.59 Amendments ML24079A0762024-05-23023 May 2024 Issuance of Amendments to Adopt TSTF 264 ML24142A3352024-05-21021 May 2024 Quad Cities—Information Request to Support the NRC Annual Baseline Emergency Action Level and Emergency Plan Changes ML24141A2102024-05-20020 May 2024 Operator Licensing Examination Approval - Quad Cities Nuclear Power Station, May 2024 RS-24-055, 2023 Corporate Regulatory Commitment Change Summary Report2024-05-17017 May 2024 2023 Corporate Regulatory Commitment Change Summary Report IR 05000254/20240012024-05-14014 May 2024 Integrated Inspection Report Nos. 05000254/2024001 and 05000265/2024001 05000265/LER-2024-001, Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing2024-05-10010 May 2024 Automatic Actuation of Reactor Protection System During Scram Discharge Volume Leak Rate Testing SVP-24-034, Annual Radiological Environmental Operating Report2024-05-10010 May 2024 Annual Radiological Environmental Operating Report RS-24-042, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-05-10010 May 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion RS-24-046, 10 CFR 50.46 Annual Report2024-05-0606 May 2024 10 CFR 50.46 Annual Report ML24109A0662024-05-0202 May 2024 – Relief Request I5R-26, Revision 0 RS-24-041, Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests2024-04-30030 April 2024 Alternative Request to Utilize Code Case OMN-32, Alternative Requirements for Range and Accuracy of Pressure, Flow, and Differential Pressure Instruments Used in Pump Tests SVP-24-028, Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report2024-04-26026 April 2024 Independent Spent Fuel Storage Installation Annual Radioactive Effluent Release Report SVP-24-029, Radioactive Effluent Release Report for 20232024-04-26026 April 2024 Radioactive Effluent Release Report for 2023 ML24114A1712024-04-23023 April 2024 State of Illinois (IEMA-OHS) Comment Quad Cities HI-STORM Exemption Environmental Assessment RS-24-032, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion2024-04-0505 April 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Extended Completion SVP-24-024, Corrected Radioactive Effluent Release Report for 20222024-04-0505 April 2024 Corrected Radioactive Effluent Release Report for 2022 IR 05000254/20245012024-04-0505 April 2024 Emergency Preparedness Biennial Exercise Inspection Report 05000254/2024501 and 05000265/2024501 RS-24-002, Constellation Energy Generation, LLC - Annual Property Insurance Status Report2024-04-0101 April 2024 Constellation Energy Generation, LLC - Annual Property Insurance Status Report SVP-24-023, Ile Outline Submittal Letter2024-03-29029 March 2024 Ile Outline Submittal Letter RS-24-019, Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF2024-03-19019 March 2024 Response to Request for Additional Information Related to License Amendment Request to Revise Technical Specifications to Adopt Risk Informed Completion Times TSTF-505, Revision 2, Provide Risk-Informed Completion Times TSTF ML23340A1552024-03-15015 March 2024 – Issuance of Amendment Nos. 299 and 295 Adoption of TSTF-564, Safety Limit MCPR RS-24-020, Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS2024-03-15015 March 2024 Request for Exemption from Certain Requirements of 10 CFR 72.212 and 10 CFR 72.214 for Quad Cities Nuclear Power Station - Holtec MPC-68MCBS SVP-24-018, Ile Proposed Exam Submittal Letter2024-03-13013 March 2024 Ile Proposed Exam Submittal Letter 2024-09-04
[Table view] |
Text
March 2, 2022
SUBJECT:
ANNUAL ASSESSMENT LETTER FOR QUAD CITIES NUCLEAR POWER STATION, UNITS 1 AND 2 (REPORT 05000254/2021006 AND 05000265/2021006)
Dear Mr. Rhoades:
The NRC has completed its end-of-cycle performance assessment of Quad Cities, Units 1 and 2, reviewing performance indicators (PIs), inspection results, and enforcement actions from January 1, 2021, through December 31, 2021. This letter informs you of the NRCs assessment of your facility during this period and its plans for future inspections at your facility.
The NRC concluded that overall performance at your facility preserved public health and safety.
The baseline inspection program was completed at your facility as defined in Inspection Manual Chapter 2515, Light-Water Reactor Inspection Program - Operations Phase.
The NRC determined the performance at Quad Cities, Units 1 and 2, during the most recent quarter was within the Licensee Response Column, the highest performance category of the NRCs Reactor Oversight Process (ROP) Action Matrix, because all inspection findings had very low safety significance (i.e., Green), and all PIs were within the expected range (i.e., Green).
Therefore, the NRC plans to conduct ROP baseline inspections at your facility.
The enclosed inspection plan lists the inspections scheduled through December 31, 2023.
The NRC provides the inspection plan to allow for the resolution of any scheduling conflicts and personnel availability issues. Routine inspections performed by resident inspectors are not included in the inspection plan. The inspections listed during the last twelve months of the inspection plan are tentative and may be revised. The NRC will contact you as soon as possible to discuss changes to the inspection plan should circumstances warrant any changes.
In response to the COVID-19 public health emergency (PHE), the NRC adjusted inspection plans and schedules in order to safeguard the health and safety of both NRC and licensee staff while still effectively implementing the ROP. While the PHE continues, overall conditions throughout the country support performance of our inspection and oversight activities to return to normal onsite presence by our resident and region-based inspectors and completion of nominal baseline inspection samples. We continue to monitor site-specific conditions and as discussed in our November 2, 2021, memo, Implementation of Inspection Programs Following Re-Entry from the Public Health Emergency for the Reactor Safety Program (ML21295A302), it may be necessary to alter how and when we perform our inspection and oversight activities as we balance the importance of protecting the health and safety of our staff with the need to conduct effective oversight that supports the NRCs critical safety mission. For inspections requiring extensive coordination with offsite organizations, such as evaluated emergency preparedness exercises, NRC guidance and frequently asked questions for security and emergency preparedness can be found here: https://www.nrc.gov/about-nrc/covid-19/security-ep/. Similarly, the NRC has developed guidance if force-on-force inspections cannot be completed as scheduled due to an emergency, such as the COVID-19 PHE. These changes help ensure the health and safety of both NRC and licensee staff while maintaining the NRCs important safety and security mission during the COVID-19 PHE. The attached inspection plan is accurate on the date of issuance but remains subject to change based on approval of potential exemption requests or other changes needed due to changing conditions in the COVID-19 PHE. NRC staff will contact your appropriate regulatory affairs staff in order to coordinate inspection planning and scheduling.
The NRC plans to perform Inspection Procedure (IP) 71003, Post-Approval Site Inspection for License Renewal, at your facility.
All of the NRC inspections that occurred at your facility in 2021 were performed while the operating license was held by Exelon Generation Company, LLC. However, on February 1, 2022, the operating license was transferred to Constellation Energy Generation, LLC (Constellation), as documented in a license amendment (ML22021B660). As such, this letter, and future communications regarding your facility will be addressed to and refer to the licensee as Constellation.
In accordance with Title 10 of the Code of Federal Regulations (10 CFR) 2.390 of the NRCs Rules of Practice, a copy of this letter will be available electronically for public inspection in the NRC Public Document Room or from the Publicly Available Records (PARS) component of NRC's document system (ADAMS). ADAMS is accessible from the NRC Web site at http://www.nrc.gov/reading-rm/adams.html (the Public Electronic Reading Room).
Please contact me at 630-829-9628 with any questions you have regarding this letter.
Sincerely,
/RA/
Kenneth Riemer, Chief Branch 1 Division of Reactor Projects Docket Nos. 05000254, 05000265, and 07200053 License Nos. DPR-29; DPR-30 Enclosure:
Inspection Plan cc: Distribution via LISTSERV